In: Finance
IRR AND NPV
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:
0 | 1 | 2 | 3 | 4 |
Project S | -$1,000 | $880.44 | $260 | $10 | $15 |
Project L | -$1,000 | $5 | $260 | $380 | $819.40 |
The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
Project S | |||||
Discount rate | 0.09 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1000 | 880.44 | 260 | 10 | 15 |
Discounting factor | 1 | 1.09 | 1.1881 | 1.295029 | 1.4115816 |
Discounted cash flows project | -1000 | 807.7431 | 218.8368 | 7.721835 | 10.626378 |
NPV = Sum of discounted cash flows | |||||
NPV Project S = | 44.93 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
Project L | |||||
Discount rate | 0.09 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1000 | 5 | 260 | 380 | 819.4 |
Discounting factor | 1 | 1.09 | 1.1881 | 1.295029 | 1.4115816 |
Discounted cash flows project | -1000 | 4.587156 | 218.8368 | 293.4297 | 580.48362 |
NPV = Sum of discounted cash flows | |||||
NPV Project L = | 97.34 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
Project S | |||||
IRR is the rate at which NPV =0 | |||||
IRR | 0.129000702 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1000 | 880.44 | 260 | 10 | 15 |
Discounting factor | 1 | 1.129001 | 1.274643 | 1.439072 | 1.6247137 |
Discounted cash flows project | -1000 | 779.8401 | 203.9787 | 6.948921 | 9.2323957 |
NPV = Sum of discounted cash flows | |||||
NPV Project S = | 0.000148002 | ||||
Where | |||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
IRR= | 12.90% | ||||
Project L | |||||
IRR is the rate at which NPV =0 | |||||
IRR | 0.121000757 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1000 | 5 | 260 | 380 | 819.4 |
Discounting factor | 1 | 1.121001 | 1.256643 | 1.408697 | 1.5791509 |
Discounted cash flows project | -1000 | 4.4603 | 206.9005 | 269.7527 | 518.88646 |
NPV = Sum of discounted cash flows | |||||
NPV Project L = | 4.2803E-06 | ||||
Where | |||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
IRR= | 12.10% | ||||
Project L has higher NPV, IRR is 12.1%