Question

In: Operations Management

You work for Microsoft in their global cell phone group. You have been made project manager...

You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
     You have been given the information in Exhibit 5.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
    Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject “S” supplier specifications. These involve engineering details for how the product will perform.
     The individual components that make up the product are the focus of subproject “D.” Subproject “I” brings all the components together, and a working prototype is built and tested.
     Finally in subproject “V,” suppliers are selected and contracts are negotiated.


Exhibit 5.13: Work Breakdown Structure and Activities for the Cell Phone Design Project

MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P1 2
Overall product specifications P2 P1 1
Hardware P3 P2 3
Software P4 P3 4
Supplier specifications (S)
Hardware S1 P4 4
Software S2 P4 6
Product design (D)
Battery D1 S1 1
Display D2 S1 2
Camera D3 S1 1
Outer cover D4 D1, D2, D3 3
Product integration (I)
Hardware I1 D4 5
User interface I2 D2 3
Software coding I3 I2 3
Prototype testing I4 I1, I3 3
Subcontracting (V)
Suppliers selection V1 S1 ,S2 9
Contract negotiation V2 I4, V1 1


a. Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter "0" wherever required.)

b. Determine the minimum number of weeks for completing the project.


c. Find the activities that are on the critical path for completing the project in the shortest time.

  • P1-P2-P3-P4-S1-D2-D4-I1-I4-V2

  • P1-P2-P3-P4-S1-D1-D4-I1-I4-V2

  • P1-P2-P3-P4-S1-D2-I2-I3-I4-V2

  • P1-P2-P3-P4-S2-V1-V2

Solutions

Expert Solution

Solution:

Network Diagram:

a) Start and Finish Times for each activity

Start Duration Early Start Early Finish Late Start Late Finish Float
P1 2 0 2 0 2 0
P2 1 2 3 2 3 0
P3 3 3 6 3 6 0
P4 4 6 10 6 10 0
S1 4 10 14 10 14 0
S2 6 10 16 12 18 2
D1 1 14 15 15 16 1
D2 2 14 16 14 16 0
D3 1 14 15 15 16 1
D4 3 16 19 16 19 0
I1 5 19 24 19 24 0
I2 3 16 19 18 21 2
I3 3 19 22 21 24 2
I4 3 24 27 24 27 0
V1 9 16 25 18 27 2
V2 1 27 28 27 28 0

b) Minimum number of weeks for completing the project:

Shortest Duration for project completion is the critical path duration. Activities lying on critical path i.e P1,P2,P3,P4,S1,D2,D4,I1,I4,V2. Critical path is P1-P2-P3-P4-S1-D2-D4-I1-I4-V2 with duration 28 days.

Minimum number of weeks for completing the project is 28 days

c) Activities on critical path for completing the project in shortes duration is : Option A) P1-P2-P3-P4-S1-D2-D4-I1-I4-V2

(Explained in part b)


Related Solutions

(Case: Global Treps) You have been selected as the project manager for the Global Treps project....
(Case: Global Treps) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths are your organizational...
You have been assigned to work as a project manager on a very important project that...
You have been assigned to work as a project manager on a very important project that requires significant funding. There are several options to consider. Being new to the organisation, you have very limited knowledge of the organisational dynamics, industry and funding preferences. As a project manager, what do you think your duties are on this project? Name a few essential steps and activities you will need to do to effectively perform your job.
Assume you are a project manager at JCDecaux and have been assigned to work with the...
Assume you are a project manager at JCDecaux and have been assigned to work with the city of Lyon to implement this physical, organizational, and social change. What are the practical and philosophical implications of this work?
Assume you are a senior manager of a cell phone provider such as TELUS, Rogers or...
Assume you are a senior manager of a cell phone provider such as TELUS, Rogers or Bell. How might your (cell phone provider) costs of production be affected in the short-run and long-run? (approx. 230 words)
As a programmer in a java project, you have been asked by your project manager to...
As a programmer in a java project, you have been asked by your project manager to describe the most efficient way to store the following assigned numbers 10,20,30,1000,200,350 for an operation which involves on calculation such as sum and average.
Suppose that you have been appointed the project manager for a project to develop an online...
Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: Patient registration Patient login Book first available appointment with any doctor Book an appointment at a time of the patient’s choosing with a doctor of their choice. What development methodologies should you consider? How would you stage the work for each...
Suppose that you have been appointed the project manager for a project to develop an online...
Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: Patient registration Patient login Book first available appointment with any doctor Book an appointment at a time of the patient’s choosing with a doctor of their choice. a. What development methodologies should you consider? How would you stage the work for...
As a newly hired manager of a company that provides cell phone service, you want to...
As a newly hired manager of a company that provides cell phone service, you want to determine the percentage of adults in your state who live in a household with cell phones and no land-line phones. How many adults must you survey? Assume that you want to be 90% confident that the sample percentage is within 4 percentage points of the true population percentage. In a test of effectiveness of garlic for lowering cholesterol, 47 subjects were treated with Garlicin,...
You have been appointed as the Project Manager for a New Product Launch Project by your...
You have been appointed as the Project Manager for a New Product Launch Project by your company. You must prepare a set of documents for the project kick-off meeting coming up next month. Task 1: Prepare a Project Charter for the New Product Launch Project (according to the choice of your product as explained above). Please use the Project Charter template given below Name of the Project Background [Why is the project being undertaken? Describe an opportunity or problem that...
Question 1 Suppose that you have been appointed the project manager for a project to develop...
Question 1 Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: • Patient registration • Patient login • Book first available appointment with any doctor • Book an appointment at a time of the patient’s choosing with a doctor of their choice. What development methodologies should you consider? How would...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT