Question

In: Accounting

An engineering company which uses job costing to attribute costs to individual products and services provided...

An engineering company which uses job costing to attribute costs to individual products and services provided to its customers has began the preparation of its fixed production overhead cost budget for 2017.

Cost has been identified as follows:

Machining Assembly Finishing Stores Maintenance

K’000 K’000 K’000 K’000 K’000

Apportioned cost 6,000 2,500 1,500 1,000 800

The stores and maintenance departments are production department and provide services as follows:

Machining Assembly Finishing Stores Maintenance Stores 40% 30% 20% - 10%

Maintenance 55% 20% 20% 5% - T

he number of machine and labour hours budgeted for 2018 is:

Machining Assembly Finishing

Machine 50,000 4,000 5,000

Labour hours 10,000 30,000 20,000

Required: (a) Calculate appropriate overhead absorption rates for each production department for 2017.

(b) Prepare a quotation for job K34 to be commenced early in 2017 assuming it has:

Direct materials Costing K24,000

Direct labour Costing K15,000

And requires:

Machine Labour

Machining department 45 10

Asembly 5 15

Finishing department 4 12

Add that profit is 20% of selling price

Solutions

Expert Solution

a)

repeated distribution method

Machining K’000 Assembly K’000 Finishing K’000 Stores K’000 Maintenance K’000
apportioned cost 6000 2500 1500 1000 800
reapportion store 400 300 200 -1000 100
subtotal 6400 2800 1700 0 900
reapportion maintenance
495
180 180 45 -900
subtotal 6895 2980 1880 45 0
reapportion store 18 13.5 9 -45 4.5
sub total 6913 2993.5 1889 0 4.5
reapportion maintenance 2.48 1 1 0 -4.5
total apportioned cost 6915.48 2994.5 1890 0 0

note: we reapportion cost of store and maintenance as cost of store/ maintenance and multiply with percentage of each other departments for example reapportion store is deducting amount from store and proportionate to other department on the basis of percentage of cost attributable to those departments.

now we have to find oar, oar are based on machine hour for some department and labour hour for some other department. we look whichever is higher, machine hour or labour hour for each department and take that as budgeted hour.

for machining department:

oar=budgeted overhead/budgeted hours

machine hours=50000 hours

labour hours=10000 hours

budgeted overhead =K 6915480

oar= 6915480/50000= K138.31 per machine

for assembly department:

oar=budgeted overhead/budgeted hours

machine hours=4000 hours

labour hours=30000 hours

budgeted overhead =K 2994500

oar= 2994500/30000=K 99.82 per labour hour

for finishing department:

oar=budgeted overhead/budgeted hours

machine hours=5000 hours

labour hours=20000 hours

budgeted overhead = K1890000

oar= 1890000/20000= K94.5 per labour hour

note: if a department use more on labour hours/ machine hours it will take as budgeted hours, we assume production overhead do more in that.

b)   

job quotation for job k34

K

direct materials 24000

direct labours 15000

prime cost 39000

production overhead:

machining department 4510

assembly department 515

finishing department 412

total cost of job k34 44437

profit margin 20% 11109.25   

selling price 55546.25

workings:

calculations of profit margin and selling price

if profit margin is 20%, sp is 100 % and cost is 80%

selling price=100%* cost /80%

=K44437*100%/80%

selling price=K55546.25

profit =K55546.25*20%=K11109.25


Related Solutions

An engineering company which uses job costing to attribute costs to individual products and services provided...
An engineering company which uses job costing to attribute costs to individual products and services provided to its customers has began the preparation of its fixed production overhead cost budget for 2017. Cost has been identified as follows: Machining Assembly Finishing Stores Maintenance K’000 K’000 K’000 K’000 K’000 Apportioned cost 6,000 2,500 1,500 1,000 800 The stores and maintenance departments are production department and provide services as follows: Machining Assembly Finishing Stores Maintenance Stores 40% 30% 20% - 10% Maintenance...
Sterling Products Company uses a job- order costing system. The company incurred the following manufacturing costs...
Sterling Products Company uses a job- order costing system. The company incurred the following manufacturing costs during March: a. Purchased materials on credit,$58,800. b. Issued materials to production as follows: direct,$51,000; indirect,$111,300. c. Incurred factory wages,$59,400. d. Allocated factory wages to production as follows: direct,$45,000;indirect,$14,900. e. incurred factory overhead costs on account,$2,500. f. Recognized other factory overhead costs as follows: depreciation of equipment,$4,00; depreciation of building,$5,000;expired insurance,$600; accrued property taxes, $1,800. g. Applied factory overhead to production,$32,500. h. completed jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that 170,000 machine-hours would be required for the periods estimated level of production. The company also estimated $212,500 of fixed manufacturing overhead expenses for the coming period and variable manufacturing overhead of $1.50 per machine hour. Required: 1. Compute the company’s predetermined overhead rate. 2. Assume that during the year of...
Avid Assemblers uses normal job-order costing to assign costs to products. The company assembles and packages...
Avid Assemblers uses normal job-order costing to assign costs to products. The company assembles and packages 25 different products according to customer specifications. Products are worked on in batches of 20 to 40 units. Each batch is given a job number. On October 1, the company had the following balances: Raw materials $ 9,800 Work in process 65,847 Finished goods 30,640 Work in process consisted of the following jobs: Job 22 Job 24 Job 25 Direct materials $  6,200 $  5,190 $  4,800...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,200,000 $ 1,440,000 $ 1,680,000 Fixed overhead costs 612,000 612,000 612,000 Total overhead $ 1,812,000 $ 2,052,000 $ 2,292,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,050,000 $ 1,260,000 $ 1,470,000 Fixed overhead costs 684,000 684,000 684,000 Total overhead $ 1,734,000 $ 1,944,000 $ 2,154,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 900,000 $ 1,080,000 $ 1,260,000 Fixed overhead costs 630,000 630,000 630,000 Total overhead $ 1,530,000 $ 1,710,000 $ 1,890,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 900,000 $ 1,080,000 $ 1,260,000 Fixed overhead costs 702,000 702,000 702,000 Total overhead $ 1,602,000 $ 1,782,000 $ 1,962,000 The expected volume is 180,000 direct...
a Kansas Company uses a job costing accounting system for its production costs. The company uses...
a Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,050,000 $ 1,260,000 $ 1,470,000 Fixed overhead costs 594,000 594,000 594,000 Total overhead $ 1,644,000 $ 1,854,000 $ 2,064,000 The expected volume is 180,000...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT