In: Finance
The City and County of Denver is completing a $45 million renovation of City Park Golf Course. To complete the renovation, the course has been closed to the public for 2.5 years (planned re-opening is Spring 2020). The project updated the course, built a new clubhouse that can accommodate golf and community events, resulted in a “net gain of 500 trees”, and reduced flood risk “for thousands of homes”.[1] All of these updates are expected to provide either increased revenue or reduced costs. Assume the $45 million cost was paid upfront by Denver and the following are the estimated cash receipts and disbursements associated with the project.[1] If the cost of capital is 6%, does the project make sense based on NPV and IRR over a 30-year useful life? Does your finding change if the cost of capital is actually 4%?
Year |
Disbursements ($) |
Receipts ($) |
Net Cash Flow ($) |
0 |
45000000 |
0 |
-45000000 |
1 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
3 |
13000000 |
15500000 |
2500000 |
4 |
13390000 |
15965000 |
2575000 |
5 |
13791700 |
16443950 |
2652250 |
6 |
14205451 |
16937269 |
2731818 |
7 |
14631615 |
17445387 |
2813772 |
8 |
15070563 |
17968748 |
2898185 |
9 |
15522680 |
18507811 |
2985131 |
10 |
15988360 |
19063045 |
3074685 |
11 |
16468011 |
19634936 |
3166925 |
12 |
16962051 |
20223984 |
3261933 |
13 |
17470913 |
20830704 |
3359791 |
14 |
17995040 |
21455625 |
3460585 |
15 |
18534892 |
22099294 |
3564402 |
16 |
19090938 |
22762273 |
3671334 |
17 |
19663666 |
23445141 |
3781474 |
18 |
20253576 |
24148495 |
3894919 |
19 |
20861184 |
24872950 |
4011766 |
20 |
21487019 |
25619138 |
4132119 |
21 |
22131630 |
26387712 |
4256083 |
22 |
22795579 |
27179344 |
4383765 |
23 |
23479446 |
27994724 |
4515278 |
24 |
24183829 |
28834566 |
4650736 |
25 |
24909344 |
29699603 |
4790259 |
26 |
25656625 |
30590591 |
4933966 |
27 |
26426323 |
31508309 |
5081985 |
28 |
27219113 |
32453558 |
5234445 |
29 |
28035686 |
33427165 |
5391478 |
30 |
28876757 |
34429980 |
5553223 |
[
NPV at 6% | -4029578.48 |
NPV at 4% | 9786350.41 |
IRR | 5.33% |
The project has negative NPV at 6% and should not be undertaken. However if the cost of capitral is 4%, the NPV is positive and the project is profitable.
Workings