Question

In: Math

A company manufactures x units of Product A and y units of Product B, on two...

A company manufactures x units of Product A and y units of Product B, on two machines, I and II. It has been determined that the company will realize a profit of $2/unit of Product A and a profit of $4/unit of Product B. To manufacture a unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture a unit of Product B requires 9 min on Machine I and 4 min on Machine II. There are 5 hr of machine time available on Machine I and 3 hr of machine time available on Machine II in each work shift. How many units of each product should be produced in each shift to maximize the company's profit?

(x, y) =



What is the optimal profit? (Round your answer to the nearest whole number.)
$

Solutions

Expert Solution

Let x units of Product A and y units of Product B be manufactured in each shift for optimal profit.

Manufacturing of x units of Product A will require 6x min on Machine I and 5x min on Machine II.

Manufacturing of y units of Product B will require 9y min on Machine I and 4y min on Machine II.

Since 5 hr of machine time is on Machine I in each work shift, hence 6x+9y ≤ 5*60 or, 6x+9y ≤ 300 or, 2x+3y ≤ 100…(1).

Also, since 3 hr of machine time available on Machine II in each work shift, hence 5x+4y ≤ 3*60 or, 5x+4y ≤ 180…(2)

The company’s profit per shift is P(x,y) = 2x+4y.

We have to maximize P(x,y) subject to the constraints (1) and (2).

A graph of the lines 2x+3y = 100 (in red) and 5x+4y= 180 ( in blue) is attached. The feasible region is on and below both the lines in the 1st quadrant ( as both xz and y cannot be negative).

The two lines intersect at the point (20,20). Here, both the constraints are satisfied. Thus, 20 units of each product should be produced in each shift to maximize the company's profit.

The company’s optimal profit is $ (2*20+4*20) = $ 120 per shift.


Related Solutions

A company manufactures x units of Product A and y units of Product B, on two...
A company manufactures x units of Product A and y units of Product B, on two machines, I and II. It has been determined that the company will realize a profit of $2/unit of Product A and a profit of $6/unit of Product B. To manufacture a unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture a unit of Product B requires 9 min on Machine I and 4 min on...
A company manufactures x units of Product A and y units of Product B, on two...
A company manufactures x units of Product A and y units of Product B, on two machines, I and II. It has been determined that the company will realize a profit of $3/unit of Product A and a profit of $6/unit of Product B. To manufacture a unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture a unit of Product B requires 9 min on Machine I and 4 min on...
Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company...
Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $788,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 238,800 12,000 MHs...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool   Activity Measure   Estimated Overhead Cost   Expected Activity Machining   Machine-hours   $   242,400   12,000   MHs...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:    Activity Cost Pool   Activity Measure   Estimated Overhead Cost   Expected Activity Machining   Machine-hours   $   200,000   10,000  ...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 203,000 10,000 MHs...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 216,700 11,000...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Using the ABC system, what percentage of the Machine Setups is assigned to Product Y and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT