In: Finance
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$261,103 –$15,350 1 26,600 5,181 2 51,000 8,059 3 51,000 13,055 4 392,000 8,690 Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A? b. What is the payback period for Project B? c. What is the discounted payback period for Project A? d. What is the discounted payback period for Project B? e. What is the NPV for Project A? f. What is the NPV for Project B ? g. What is the IRR for Project A? h. What is the IRR for Project B? i. What is the profitability index for Project A? j. What is the profitability index for Project B?
a | |||||
Project A | |||||
Year | Cash flow stream | Cumulative cash flow | |||
0 | -261103 | -261103 | |||
1 | 26600 | -234503 | |||
2 | 51000 | -183503 | |||
3 | 51000 | -132503 | |||
4 | 392000 | 259497 | |||
Payback period is the time by which undiscounted cashflow cover the intial investment outlay | |||||
this is happening between year 3 and 4 | |||||
therefore by interpolation payback period = 3 + (0-(-132503))/(259497-(-132503)) | |||||
3.34 Years | |||||
b | |||||
Project B | |||||
Year | Cash flow stream | Cumulative cash flow | |||
0 | -15350 | -15350 | |||
1 | 5181 | -10169 | |||
2 | 8059 | -2110 | |||
3 | 13055 | 10945 | |||
4 | 8690 | 19635 | |||
Payback period is the time by which undiscounted cashflow cover the intial investment outlay | |||||
this is happening between year 2 and 3 | |||||
therefore by interpolation payback period = 2 + (0-(-2110))/(10945-(-2110)) | |||||
2.16 Years | |||||
c | |||||
Project A | Discount rate= | 0.06 | |||
Year | Cash flow stream | Cumulative cash flow | Discounting factor | Discounted CF | Cumulative cash flow |
0 | -261103 | -261103 | 1 | -261103 | -261103 |
1 | 26600 | -234503 | 1.06 | 25094.34 | -234503 |
2 | 51000 | -183503 | 1.1236 | 45389.82 | -183503 |
3 | 51000 | -132503 | 1.191016 | 42820.58 | -132503 |
4 | 39200000.00% | 259497 | 1.262477 | 310500.7 | 259497 |
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay | |||||
this is happening between year 3 and 4 | |||||
therefore by interpolation payback period = 3 + (0-(-147798.26))/(162702.46-(-147798.26)) | |||||
3.48 Years | |||||
Where | |||||
Discounting factor =(1 + discount rate)^(corresponding year) | |||||
Discounted Cashflow=Cash flow stream/discounting factor | |||||
d | |||||
Project B | Discount rate= | 0.06 | |||
Year | Cash flow stream | Cumulative cash flow | Discounting factor | Discounted CF | Cumulative cash flow |
0 | -15350 | -15350 | 1 | -15350 | -15350 |
1 | 5181 | -10169 | 1.06 | 4887.736 | -10169 |
2 | 8059 | -2110 | 1.1236 | 7172.481 | -2110 |
3 | 13055 | 10945 | 1.191016 | 10961.23 | 10945 |
4 | 8690 | 19635 | 1.262477 | 6883.294 | 19635 |
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay | |||||
this is happening between year 2 and 3 | |||||
therefore by interpolation payback period = 2 + (0-(-3289.78))/(7671.45-(-3289.78)) | |||||
2.3 Years | |||||
Where | |||||
Discounting factor =(1 + discount rate)^(corresponding year) | |||||
Discounted Cashflow=Cash flow stream/discounting factor | |||||
e | |||||
Project A | |||||
Discount rate | 0.06 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -261103 | 26600 | 51000 | 51000 | 392000 |
Discounting factor | 1 | 1.06 | 1.1236 | 1.191016 | 1.262477 |
Discounted cash flows project | -261103 | 25094.34 | 45389.82 | 42820.58 | 310500.72 |
NPV = Sum of discounted cash flows | |||||
NPV Project A = | 16270246.00% | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
f | |||||
Project B | |||||
Discount rate | 0.06 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -15350 | 5181 | 8059 | 13055 | 8690 |
Discounting factor | 1 | 1.06 | 1.1236 | 1.191016 | 1.262477 |
Discounted cash flows project | -15350 | 4887.736 | 7172.481 | 10961.23 | 6883.2939 |
NPV = Sum of discounted cash flows | |||||
NPV Project B = | 14554.74 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||