IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...

IRR AND NPV

A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:

0 1 2 3 4
Project S -$1,000 $896.48 $240 $15 $10
Project L -$1,000 $0 $240 $400 $801.23

The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.

%

A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:

0 1 2 3 4
Project X -$1,000 $110 $320 $430 $700
Project Y -$1,000 $1,100 $90 $50 $55

The projects are equally risky, and their WACC is 8%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.

%

Solutions

Expert Solution


Related Solutions

IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $872.52 $260 $15 $10 Project L -$1,000 $0 $250 $380 $811.10 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $882.76 $260 $5 $5 Project L -$1,000 $0 $250 $400 $775.11 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $885.37 $250 $15 $15 Project L -$1,000 $5 $240 $380 $844.53 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $896.53 $250 $5 $5 Project L -$1,000 $10 $260 $380 $821.65 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
(IRR and NPV) A company is analyzing two mutually exclusive projects, S and L, with the...
(IRR and NPV) A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $885.37 $250 $15 $15 Project L -$1,000 $10 $240 $380 $842.17 The company's WACC is 8.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. ______%
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $884.70 $260 $15 $5 Project L -$1,000 $0 $240 $380 $846.86 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $877.09 $250 $5 $10 Project L -$1,000 $10 $260 $420 $744.72 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L,...
Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $898.26 $240 $5 $10 Project L -$1,000 $5 $250 $380 $827.29 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $868.78 $260 $15 $10 Project L -$1,000 $5 $240 $380 $812.00 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. ___%
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $885.70 $250 $5 $15 Project L -$1,000 $5 $250 $380 $813.38 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.   %