Question

In: Accounting

Standard Costing & Variance Analysis Delic plc. is a manufacturer of cakes that makes a wide...

Standard Costing & Variance Analysis

Delic plc. is a manufacturer of cakes that makes a wide range of cakes. It operates a standard marginal cost accounting system. Given below, is information relating to one of its products, i.e. birthday cakes, which are made in one of the company departments:

Birthday cakes

Standard marginal product cost

per unit ($)

Direct material

(6 kgs at $4 per kg)

24

Direct labour

(1 hour at $7 per hour)

7

Variable production overhead

3

total

34

Additional information

  • Variable production overhead varies with direct labour hours of input
  • Budgeted fixed production overhead per month is $100,000
  • Budgeted production for birthday cakes is 20,000 units per month

Actual production and costs for one of the months were as follows: -          

Units of birthday cakes produced                                           18,500 units

                                                                                                

                                                                                                          $

Direct materials purchased and used, 113,500kg                       442,650

        Direct labour, 17,800 hours                                                   129,940

        Variable production overhead incurred                                    58,800

        Fixed production overhead incurred                                     104,000

                         total                                                                               735,390

Required:

  1. Prepare a statement showing, by cost elements (i.e. direct materials; direct labour; variable overhead; and fixed overhead), the:
    1. original budget                                                                                                
    2. flexed budget                                                                                                  
    3. actual cost                                                                                                       
    4. total variances                                                                                             
  2. To be more informative for managerial purposes, prepare the following variances:
    1. Material price variance                                                                                   
    2. Material usage variance                                                                                 

                (iii) Wage rate variance                                                                                        

  1. Labour efficiency variance                                                                            
  2. Variable overhead expenditure variance                                                        

                   vi) Variable overhead efficiency variance                                                            

Solutions

Expert Solution

a.

Delic. PLC
Flexible Budget Performance Report
For the month of ...
Actuals Spending Variances Flexible Budget Volume Variances Original Budget
Activity Level 18,500 cakes 18,500 cakes 20,000 cakes
Costs $ $ $ $ $
Direct Materials 442,650 1,350 F 444,000 36,000 F 480,000
Direct Labor 129,940 440 U 129,500 10,500 F 140,000
Variable Production Overhead 58,800 3,300 U 55,500 4,500 60,000
Fixed Production Overhead 104,000 4,000 U 100,000 None 100,000
Total Cost 735,390 6,390 U 729,000 51,000 F 780,000

b.

Type of Variance Computation Amount of Variance Total
i. Material Price Variance $ ( 4.00 - 3.90) * 113,500 kg $ 11,350 F
ii. Material Usage Variance ( 18,500 x 6 kg - 113,500 kg ) * $ 4.00 10,000 U
Direct Materials Spending Variance $1,350 F
iii. Wage Rate Variance $ ( 7.00 - 7.30 ) * 17,800 hrs 5,340 U
iv. Labor Efficiency Variance ( 18,500 x 1 - 17,800) * $ 7.00 4,900 F
Direct Labor Spending Variance 440 U
v. Variable Overhead Expenditure Variance $ ( 3 x 17,800 - 58,800) 5,400 U
vi. Variable Overhead Efficiency Variance ( 18,500 - 17,800) * $ 3.00 2,100 F
Variable Overhead Spending Variance 3,300 U

Related Solutions

Problem 1 – Standard Costing Sidney Bakers Patisserie makes banana cakes on a standard costing basis....
Problem 1 – Standard Costing Sidney Bakers Patisserie makes banana cakes on a standard costing basis. Over the past years, the company has determined a standard materials quantity allowed of 0.75 pound per piece of banana cake at a standard price agreed with suppliers at $1.5 per pound. Historically, the company has been producing 11,000 banana cakes per month. During the just concluded month May 2020, company records show 10,500 banana cakes produced with an actual cost of $13,860 with...
ABC bakery makes banana cakes on a standard costing basis. Over the past years, the company...
ABC bakery makes banana cakes on a standard costing basis. Over the past years, the company has determined a standard materials quantity allowed of 0.75 pound per piece of banana cake at a standard price agreed with suppliers at $1.5 per pound. Historically, the company has been producing 11,000 banana cakes per month. During the just concluded month May 2020, company records show 10,500 banana cakes produced with an actual cost of $13,860 with 8,400 pounds purchased and used in...
How did the managerial accounting process of standard costing and variance analysis improve the analysis of...
How did the managerial accounting process of standard costing and variance analysis improve the analysis of the operations of the firm? What would be your reaction, as a manager, now that all the “new” information has reached your desk? Direct Labor Variances Direct Materials Variance Overhead Variance
When it comes to variance analysis and standard costing, how can you apply this concept to...
When it comes to variance analysis and standard costing, how can you apply this concept to your personal life? How can you apply it in your workplace?
Characterize the use of standard costing and variance analysis for short-term financial control. What are the...
Characterize the use of standard costing and variance analysis for short-term financial control. What are the arguments against using standard costing and variance analysis (SCVA) for lean organizations? What are some of the key “flaws” of SCVA? What are the primary reasons more organizations have not discarded traditional approaches to short-term financial control?
Task 1: Standard Costing & Variance Analysis Kita Ltd, produces a single product in one of...
Task 1: Standard Costing & Variance Analysis Kita Ltd, produces a single product in one of its factory. For control and measurement purposes, a standard costing system was recently introduced and is now in operation. The standards set for the month of May were as follows:   Production and sales                                                   16,000 units Selling price (per unit)                                                  RM140 Materials: Material XX                                                                     6 kilos per unit at RM12.25 per kilo Material YY                                                                     3 kilos per unit at RM3.20 per kilo...
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
QUESTION 3 Cloudsdale plc makes a wide range of motor accessories in a mass production environment....
QUESTION 3 Cloudsdale plc makes a wide range of motor accessories in a mass production environment. Standard costing is used to control performance and variances are incorporated into weekly management reports using the planning and operational approach. The following data relates to one of their most popular products. The standards set at the beginning of the period include the following: Selling price per unit                                                           £80 Direct materials price per kilo                                            £5 Direct materials usage per unit                                         7 kilos Other variable costs (per unit)                                          £20...
8. What is a standard cost variance, and what is the objective of variance analysis? Identify...
8. What is a standard cost variance, and what is the objective of variance analysis? Identify three possible causes for (1) a favorable materials price variance; (2) an unfavorable materials price variance; (3) a favorable materials quantity variance; and (4) an unfavorable materials quantity variance
Each week, a manufacturer of chocolate cakes is able to produce f(H, M) cakes if their...
Each week, a manufacturer of chocolate cakes is able to produce f(H, M) cakes if their employees work a total of H hours and they use their cake production machines for a total of M hours. The employees’ wage is $19 per hour and due to electricity and maintenance, the machines cost about $30 per hour to run. Their operating budget is $10,000 per week. In order to determine how to maximize their production, they use the method of Lagrange...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT