Question

In: Accounting

Whitley has recently completed work for three clients: Harrison, Barnes, and Tyler. The cost data for...

Whitley has recently completed work for three clients: Harrison, Barnes, and Tyler. The cost data for each of the three jobs are summarized below:

Job Direct Materials Direct Labor Hours Direct Labor Cost
Harrison $ 6,948 55 $ 15,783
Barnes 13,424 94 23,770
Tyler 44,002 125 51,240

Budgeted direct materials cost and direct labor cost for the year are estimated at $515,000 and $730,000, respectively. Direct labor hours are budgeted at 29,000 hours, and total overhead is budgeted at $493,000.

Required:

1. Calculate the total cost of each of the three jobs.

2. Suppose that for the entire year, Whitley used 30,300 labor hours and total actual overhead was $512,000. What is the amount of underapplied or overapplied overhead?

Complete this question by entering your answers in the tabs below.

  • Required 1
  • Required 2

Calculate the total cost of each of the three jobs.

Total Job Cost
Harrison
Barnes
Tyler

Solutions

Expert Solution

Required 1 :-

Calculation of Total cost for each jobs:-

Predetermined rate for overhead = budget OH/Budgeted Labor Hr

= $493,000/29,000

= $17

Total cost for Harison:-

Direct Material = $6,948+

Direct Labor = $15,783+

Overhead Applied ($17*55) $ 935

Total Cost = $23,666

Total cost for Barnes:-

Direct Material = $13,424

Direct Labor = $23,770

Overhead Applied($17*94)= $ 1,598

Total cost = $38,792

Total cost for Tyler:-

Direct Material = $44,002

Direct Labor = $51,240

Overhead Applied($17*125) $ 2,125

Total cost = $97,367

Usually all firms uses normal costing. In normal costing the direct material and direct labor are taken the actual figure because the firm knows how much they spend for material and labor. Overhead is taken on the predetermined rate because the overhead costs are usually calculated for a year not for a particular job. So they are unknown for the until the year end. So firms prefer to use normal costing.

​​​​Required 2 :-

Overhead Applied = $17*30,300 = $515,100

Actual Overhead = $512,000

So,

$515,100 - $512,000

= $3,100 is OVER APPLIED.


Related Solutions

Job 434 was recently completed. The following data have been recorded on its job cost sheet:...
Job 434 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 45,000 Direct labor-hours 630 labor-hours Direct labor wage rate $ 13 per labor-hour Machine-hours 390 machine-hours Number of units completed 3,000 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job.
Barnes Company uses a job order cost system. The following data summarize the operations related to...
Barnes Company uses a job order cost system. The following data summarize the operations related to production for October: October 1 Materials purchased on account, $315,500. 2 Materials requisitioned, $290,100, of which $8,150 was for general factory use. 31 Factory labor used, $489,500, of which $34,200 was indirect. 31 Other costs incurred on account for factory overhead, $600,000; selling expenses, $150,000; and administrative expenses, $100,000. 31 Prepaid expenses expired for factory overhead were $18,000; for selling expenses, $6,000; and for...
Barnes Company uses a job order cost system. The following data summarize the operations related to...
Barnes Company uses a job order cost system. The following data summarize the operations related to production for October: October 1 Materials purchased on account, $635,470. 2 Materials requisitioned, $628,070, of which $74,070 was for general factory use. 31 Factory labor used, $674,350, of which $94,570 was indirect. 31 Other costs incurred on account for factory overhead, $151,200; selling expenses, $228,420; and administrative expenses, $152,810. 31 Prepaid expenses expired for factory overhead were $27,820; for selling expenses, $28,010; and for...
Barnes Company uses a job order cost system. The following data summarize the operations related to...
Barnes Company uses a job order cost system. The following data summarize the operations related to production for October: October 1 Materials purchased on account, $315,500. 2 Materials requisitioned, $290,100, of which $8,150 was for general factory use. 31 Factory labor used, $489,500, of which $34,200 was indirect. 31 Other costs incurred on account for factory overhead, $600,000; selling expenses, $150,000; and administrative expenses, $100,000. 31 Prepaid expenses expired for factory overhead were $18,000; for selling expenses, $6,000; and for...
A game show has a host and three contestants. Suppose the three contestants are Meg, Tyler...
A game show has a host and three contestants. Suppose the three contestants are Meg, Tyler and Ashley. The host and each contestant each have a bag with 3 marbles; one red, one white and one blue. The host will choose a marble from her bag, then Meg will choose a marble from her bag. If Meg’s marble is the same color as the host, then Meg has won and the game is over. If Meg loses, then Tyler will...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 9,000 units, 65% completed 31,635 To Finished Goods, 207,000 units ? Direct materials, 212,000 units @ $1.5 318,000 Direct labor 492,900 Factory overhead 191,685 Bal. ? units, 45% completed ? a. Based on the above data, determine the...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 3,000 units, 75% completed 9,450 To Finished Goods, 69,000 units ? Direct materials, 71,000 units @ $1.8 127,800 Direct labor 93,700 Factory overhead 36,450 Bal., ? units, 35% completed ? Cost per equivalent units of $1.80 for Direct...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 7,000 units, 70% completed 28,210 To Finished Goods, 161,000 units ? Direct materials, 165,000 units @ $2 330,000 Direct labor 363,100 Factory overhead 141,270 Bal. ? units, 60% completed ? a. Based on the above data, determine the...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 6,000 units, 70% completed16,140To Finished Goods, 138,000 units? Direct materials, 141,000 units @ $1.5211,500   Direct labor178,700   Factory overhead69,430   Bal., ? units, 45% completed?   Cost per equivalent units of $1.50 for Direct Materials and $1.80 for Conversion Costs. a....
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 6,000 units, 75% completed 25,500 To Finished Goods, 138,000 units ? Direct materials, 141,000 units @ $1.7 239,700 Direct labor 372,400 Factory overhead 144,860 Bal. ? units, 70% completed ? a. Based on the above data, determine the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT