In: Accounting
Part 1 : Overhead cost assigned to Product line using Traditional costing system with machine hours as the cost driver:
| Particulars | Home | Work | Total | 
| Machine Hours | 1,000 | 2,100 | 3,100 | 
| Overhead Cost | $66,194 | $139,006 | 205,200 | 
Working Notes:
Home
Overhead Cost = $205,200 * 1,000 machine hours / 3,100 machine hours = $66,194
Work
Overhead Cost = $205,200 * 2,100 machine hours / 3,100 machine hours = $139,006
Part 2 : Production cost per unit using Traditional costing system
| Particulars | Home | Work | 
| Direct Materials | $37 | $69 | 
| Direct Labor | $17 | $36 | 
| Overheads | $100.29 | $278.01 | 
| Total Production cost per unit | $154.29 | $383.01 | 
Workings:
Overhead cost per unit
Home
Overhead cost per unit = $66,194 / 660 units = $100.29 per unit
Work
Overhead cost per unit = $139,006 / 500 units = $278.01 per unit
Part 3 : Harbour's gross margin per unit using traditional costing system
| Particulars | Home | Work | 
| Sales | $350.00 | $571.00 | 
| Less: Production cost per unit | $154.29 | $383.01 | 
| Gross Margin per unit | $195.71 | 187.99 | 
Part 4 : Activity Rate

Part 5 : Overhead cost assigned to Product line using ABC System

Part 6 : Production cost per unit using ABC System
| Particulars | Home | Work | 
| Direct Materials | $37 | $69 | 
| Direct Labor | $17 | $36 | 
| Overheads | $124.70 | $245.80 | 
| Total Production cost per unit | $178.70 | $350.80 | 
Workings:
Overhead cost per unit
Home
Overhead cost per unit = $82,300 / 660 units = $124.70 per unit
Work
Overhead cost per unit = $122,900 / 500 units = $245.80 per unit
Part 7 : Harbour's gross margin per unit using ABC system
| Particulars | Home | Work | 
| Sales | $350.00 | $571.00 | 
| Less: Production cost per unit | $178.70 | $350.80 | 
| Gross Margin per unit | $171.30 | $220.20 | 
Part 8 : Comparison
| Particulars | Home | Work | 
| Gross Margin using Traditional costing system | $195.71 | $187.99 | 
| Gross Margin using ABC system | $171.30 | $220.20 | 
Home
Gross Margin under ABC costing is lesser than the gross margin under traditional costing system by $24.41 ($195.71 - $171.30).
Work
Gross Margin under ABC costing is higher than the gross margin under traditional costing system by $32.21 ($220.20 - $187.99).
All the best...