In: Operations Management
You work for Microsoft in their global cell phone group. You
have been made project manager for the design of a new cell phone.
Your supervisors have already scoped the project so you have a list
showing the work breakdown structure and this includes major
project activities. You must plan the project schedule and
calculate project duration. Your boss wants the schedule on his
desk tomorrow morning!
You have been given the information
in Exhibit 5.13. It includes all the activities required in the
project and the duration of each activity. Also, dependencies
between the activities have been identified. Remember that the
preceding activity must be fully completed before work on the
following activity can be started.
Your project is divided into five major
subprojects. Subproject “P” involves developing specifications for
the new cell phone. Here decisions related to such things as
battery life, size of the phone, and features need to be made.
These details are based on how a customer uses the cell phone.
These user specifications are redefined in terms that have meaning
to the subcontractors that will actually make the new cell phone in
subproject “S” supplier specifications. These involve engineering
details for how the product will perform.
The individual components that make
up the product are the focus of subproject “D.” Subproject “I”
brings all the components together, and a working prototype is
built and tested.
Finally in subproject “V,” suppliers
are selected and contracts are negotiated.
Exhibit 5.13: Work Breakdown Structure and Activities for the Cell
Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES | ACTIVITY IDENTIFICATION | DEPENDENCY | DURATION (WEEKS) | |
Product Specifications (P) | ||||
Market research | P1 | — | 2 | |
Overall product specifications | P2 | P1 | 1 | |
Hardware | P3 | P2 | 3 | |
Software | P4 | P3 | 4 | |
Supplier specifications (S) | ||||
Hardware | S1 | P4 | 4 | |
Software | S2 | P4 | 6 | |
Product design (D) | ||||
Battery | D1 | S1 | 1 | |
Display | D2 | S1 | 2 | |
Camera | D3 | S1 | 1 | |
Outer cover | D4 | D1, D2, D3 | 3 | |
Product integration (I) | ||||
Hardware | I1 | D4 | 5 | |
User interface | I2 | D2 | 3 | |
Software coding | I3 | I2 | 3 | |
Prototype testing | I4 | I1, I3 | 3 | |
Subcontracting (V) | ||||
Suppliers selection | V1 | S1 ,S2 | 9 | |
Contract negotiation | V2 | I4, V1 | 1 | |
a. Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter "0" wherever required.)
b. Determine the minimum number of weeks for completing the project.
c. Find the activities that are on the critical
path for completing the project in the shortest time.
P1-P2-P3-P4-S1-D2-D4-I1-I4-V2
P1-P2-P3-P4-S1-D1-D4-I1-I4-V2
P1-P2-P3-P4-S1-D2-I2-I3-I4-V2
P1-P2-P3-P4-S2-V1-V2
Solution:
Network Diagram:
a) Start and Finish Times for
each activity
Start | Duration | Early Start | Early Finish | Late Start | Late Finish | Float |
P1 | 2 | 0 | 2 | 0 | 2 | 0 |
P2 | 1 | 2 | 3 | 2 | 3 | 0 |
P3 | 3 | 3 | 6 | 3 | 6 | 0 |
P4 | 4 | 6 | 10 | 6 | 10 | 0 |
S1 | 4 | 10 | 14 | 10 | 14 | 0 |
S2 | 6 | 10 | 16 | 12 | 18 | 2 |
D1 | 1 | 14 | 15 | 15 | 16 | 1 |
D2 | 2 | 14 | 16 | 14 | 16 | 0 |
D3 | 1 | 14 | 15 | 15 | 16 | 1 |
D4 | 3 | 16 | 19 | 16 | 19 | 0 |
I1 | 5 | 19 | 24 | 19 | 24 | 0 |
I2 | 3 | 16 | 19 | 18 | 21 | 2 |
I3 | 3 | 19 | 22 | 21 | 24 | 2 |
I4 | 3 | 24 | 27 | 24 | 27 | 0 |
V1 | 9 | 16 | 25 | 18 | 27 | 2 |
V2 | 1 | 27 | 28 | 27 | 28 | 0 |
b) Minimum number of weeks for completing the project:
Shortest Duration for project completion is the critical path duration. Activities lying on critical path i.e P1,P2,P3,P4,S1,D2,D4,I1,I4,V2. Critical path is P1-P2-P3-P4-S1-D2-D4-I1-I4-V2 with duration 28 days.
Minimum number of weeks for completing the project is 28 days
c) Activities on critical path for completing the project in shortes duration is : Option A) P1-P2-P3-P4-S1-D2-D4-I1-I4-V2
(Explained in part b)