Question

In: Finance

Key players of renewable energy generation are assumed to be looking to implement projects to build a green power plant at the CEZ

Key players of renewable energy generation are assumed to be looking to implement projects to build a green power plant at the CEZ. One such entity, has estimated the annual costs and revenues expected from such a project as shown in the table below:

Time/years

Revenue/USD

Cost/USD

0

$ 0

$15M

1

$5M

$3M

2

$16M

$1M

3

$25 M

$ 0

Required

Using this information, calculate the Net Present Value of the Project at a
10% discount rate.                                                                          

A bottom-up approach was used to compute the detailed cost for the project.
Give four (4) characteristics of bottom-up estimates.                     

 

The entity is currently implementing a similar project oversees and is keen to use it as a benchmark for the CEZ.

From the table below, find the PV, EV, CPI and EAC (assuming that the same
             cost performance continues) for one of the activities of the similar project at
             month 3.

            The activity duration is estimated for 4 months with a budget of $200,000.
             $50,000 is planned to be spent each month.
             At month 3, determine PV, EV, AC, CPI and EAC.

            What can you say about the current cost performance of the project providing
             that the CPI remains the same?                                                        

                           

Activity Time

Planned Expenditure

Money Spent

Status

Month 1

50,000

$50,000

100% Complete

Month 2

50,000

$ 50,000

100% Complete

Month 3

50,000

$ 30,000

70% Complete

Solutions

Expert Solution

NPV = 17,997,746.

Estimate at Completion (EAC) for this project - 4 months

Given in the question:

Budget at Completion (BAC) = 200,000

Actual Cost (AC) = 130,000 ==> money spent

Planned Value (PV) = 75% of 200,000 - month 4 - project completion

= 150,000

Earned Value (EV) = 67.5 % of 200,000 = = 135,000

month 3 - 70% completed 70% is what percentage of 25% that is each month project completion is 25% and in 4th month whole project is completed - 100%

month 1 - 25%

month 2 - 25%

month 3 - 17.5 % = 25% * 70%

total = 67.5%

To calculate the EAC, first you have to calculate the Cost Performance Index:

Cost Performance Index (CPI) = EV / AC

= 135,000 / 130,000

= 1.03

=>Cost Performance Index (CPI) = 1.03

Now,

Estimate at Completion (EAC) = BAC / CPI

= 200,000 / 1.03

= 194,174.75

Hence, the Estimate at Completion (EAC) is 194,174.75.

In other words, if the project continues to progress with CPI = 1.03 until the end, you will have to spend 194,174.75 to complete the project.

  • If the CPI = 1, then EAC = BAC. This means you can complete your project with your approved budget.
  • In the given problem the CPI > 1, then EAC < BAC. This means you can complete your project with in your approved budget.

Related Solutions

A new renewable energy generation system has a life-time of 10 years. It is assumed that...
A new renewable energy generation system has a life-time of 10 years. It is assumed that the salvage value of the system at the end of the 10 years' life-time is negligible. The initial (Present time) investment of the system costs 50,000 HK$. The manufacturer agrees to maintain the system every year over the 10 years' life-time with a uniform annual maintenance fee of 1000 HK$/year. At the end of the 5th year, a key component should be replaced, which...
A new renewable energy generation system has a life-time of 10 years. It is assumed that...
A new renewable energy generation system has a life-time of 10 years. It is assumed that the salvage value of the system at the end of the 10 years' life-time is negligible. The initial (Present time) investment of the system costs $50,000. The manufacturer agrees to maintain the system every year over the 10 years' life-time with a uniform annual maintenance fee of $1000/year. At the end of the 5th year, a key component should be replaced, which will cost...
Green bonds are bonds issued by a company to fund renewable energy projects. Kuzlon India had...
Green bonds are bonds issued by a company to fund renewable energy projects. Kuzlon India had raised financing for investing in wind power projects by issuing green bonds with 10 years as time to maturity. The green bonds were semi-annual bonds with a 10% p.a (EAR). coupon rate AAA rated. The Face value of the bonds was ₹1000. Since, these bonds enabled capital raising for projects with environmental benefits, the green bonds were issued at a premium. The yield to...
The Antelope Elk Energy Center in Abernathy, Texas, a natural gas power generation plant, is considering...
The Antelope Elk Energy Center in Abernathy, Texas, a natural gas power generation plant, is considering an upgrade to its fuel distribution system. The upgrade is expected to increase fuel efficiency thus decrease natural gas consumption to create a savings of $6.5 million per year over a 15-year period. Accounts receivable is expected to increase by 5%, inventory is anticipated to decrease by 20%, and accounts payable to decrease by 10%. MasTech, a leading power generation construction company, estimated the...
You are trying to build the small scale hydroelectric power plant on the hill. Potential energy...
You are trying to build the small scale hydroelectric power plant on the hill. Potential energy is the main energy that you can use to generate the electricity. How much of the water (in kg) should be in the source to provide the 7 kW of power to the house? Assume that the efficiency of the electricity generator is 0.7 and g=9.8 m/s2 .
CASE STUDY:                RENEWABLE ENERGY SOURCES FOR ELECTRICITY GENERATION You developed an interest in the LEC...
CASE STUDY:                RENEWABLE ENERGY SOURCES FOR ELECTRICITY GENERATION You developed an interest in the LEC relation and the publicized cost of electricity of 10.27¢/kWh for this year. You wonder if the addition of 60 MW of wind-sourced electricity will make any difference in the LEC value for this next year. You did learn the following: This is year t = 11 for LEC computation purposes n = 25 years i = 5% per year E11 = 5.052 billion kWh...
The ability to scale up renewable energy and in particular wind power and speed is dependent...
The ability to scale up renewable energy and in particular wind power and speed is dependent on the ability to forecast its short term availability soman et al (2010( describe different methods for wind power forecasting (the quote is slightly edited for brevity) Persistence method: this method is also known as ‘naïve predictor. Its is assumed that the wind speed at time t + tetat will be the same as it was at time t. unbelievably it is more accurate...
1. Power generation by natural gas or other petroleum productfired steam power plant is the...
1. Power generation by natural gas or other petroleum product fired steam power plant is the most comment way of producing energy in most parts of the worlda. Sketch steam power plant and discuss the function of each unit Operation in the process(b. What are the major operational and safety challenges in steam power plants )c. Pumps are the most important fluid movers in process industries, discuss the various types of Pumps you find in steam power plant and their...
A power company operates three power generation plants. One is a wind plant, and the other...
A power company operates three power generation plants. One is a wind plant, and the other two consume a combination of Fuel 1 and Fuel 2, emitting carbon dioxide in the process. In addition, all three plants require maintenance. The amount of fuel consumed (in Mg), maintenance required (in person-hours), carbon dioxide (CO2) emitted (in Mg), and power generated (in MWh) per day of operation is as follows: Maintenance Fuel 1 Fuel 2 CO2 Power Plant Required Required Required Emitted...
Design a geothermal source power generation system; a) Describe the type of geothermal power plant (Total...
Design a geothermal source power generation system; a) Describe the type of geothermal power plant (Total Flow / Flash / Binary) b) Describe the turbine isentropic efficiency c) Show the entire cycle in the T-s diagram. d) Calculate the power produced. answer for expert: Not all , just one of theese three ( Total flow / flash or binary)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT