Question

In: Accounting

Problem 1 – Standard Costing Sidney Bakers Patisserie makes banana cakes on a standard costing basis....

Problem 1 – Standard Costing Sidney Bakers Patisserie makes banana cakes on a standard costing basis. Over the past years, the company has determined a standard materials quantity allowed of 0.75 pound per piece of banana cake at a standard price agreed with suppliers at $1.5 per pound. Historically, the company has been producing 11,000 banana cakes per month. During the just concluded month May 2020, company records show 10,500 banana cakes produced with an actual cost of $13,860 with 8,400 pounds purchased and used in production. Further information reveals that the company has standardized 0.25 hours to finish one unit at a standard rate of $7.00. Time tickets reveal that actual payroll for direct labor amounted to $14,175 with 2,100 hours worked. Required: For the final answers follow instructions. Denote variances with F or U after the answer (Ex. 100F for 100 Favorable; 100U for Unfavorable). Failure to comply with this format will not get any credit. Do not simply write positive or negative answer. 1. Total Materials Variance 2. Total Labor Variance 3. Materials Price Variance 4. Materials Quantity Variance 5. Labor Rate Variance 6. Labor Efficiency Variance 7. Compute the Materials Quantity Variance assuming only 7,500 units were produced with actual usage of 5,500 pounds, the remaining materials were left in ending inventory

Need to find

1. Total Materials Variance 2. Total Labor Variance 3. Materials Price Variance 4. Materials Quantity Variance 5. Labor Rate Variance 6. Labor Efficiency Variance 7. Compute the Materials Quantity Variance assuming only 7,500 units were produced with actual usage of 5,500 pounds, the remaining materials were left in ending inventory

Solutions

Expert Solution

Solution

1) Information required for calculating the material variance

  • The actual production is 10,500 cakes.
  • The actual direct material purchased and used is 8,400 pounds
  • The actual price paid is $ 1.65 per pound is ($13,860 / 8,400 pounds)
  • The material required to produce 1 cake is 0.75 pounds.
  • The standard price is $1.5 per pound
  • Total standard quantity required to is 7,875 pounds (10,500 cakes x 0.75 pound)

Total Materials Variance

= (Standard pounds for actual production x Standard price per pound) - (Actual pounds purchased x Actual price per pound

= (7,875 pounds x $ 1.5) - (8,400 pounds x $ 1.65)

= $ 11,812.5 - $ 13,860

= $ 2047.5 (U)

Material price variance = (standard price per pound- actual price per pound) * actual quantity purchased
= ($1.5 - $ 1.65) * 8,400

= ($0.15) * 8,400
= $ 1,260 (U)

Material quantity variance = Standard price per unit * (Standard quantity - Actual quantity)
=$ 1.5 x (7,875 – 8,400)
=$1.5 * 525
= $787.5 (U)

2) Given information required to calculate the labor variance

· The actual direct labor hours used is 2100 hours

· The actual price paid per direct labor hour is $6.75 ($14,175/ 2100)

· The standard direct labor cost per hour is $7 per hour

· .The standard labor hours to be used is 2,625 hours (10,500 x 0.25 hour required per cake)

Total Labor Variance

= (Standard labor hours x Standard rate per hour) - (Actual hours x Actual rate per hour

= (2,625 hours x $ 7) - (2,100 hours x $ 6.75)

= $ 18,375 - $ 14,175

= $ 4,200 (F)

Labor price variance = (standard price per labor hour - actual price per labor hour) * actual labor hours
= ($7 - $6.75) x 2,100 hours

= $0.25 * 2100
= $525 (F)

Labor Efficiency variance = standard price per labor hour * (standard labor hours – actual labor hours)
= (2,625 – 2,100) x $7
=$7 * 525
= $3,675 (F)

Computation of Materials Quantity Variance assuming only 7,500 units were produced with actual usage of 5,500 pounds, the remaining materials were left in ending inventory

Material quantity variance = Standard price per unit * (Standard quantity - Actual quantity)
=$ 1.5 x (5,625– 5,500)
=$1.5 * 125
= $187.5 (F)

W.N. 1

Standard quantity to be used when 7,500 units produced

= 7,500 units x 0.75 pounds

= 5,625 pounds


Related Solutions

ABC bakery makes banana cakes on a standard costing basis. Over the past years, the company...
ABC bakery makes banana cakes on a standard costing basis. Over the past years, the company has determined a standard materials quantity allowed of 0.75 pound per piece of banana cake at a standard price agreed with suppliers at $1.5 per pound. Historically, the company has been producing 11,000 banana cakes per month. During the just concluded month May 2020, company records show 10,500 banana cakes produced with an actual cost of $13,860 with 8,400 pounds purchased and used in...
The Matisse Co. produces banana cakes. The following information relates to the actual production of 4,000...
The Matisse Co. produces banana cakes. The following information relates to the actual production of 4,000 banana cakes. Standards: ·         Direct materials cost $2.00 per pound & each cake requires 1 pound of bananas. ·         Direct labor cost $11.00 per hour & each cake will take 1 DLH to complete. Actual: ·         Bananas $1.90 per pound. 4,500 pounds of bananas were purchased and used. ·         Actual direct labor cost was $43,460 at a cost of $10.60 per DLH. What is the direct materials quantity...
Bevard Nuptial Bakery makes very elaborate wedding cakes to order. The company has an activity-based costing...
Bevard Nuptial Bakery makes very elaborate wedding cakes to order. The company has an activity-based costing system with three activity cost pools. The activity rate for the Size-Related activity cost pool is $0.95 per guest. (The greater the number of guests, the larger the cake.) The activity rate for the Complexity-Related cost pool is $31.28 per tier. (Cakes with more tiers are more complex.) Finally, the activity rate for the Order-Related activity cost pool is $77.41 per order. (Each wedding...
Meade Nuptial Bakery makes very elaborate wedding cakes to order. The company has an activity-based costing...
Meade Nuptial Bakery makes very elaborate wedding cakes to order. The company has an activity-based costing system with three activity cost pools. The activity rate for the Size-Related activity cost pool is $1.20 per guest. (The greater the number of guests, the larger the cake.) The activity rate for the Complexity-Related cost pool is $28.55 per tier. (Cakes with more tiers are more complex.) Finally, the activity rate for the Order-Related activity cost pool is $84.55 per order. (Each wedding...
Company uses standard costing. Overhead is applied to products on the basis of standard direct labor...
Company uses standard costing. Overhead is applied to products on the basis of standard direct labor hours for actual production. Data for company follows: Standard direct labor hours allowed for actual output 110,000 Actual direct labor hours 115,000 Direct labor hours budgeted in the master budget 120,000 Budgeted total variable overhead cost $360,000 Actual variable overhead cost 328,000 1.Calculate the variable overhead spending variance and whether it is favorable or unfavorable. 2.Calculate the variable overhead efficiency variance and whether it...
Cream Cakes makes and sells cakes daily. Based on past experience the owner has estimated the...
Cream Cakes makes and sells cakes daily. Based on past experience the owner has estimated the following probabilities for the daily demand for fresh cream cakes:Daily Demand (cakes)Probability 300.1400.2500.3600.3700.1 The cakes cost $12 to make and are sold for $22 per cake. Cream Cakes believes a lot of their success is because they only sell fresh cakes. Any cakes unsold at the end of the day is mashed up and sold to the local piggery for $7.00 If the proprietor...
Kim has a company called Daisy Cakes where she makes cakes with her grandmother with fresh...
Kim has a company called Daisy Cakes where she makes cakes with her grandmother with fresh ingredients. Kim invested $93,000 in the company. Kim sells the cakes for $44.50 on her website and it takes $18 to make the cakes. Kim's sales in three months (October, November, and December) was $27,000, however, she is seeking for an investor to invest $50,000 in her company in exchange for 25% equity. Barbara, an investor, agrees to invest $50,000 in her company under...
Process Costing Tempe Manufacturing Company makes a single product that is produced on a continuous basis...
Process Costing Tempe Manufacturing Company makes a single product that is produced on a continuous basis in one department. All materials are added at the beginning of production. The total cost per equivalent unit in process in March 2009 was $4.60, consisting of $3.00 for materials and $1.60 for conversion. During the month, 8,700 units of product were transferred to finished goods inventory; on March 31, 2,000 units were in process, 10 percent converted. The company uses weighted average costing....
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats...
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats of cake batter are processed in the Mixing Department and then transferred to the Baking Department, where individual cakes are baked, cooled, and frosted. There were 500 gallons of partially mixed batter in the Mixing Department’s inventory on August 1. The batter was 100 percent complete with respect to direct materials, but only 30 percent complete with respect to conversion. Manufacturing costs assigned to...
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats...
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats of cake batter are processed in the Mixing Department and then transferred to the Baking Department, where individual cakes are baked, cooled, and frosted. There were 500 gallons of partially mixed batter in the Mixing Department’s inventory on August 1. The batter was 100 percent complete with respect to direct materials, but only 30 percent complete with respect to conversion. Manufacturing costs assigned to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT