Question

In: Accounting

Actual overhead is $496,000, while budgeted overhead is $598,000. What is the fixed overhead static-budget variance...

  1. Actual overhead is $496,000, while budgeted overhead is $598,000. What is the fixed overhead static-budget variance if 250,000 units are produced and 350,000 are budgeted?
    1. $80,000 favourable
    2. $100,000 unfavourable
    3. $100,000 favourable
    4. $101,000 unfavourable
    5. $102,000 favourable

Solutions

Expert Solution

e. $ 102,000 favourable

Explanation -

Actual overhead = $ 496,000

Budgeted overhead = $ 598,000

Fixed overhead static budget variance =

Budgeted overhead - actual overhead

$ 598,000 - $ 496,000 = $ 102,000 favourable

As actual overhead are less than budgeted overhead, so favourable variance.


Related Solutions

What does a positive and negative fixed overhead budget variance and fixed overhead volume variance mean?...
What does a positive and negative fixed overhead budget variance and fixed overhead volume variance mean? In the answer, ensure to go beyond stating that it is favourable or unfavourable.
Given the information below, What is the total variance in the actual and static budget? DeFleur...
Given the information below, What is the total variance in the actual and static budget? DeFleur manufactures bicycles. The bicycles are manufactured in two divisions. In the framing division, the carbon bicycle frames are manufactured. In the assembly division, the components are assembled to the frame and the bike is ready for sale. There is no market for the unassembled frames and all manufactured frames are transferred to the assembly division. For the purposes of performance evaluation, the framing division...
You are given the following static budget report: Budget            Actual              Variance Unit Sales  &nbsp
You are given the following static budget report: Budget            Actual              Variance Unit Sales                                           10,000               15,000             5,000 F Variable Expenses:     Commissions                                  $30,000 $33,000 $3,000 U     Advertising                                      $1,000 $1,200 $200 U     Travel                                              $10,000 $11,000 $1,000 U     Samples                                          $2,500 $2,300 $200 F Total Variable                                     $43,500 47,500 $4,000 U Fixed Expenses     Rent                                                 $5,000 $5,000 0     Salaries – Sales                               $2,000 $2,000 0     Salaries – Office                              $1,200 $1,200 0     Depreciation                                    $1,500 $1,500 0 Total Fixed                                          $9,700 $9,700             0 Total Expenses $53,200 $57,200 $4,000 U Prepare a flexible budget analysis and explain whether you believe that costs were controlled.  How do the results of...
What is the volume variance in fixed overhead? Is the volume variance in fixed overhead favorable...
What is the volume variance in fixed overhead? Is the volume variance in fixed overhead favorable or unfavorable? Use the following scenario to help with the questions: DeFleur manufactures bicycles. The bicycles are manufactured in two divisions. In the framing division, the carbon bicycle frames are manufactured. In the assembly division, the components are assembled to the frame and the bike is ready for sale. There is no market for the unassembled frames and all manufactured frames are transferred to...
Waterways Corporation is continuing its budget preparations. Waterways had the following static budget and actual overhead...
Waterways Corporation is continuing its budget preparations. Waterways had the following static budget and actual overhead costs for March. WATERWAYS CORPORATION Manufacturing Overhead Budget (Static) For the Month of March Budgeted production in units 123,000 Budgeted costs Indirect materials $6,150 Indirect labor 14,760 Utilities 12,300 Maintenance 8,610 Salaries 43,800 Depreciation 16,100 Property taxes 3,000 Insurance 1,200 Janitorial 1,600 Total budgeted costs $107,520 WATERWAYS CORPORATION Manufacturing Overhead Costs (Actual) For the Month of March Production in units 124,000 Costs Indirect materials...
The sales-volume variance plus or minus the static budget amount results in A static budget variance...
The sales-volume variance plus or minus the static budget amount results in A static budget variance The variable-budget amount An unfavourable/favourable amount The flexible budget amount
Describe an example of how an unfavorable variance between actual and budget amounts in a fixed...
Describe an example of how an unfavorable variance between actual and budget amounts in a fixed static (master) budget can become a favorable variance in a flexible budget report. Also, since flexible budget is more accurate in measuring performance, can company just develop flexible budget without the static budget? Why or why not?
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 7,200 units of product were as follows: Standard Costs Actual Costs Direct materials 9,400 lb. at $5.20 9,300...
Below is the variance report Prior year Item Budget Actual Variance Variance % Actual Days in...
Below is the variance report Prior year Item Budget Actual Variance Variance % Actual Days in time period 31 31 31 Staffed Beds 20 20 20 Patient days 527 498 (29.0) -5.5% 415 Total RN FTEs 45.1 50.1 (5.0) -11.1% 36.7 Revenue: Gross patient revenue $460,450 $441.932 ($18,518) -4.0% $417,883 Personnel Expense: Total salaries and wages $171,920 $192,845 ($20,925) -12.2% $141,552 Benefits $51,576 $52,797 ($1,221) -2.4% $42,466 Total personnel expenses $223,496 $245,642 ($22,146) -9.9% $184,018 Overtime wages % 2.0% 6.1%...
A budget variance occurs when the actual results of your financial activity differ from your budgeted...
A budget variance occurs when the actual results of your financial activity differ from your budgeted projections. Please identify what might be causing you budget variances at the moment. What are some microeconomic factors that could be causing this outcome? What are some macroeconomic factors that could be sources of the variance? What might you change in your financial behaviour, budget, or goals to your improve outcomes?