Question

In: Accounting

If a previously profitable construction contract being accounted for with the percentage-of-completion method is later projected to be unprofitable, then the Net Loss in that period will be equal to:

If a previously profitable construction contract being accounted for with the percentage-of-completion method is later projected to be unprofitable, then the Net Loss in that period will be equal to:

Select one:

a. All previously recognized Gross Profit on the contract

b. The projected Net Loss on the entire contract

c. All previously recognized Gross Profit plus the percentage of completion times the projected Net Loss on the entire contract

d. All previously recognized Gross Profit on the contract plus the projected Net Loss on the entire contract

e. The projected Net Loss on the entire contract times the percentage of completion.


Solutions

Expert Solution

Answer d is correct,

As per Para 36 of IAS 11 says that "When it is probable that total contract costs will exceed total contract revenue, the expected loss shall be recognised as an expense immediately."

Thus in accordance with Paragraph 36 of IAS 11 Construction Contract The expected loss i.e. The projected Net Loss on the entire contract shall be recognised as an expense immediately. Hence the Net Loss in that period will be The projected Net Loss on the entire contract.

As contract become unprofitable lateron hence we need to reverse the all previously recognized Gross Profit also.

By summing up we get that All previously recognized Gross Profit on the contract plus the projected Net Loss on the entire contract will be the Net Loss in that period.

Answer a is incorrect because we also need to follow paragraph 36 as mentioned above and

Answer b is incorrect because it does not take account of reversal of all previously recognized Gross Profit.

Answer c is incorrect because rather than percentage of completion times the projected Net Loss on the entire contract, as per Paragraph 36 we need to recognize whole expenses.

Answer e is incorrect because it does not take account of reversal of all previously recognized Gross Profit and also rather than percentage of completion times the projected Net Loss on the entire contract, as per Paragraph 36 we need to recognize whole expenses.


Related Solutions

When we formed the construction contract, do we need the margin percentage for the percentage-of-completion method?...
When we formed the construction contract, do we need the margin percentage for the percentage-of-completion method? I am trying to calculate the revenue. I have information about the estimated cost, cost incurred per year, the finalized cost, project years, and margin. However, I am not sure it is necessary. It said that the worker wants to add a margin of % on its cost estimate. Can anyone help me to use an example to explain to me?
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the following should be used in the calculation of the income recognized in the first year? Select one: a. Progress Billings, but not Collections on Progress Billings b. Collections on Progress Billings, but not Progress Billings c. Both Progress Billings and Collections on Progress Billings d. Neither Progress Billings nor Collections on Progress Billings
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method....
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method. It is a 4 year contract that is currently in its second year. The latest estimates of contact costs indicate that the contact will be completed at a profit to the company. Based on this information please answer the following: 1 What theoretical justification is there or the Widjaja Company's use of the percentage-of-completion method 2 Discuss how the progress billings will be accounted...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which began on January 1, 2015 to build a new football stadium with an expected completion date of October 31, 2017. The following table provides information gathered during the construction period. Jim uses the percentage completion method to account for this contract.                                                                                                                                  2015 2016 2017 Construction costs incurred during the year 2,040,000 2,932,500 1,657,500 Estimated costs to complete 3,060,000 1,657,500 0 Billings during the...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for $22,000,000; it was completed in 2019. The following cost data pertain to this contract for the year-ended 2018... Cost incurred during the year: $7,800,000... Estimated costs to complete: $5,200,000. The following cost data pertain to this contract for the year-ended 2019... Cost incurred during the year: $5,600,000... Estimated costs to complete: n/a. If the completed-contract method of accounting was used, the amount of gross...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
In the construction industry, the percentage of completion (POC) method is the most common accounting method....
In the construction industry, the percentage of completion (POC) method is the most common accounting method. Explain what business environments create favorable conditions for a company to use this POC method.
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract for which they would receive $900,000 at completion.... In 2024, they reported a gross profit of 58,440..... 2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion on the basis of kilometres completed. In November 20X9, CCS signed an agreement with the NWT government to build 50 kilometres of new road for a total cost of $40 million. The contract would likely take three years to complete and would start in the spring of 20X10. Over the next three years, 15 kilometres were completed in 20X10,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT