In: Operations Management
Rocky Mountain Tire Center sells 5,000 go-cart tires per year. The ordering cost for each order is 35, and the holding cost is 30% of the purchase price of the tires per year. The purchase price is 25 per tire if fewer than 200 tires are ordered, 18 per tire if 200 or more, but fewer than 5,000, tires are ordered, and 17 per tire if 5,000 or more tires are ordered.
a) How many tires should Rocky Mountain order each time it places an order?
Rocky Mountain's optimal order quantity is __________units
b) What is the total cost of ordering optimal order size with this order quantity, annually?
Since the holding cost varies with Price of the tire, we will have to find Economic order quantity for each price as shown below:
Annual Demand = D = 5000 tires
Ordering cost = S = 35
Holding cost = 30%
For Price P = 25,
Holding cost = 30% * 25 =H1 = 7.5
Economic order quantity EOQ =
=
= 216.02 = 216 tires
This quantity > 200 tires which is the maximum limit for P = 25. Hence, this EOQ is not feasible for < 200 tires, P = 25. Hence, the maximum quantity that can be ordered for P = 25 is 200 tires
For Price P = 18,
Holding cost = 30% * 18 =H2 = 5.4
Economic order quantity EOQ =
=
= 254.59 = 255 tires
This quantity > 200 tires and < 5000 which is within limit for P = 18. Hence, this EOQ is feasible for P = 18
For Price P = 17,
Holding cost = 30% * 17 =H3 = 5.1
Economic order quantity EOQ =
=
= 261.97 = 262 tires
This quantity < 5000 which is outside limit for P = 17 where Q required > 5000. Hence, this EOQ is not feasible for P = 17. Minimum quantity to be ordered = 5000 units
Hence,
Option 1: For P = 25, Q = 200
Option 2: P = 18, Q = 255
Option 3: P = 17, Q = 5000
We find total cost each option:
Option 1:
Total cost = Ordering cost + Holding cost + Purchase cost =
=
= 875 + 750 + 125,000 = $1,26,625
Option 2:
Total cost = Ordering cost + Holding cost + Purchase cost =
=
= 686.27 + 688.5 + 90,000 = $91,374.77
Option 3:
Total cost = Ordering cost + Holding cost + Purchase cost =
=
= 35 + 12,750 + 85,000 = $97,785
As seen from above, tghe lowest cost is for Q = 255 units
Hence,
a) Rocky Mountain's optimal order quantity is 255 units
b) The total cost of ordering optimal order size with this order quantity, annually = $91,374.77
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!