Briefly describe a work-related or personal project that has been completed. What specific project control steps/methods were/could have been applied to enhance the probability of success? Consider the steps of The Project Control Cycle and various methods for monitoring performance.
Interior Design and Office Space Fitout works (Sample Project)
Project: Fit-out interiors for a shell and core office with 4 meeting rooms, CEO, CFO, CTO Rooms, Pantry, Lobby, Break out Area, Server Rooms, Branding of Common Areas, Total area to be worked 12500 Sqft
PLANNING PHASE
Project Team: Consisted of the following teams. Admin Team, Finance Team, Operations Team.
Project Softwares used: Slack communications, Trello Board and Monday.com
STEPS INVOLVED IN PLANNING PHASE
EXECUTION PHASE
All these software mentioned above has an email triggering facility that can be configured so that each activity is individually reported. For any project to end fast, and efficiently, reporting is an important factor.
CONTROL PHASE
In the control phase, the project manager makes sure that the defined processes are completed according to the break up of the work schedule. It is during this phase the project manager identifies deviations from the initial project planning. For example, during the approval submission phase, the contractor may have skipped (just for example purpose only) the emergency exit and stairways associated with it. This becomes a deviation since the entire drawing needs to redrawn, the project schedule gets affected. Progress entered in the software above should be amended along with the costs associated with it.
The advantages of using the software mentioned above is that, multiple levels of monitoring is possible. For example, the top management can monitor what task the project manager does by having the email trigger or having the supervisory passwords for the platforms mentioned above. Even though the project manager reports the actual progress of the project, based on his inputs, the top management can easily due an audit since they too (if configured) will receive the project updatees.
Corrective actions can easily be suggested to those items if overseen by the project manager itself by the top managment
COMPLETION PHASE.
If managed correctly, and reporting
makes a new task assignment easier for any incomplete or
non-progressive tasks. The project could be completed with
deviations from originals if any by using the software platforms
above. The ultimate objective of the top management as well as the
project manager should be the ability to monitor the task
completion and reporting in the software used. Constant audit of
different tasks needs to be done in the software platforms. The
successful completion of the project depends largely upon the
ability of the management as well as the project manager to manage
the software used properly. If any tasks remain unassigned or not
completed could affect the completion of the project.