Question

In: Finance

  Ranking is an important consideration when projects are mutually exclusive or when capital rationing is necessary....

  Ranking is an important consideration when projects are mutually exclusive or when capital rationing is necessary. When projects are mutually exclusive, ranking enables the firm to determine which project is best from a financial standpoint. When capital rationing is necessary, ranking projects will provide a logical starting point for determining what group of projects to accept. However, there are instances wherein Financial Managers are faced with conflicting rankings using NPV and IRR. It is difficult to choose one approach over the other, because the theoretical and practical strengths of the approaches differ. Interpret both NPV and IRR techniques by highlighting its respective strengths and weaknesses in both theoretical and practical dimensions

Solutions

Expert Solution

NPV and IRR are both capital budget evaluation technique used by companies across the world in their project evaluation. Both techniques have their own strength and weakness. NPV is a more widely used approach than IRR. The focus of NPV is on finding how much value is being added to the firm, if the project has positive NPV then the project is said to be creating value for the company. The benefit of NPV is also that it does consider the time value of money concept and is sensitive to the change in the required rate. The NPV does consider all the cash flows occurring from the project. The weakness of the NV method lies in the fact that the cash flow and the required rate are estimated by the managers so the efficiency of the NPV lies in the input. The IRR method is quite simple to use and it is used in comparative way. We calculate the IRR of the project and then compare it with the required rate on the project, if the project IRR is greater than the required rate, we accept the project. The disadvantage of the IRR method is that with multiple cash inflows and outflows, the number of IRR will also increase and making it slightly complicated. It also assumes that the cash flow is being reinvested at the IRR which is not always a feasible thing.


Related Solutions

If there is no capital rationing problem, which of the following mutually exclusive projects should be...
If there is no capital rationing problem, which of the following mutually exclusive projects should be accepted? Project A: NPV = $8,000; NINV = $55,000 Project B: NPV = $11,000; NINV = $110,500 Question options: Neither A nor B A B Both A and B D&D, Inc., plans to build a new toll way. The cost (NINV) of the project is expected to be $2.1 billion. Net cash inflows are expected to equal $351 million per year. How many years...
What is capital rationing? How capital budgeting projects are chosen when capital rationing exist? Explain.
What is capital rationing? How capital budgeting projects are chosen when capital rationing exist? Explain.
what is IRR...what are the problem related to ranking mutually exclusive projects ts based on IRR...
what is IRR...what are the problem related to ranking mutually exclusive projects ts based on IRR as the investment criteria
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. If r = 10%, which project should be selected under the NPV method? b. If r = 20%, which project should be selected under the NPV method? c. Calculate each project’s PI...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. Calculate each project’s payback (PB) period if r = 10% (up to 2 decimal places). Which project should be accepted? b. Calculate each project’s discounted payback (DPB) period if r = 10%...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
Simson Berhad has three mutually exclusive projects under consideration. The expected cash flows are given in...
Simson Berhad has three mutually exclusive projects under consideration. The expected cash flows are given in the following table. The minimum required rate of return on any project chosen by Simson bhd is 10.5%. Project A Project B Project C Initial Investment RM 484m 682m 467m Years Cash Flows RM in million 1 128 150 95 2 241 265 239 3 115 246 216 4 105 227 96 5 95 94 53 6 15 26 12 Environment restoration cost 50...
Simson Berhad has three mutually exclusive projects under consideration. The expected cash flows are given in...
Simson Berhad has three mutually exclusive projects under consideration. The expected cash flows are given in the following table. The minimum required rate of return on any project chosen by Simson bhd is 10.5%. Project A Project B Project C Initial Investment RM 484m 682m 467m Years Cash Flows RM in million 1 128 150 95 2 241 265 239 3 115 246 216 4 105 227 96 5 95 94 53 6 15 26 12 Environment restoration cost 50...
The following 3 mutually exclusive projects are under consideration. Use Incremental IRR to determine which project...
The following 3 mutually exclusive projects are under consideration. Use Incremental IRR to determine which project should be undertaken if MARR = 18%. year Proj. A Projc. B Proj. C 0 $-500,000 $-350,000 $-700,000 1 $200,000 $100,000 $300,000 2 $200,000 $150,000 $300,000 3 $250,000 $200,000 $300,000 4 $250,000 $250,000 $300,000
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT