In: Accounting
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1.
Indirect cost
27 weeks – RM 350
26 weeks – RM 270
25 weeks – RM 160
24 weeks – RM 100
12 weeks – RM 70
Table 1 Housing Project Schedule
Activity |
Predecessor |
Normal time |
Normal cost |
Crash cost (slope) |
Maximum crash time |
A |
- |
10 |
40 |
80 |
2 |
B |
- |
8 |
10 |
30 |
3 |
C |
- |
5 |
80 |
40 |
1 |
D |
A |
11 |
50 |
50 |
2 |
E |
C |
15 |
100 |
100 |
4 |
F |
B, D, E |
6 |
20 |
30 |
1 |
*Time unit = 1 week
The Network diagram will be as follows:
In the above diagram each activity is followed by its normal time and maximum crash time in parenthesis.
First we will try to find out the available paths:
Paths | Normal Duration |
---|---|
A-D-F | 27 weeks (10+11+6) |
B-F | 14 weeks (8+6) |
C-E-F |
26 weeks (5+15+6) |
Thus the expected project duration is 27 weeks and the critical path is A-D-F. Now when we want to reduce the duration of the project, we should select activities from the critical path itself. This is because even after crashing we should try to maintain the same path as the critical path. It cannot change. Secondly those activities from the critical path should be selected which have a lower activity cost slope. Activity cost slope is calculated by dividing the difference between Crash cost and Normal cost by difference between the normal time and the crash time. In the question we are already given the Crash cost slope
The following table shows the Activity cost slope of each activity alongwith its Scope for crashing:
Activities | Activity Cost Slope | Scope of Crashing |
---|---|---|
A | 80 | 2 |
B | 30 | 3 |
C | 40 | 1 |
D | 50 | 2 |
E | 100 | 4 |
F | 30 | 1 |
i)Table showing crashing of activities and total cost at each duration:
Crash Decision | Incremental Cost | Revised Normal Duration |
---|---|---|
Crash F by 1 week | 30 | 26 weeks (27-1) |
Crash D by 1 week | 50 | 25 weeks (26-1) |
Crash D by 1 week & Crash C by 1 week |
50 & 40 |
24 weeks (25-1) |
Crash A by 2 weeks & Crash E by 2 weeks |
60 (80*2) & 200 (100*2) |
22 weeks (24-2) |
Note that to reduce the duration to 24 weeks we had to select two activities, D & C. The reason for this is that if D alone was chosen then A-D-F would have no longer remained the critical path but C-E-F. Thus simultaneously we have to crash activity C too so that the A-D-F remains the critical path.
It is not possible to reduce the duration of the project to 12 weeks since the critical path can be reduced maximum to 22 weeks. This is because if you add the scope of crashing of the activities within the critical path which A-D-F it is 5 weeks. Original project duration is 27 days. Thus 27 minus 5 is 22 weeks which is the minimum possible duration of this project.
Duration | Normal Cost | Crash Cost | Indirect Cost | Total Cost |
---|---|---|---|---|
27 weeks | 300 (40+10+80+50+100+20) | Nil | 350 | 650 (300+350) |
26 weeks | 300 (40+10+80+50+100+20) | 30 | 270 | 600 (300+30+270) |
25 weeks | 300 (40+10+80+50+100+20) | 80 (30+50) | 160 | 540 (300+80+160) |
24 weeks | 300 (40+10+80+50+100+20) | 170 (30+50+50+40) | 100 | 570 (300+170+100) |
12 weeks | Not possible | Not possible | Not possible | Not possible |
Thus as can be seen from the above table the optimum cost-time schedule is 25 weeks. At this duration the cost is the minimum.
ii) If the client offers an incentive of 20 per week then we should accept the offer and reduce the duration of the project by 2 weeks thus giving final duration of 25 weeks and the total cost after incentive will be RM500 {540-(20*2)}. Reducing the duration by 2 weeks alone gives the least cost for the project.