Question

In: Finance

Case 2: Evaluate a project with a $25,000 startup cost and annual ongoing costs of $2,500....

Case 2: Evaluate a project with a $25,000 startup cost and annual ongoing costs of $2,500. Cash flows in the first year are estimated to be $1,500 in the first year, $5,500 in the second year, $6,700 in the third year, $9,300 in the fourth year, and $11,500 in the fifth and final year. There is also equipment that is estimated to have a $20,000 salvage value. Assume that the final cash flows and the equipment salvage happen in the same period.
1. Use the NPV function to help calculate the Net Present Value of the project in Case 2 (NPV plus the startup cost[a negative number]) Use 12% as your required return/cost of capital for Case 2
2. Calculate the present value of each cash flow and add the values together. Did the answer match your answer in Q6?
3. Use the XIRR function to calculate the Internal Rate of Return for the project in Case 2.  Use today's date as the start date T0, and the same date a year later for T1 and so on.
4. What required rate/cost of capital would make you indifferent to the project in Case 1 and Case 2? (What rate makes the Net Present Value equal?
5. What is the Discounted Payback Period for Case 2?
6: Using the base required return/cost of capital for cases 1 and 2, which project do you prefer and why?

Solutions

Expert Solution

NPV = Present value of Gross Earnings – Net Cash Investment NPV can be found out from the following formula:

NPV= A1/(1+ r)^1 + A2/ (1 + r)^2 + A3 (1 + r)^3 + …..An/ (1+r)^n – C

Where A1, A2, A3 etc. are the cash inflows at the end of first, second and third year respectively

n = Expected life of investment proposals;

r = Rate of discount which is equal to the cost of capital;

С = Present value of costs.

Initial Investment $ (25,000.00)
Annual Costs $   (2,500.00)
Cash Flow in 1st year $      1,500.00
Cash Flow in 2nd year $      5,500.00
Cash Flow in 3rd year $      6,700.00
Cash Flow in 4th year $      9,300.00
Cash Flow in 5th year $   11,500.00
Equipment Salvage Value $   20,000.00
Cost of Capital 12%
t0 t1 t2 t3 t4 t5
Cash Flows $ (25,000.00) $ (2,500.00) $ (2,500.00) $ (2,500.00) $ (2,500.00) $ (2,500.00)
$   1,500.00 $   5,500.00 $   6,700.00 $   9,300.00 $ 11,500.00
$ 20,000.00
Net Cash Flow in the year $ (25,000.00) $ (1,000.00) $   3,000.00 $   4,200.00 $   6,800.00 $ 29,000.00

1.

So NPV = NPV= -1000/(1+ 12%)^1 + 3000/ (1 + 12%)^2 + 4200 (1 + 12%)^3 + 6800 (1+12%)^4 + 29000 (1+12%)^5 – 25000

NPV = $265.10

2.

PV of Cash Flows = -1000/(1+ 12%)^1 + 3000/ (1 + 12%)^2 + 4200 (1 + 12%)^3 + 6800 (1+12%)^4 + 29000 (1+12%)^5

PV of Cash Flows = $ (892.86) + $2,391.58 + $2,989.48 + $4,321.52 + $16,455.38 = $25,265.10

3.

IRR can be measured as:

A1/ (1+ r) 1 + A2/ (1 + r) 2 + A3 (1 + r) 3 + …..An/ (1+r) n-C=0

Where, A1, A2 A3, etc. are the cash inflows at the end of the first, second and third year respectively. We have to measure the Rate r with this formula.

So in our problem:

-1000/(1+ r)^1 + 3000/ (1 + r)^2 + 4200 (1 + r)^3 + 6800 (1 + r)^4 + 29000 (1 + r)^5 – 25000 = 0

Using the XIRR function in excel we get 12%

t0 t1 t2 t3 t4 t5
Cash Flows $ (25,000.00) $ (2,500.00) $ (2,500.00) $ (2,500.00) $ (2,500.00) $ (2,500.00)
$   1,500.00 $   5,500.00 $   6,700.00 $   9,300.00 $ 11,500.00
$ 20,000.00
Net Cash Flow in the year $ (25,000.00) $ (1,000.00) $   3,000.00 $   4,200.00 $   6,800.00 $ 29,000.00
Discounted Cash Flows $     (892.86) $   2,391.58 $   2,989.48 $   4,321.52 $ 16,455.38
Date of cash flows assumed 1/1/2010 1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
PV of Cash Flows $25,265.10
IRR 12%

5.

Discounted Payback Period helps us to understand when the initial investment cost will be recovered. Here we use the discounted cash flows to check the same.

Seeing the data in the above table we can see that by the 4th year-end Cash Flows amount to $8809.72. So the Payback Period lies somewhere between the 4th and 5th years.


Related Solutions

Evaluate a project that has a startup cost of $10,000, a projected cash flow of $3,000...
Evaluate a project that has a startup cost of $10,000, a projected cash flow of $3,000 at the end of the first year, $4,200 the second year, and $6,800 in the third and final year. Use 10% as the required rate/cost of capital 1. Use the XNPV function to calculate the Net Present Value for the project in.  Use today's date as the start date T0, and the same date a year later for T1 and so on. 2. Use the...
A project that costs $2,500 to install will provide annual cash flows of $750 for each...
A project that costs $2,500 to install will provide annual cash flows of $750 for each of the next 5 years. a. Calculate the NPV if the opportunity cost of capital is 10%? (Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV $ b. Is this project worth pursuing? Yes No c. What is the project's internal rate of return IRR? (Do not round intermediate calculations. Round your answer to 2 decimal places.) IRR %
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.   ...
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.    Required: (a) If the required return is 9 percent, what is the NPV for this project?    (b) Determine the IRR for this project. rev: 09_18_2012, 09_26_2017_QC_C
A new piece of equipment costs $25,000. The annual cost of using the equipment is projected...
A new piece of equipment costs $25,000. The annual cost of using the equipment is projected to be $1000. Annual maintenance costs are expected to be $400 the first year, increasing by $75/yr each year after that. The effective annual interest rate is 5%. Using correct equivalence notation, write out (but do not solve) the equation that would be used to find the equivalent annual cost of purchasing the equipment for its 20-year lifespan.
Project A is as follows: $100,000 upfront cost and annual cash flows of $25,000 a year...
Project A is as follows: $100,000 upfront cost and annual cash flows of $25,000 a year for seven years. Project B is as follows: $100,000 upfront cost and cash flow of $20,000 per year for 8 years. what are the payback periods for projects A and B?
Project A is as follows: $100,000 upfront cost and annual cash flows of $25,000 a year...
Project A is as follows: $100,000 upfront cost and annual cash flows of $25,000 a year for seven years. Project B is as follows: $100,000 upfront cost and cash flow of $20,000 per year for 8 years. Project A Payback Period is 4 years and Project B is 5 years. using that data calculate NPV for projects A and B using a 10% discount rate. which project do you pick if they are mutually exclusive? Which do you pick if...
18) You are considering investing in a project that increases annual costs $25,000 by per year...
18) You are considering investing in a project that increases annual costs $25,000 by per year over the project's 5 year life . The project has an initial cost of $ 500,000 and will be depreciated straight - line over 5 years Assume a 32 % tax bracket and a discount rate of 11 % . Suppose the equipment is sold at the end of year 5 for $ 300,000 , pretax . What is the NPV ? a)-$317,,818.44 b)-$455,887.34...
you are considering investing in a project that increases annual costs by $25,000 per year over...
you are considering investing in a project that increases annual costs by $25,000 per year over the project's 5 year life. The project has an initial cost of $500,000 and will be deprciated straight-line over 5 years. Assume a 32% tax bracket and a discount rate of 11%. Suppose the equipment is sold at the end of year 5 for $300,000, pretax. What is the NPV?
a) Explain what is meant by the critical perspective of accounting b) Evaluate the ongoing project...
a) Explain what is meant by the critical perspective of accounting b) Evaluate the ongoing project of the Financial Accounting Standards Board (FASB) and the International Accounting Standards Board (IASB) to converge their conceptual frameworks from a critical perspective. c) Are critical theorists likely to support moves to find a way to measure externalities in seeking to calculate a sustainable profit? d) Would critical theorists support or oppose the development of standards for sustainability reporting.
2)   A proposed project has fixed costs of $25,000 and a depreciation of $8,000 per year....
2)   A proposed project has fixed costs of $25,000 and a depreciation of $8,000 per year. The variable costs are $7 per unit and sales are $9 per unit.       a)   What is the breakeven point in units produced?       b)   What is the breakeven point in dollars of revenue?       c)   If the operating profit at 20,000 units is $7,000. What is the degree of operating leverage?             d)   If sales increase to 22,000 units, what will operating profits...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT