In: Finance
Key players of renewable energy generation are assumed to be looking to implement projects to build a green power plant at the CEZ. One such entity, has estimated the annual costs and revenues expected from such a project as shown in the table below:
Time/years |
Revenue/USD |
Cost/USD |
0 |
$ 0 |
$15M |
1 |
$5M |
$3M |
2 |
$16M |
$1M |
3 |
$25 M |
$ 0 |
Required
Using this information, calculate the Net Present Value of the Project at a
10% discount rate.
A bottom-up approach was used to compute the detailed cost for the project.
Give four (4) characteristics of bottom-up estimates.
The entity is currently implementing a similar project oversees and is keen to use it as a benchmark for the CEZ.
From the table below, find the PV, EV, CPI and EAC (assuming that the same
cost performance continues) for one of the activities of the similar project at
month 3.
The activity duration is estimated for 4 months with a budget of $200,000.
$50,000 is planned to be spent each month.
At month 3, determine PV, EV, AC, CPI and EAC.
What can you say about the current cost performance of the project providing
that the CPI remains the same?
Activity Time |
Planned Expenditure |
Money Spent |
Status |
Month 1 |
50,000 |
$50,000 |
100% Complete |
Month 2 |
50,000 |
$ 50,000 |
100% Complete |
Month 3 |
50,000 |
$ 30,000 |
70% Complete |
NPV = 17,997,746.
Estimate at Completion (EAC) for this project - 4 months
Given in the question:
Budget at Completion (BAC) = 200,000
Actual Cost (AC) = 130,000 ==> money spent
Planned Value (PV) = 75% of 200,000 - month 4 - project completion
= 150,000
Earned Value (EV) = 67.5 % of 200,000 = = 135,000
month 3 - 70% completed 70% is what percentage of 25% that is each month project completion is 25% and in 4th month whole project is completed - 100%
month 1 - 25%
month 2 - 25%
month 3 - 17.5 % = 25% * 70%
total = 67.5%
To calculate the EAC, first you have to calculate the Cost Performance Index:
Cost Performance Index (CPI) = EV / AC
= 135,000 / 130,000
= 1.03
=>Cost Performance Index (CPI) = 1.03
Now,
Estimate at Completion (EAC) = BAC / CPI
= 200,000 / 1.03
= 194,174.75
Hence, the Estimate at Completion (EAC) is 194,174.75.
In other words, if the project continues to progress with CPI = 1.03 until the end, you will have to spend 194,174.75 to complete the project.