Question

In: Economics

For the below ME alternatives , which machine should be selected based on the PW analysis....

For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%

Machine A Machine B Machine C
First cost, $ 23,979 30000 10000
Annual cost, $/year   8,679                6,000             4,000
Salvage value, $                  4,000                5,000             1,000
Life, years 3 6 2

Answer the below questions :

A- PW for machine A=

Solutions

Expert Solution

Since the life of the alternatives are unequal, we have to take the LCM of 3, 6, and 2. The LCM is 6. We have to calculare present worth of the alternatives taking life of the project as 6 years.

PW for machine A = -23,979 - (23979 - 4,000) (P/F, 10%, 3) - 8,679(P/A, 10%, 6) + 4,000(P/F, 10%, 6)

                             = -23,979 - 19979(0.7513) - 8,679(4.355) + 4,000(0.5645)

                             = -23,979 - 15,010.22 37,797.04 + 2,258

                             = -$75,528.26


Related Solutions

For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 11,265 Annual cost, $/year   14,021                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- PW for machine C =
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 22,421 30000 10000 Annual cost, $/year   8,497                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A=
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 15000 21,476 10000 Annual cost, $/year   8,095                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : B- PW for machine B=
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%.
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%.Machine AMachine BMachine CFirst cost, $              15000            30000          10,423Annual cost, $/year                 12,340               6,000            4,000Salvage value, $                 4,000               5,000            1,000Life, years 362Answer the below questions :A- PW for machine C =B- Based on the PW value you got in the previous questions, which machine we should select? type you explanation below 
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 11,937 Annual cost, $/year   13,944                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- AW for machine C =
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 15,567 30000 10000 Annual cost, $/year   9,535                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- AW for machine A=
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 11,564 Annual cost, $/year   10,709                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- AW for machine C =
QUESTION 3 For the below ME alternatives , which machine should be selected based on the...
QUESTION 3 For the below ME alternatives , which machine should be selected based on the PW analysis. Machine A Machine B Machine C First cost, $ 21,929 30000 10000 Annual cost, $/year   8,702               6,000            4,000 Salvage value, $                 4,000               5,000            1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A= --------------------------------------------------------------------------------------------- QUESTION 4 For the below ME alternatives , which machine should be selected based on the PW analysis. Machine A Machine B...
Perform a present worth (PW)-based evaluation of the two alternatives below using a spreadsheet. The after-tax...
Perform a present worth (PW)-based evaluation of the two alternatives below using a spreadsheet. The after-tax minimum acceptable rate of return (MARR) is 8% per year, Modified Accelerated Cost Recovery System (MACRS) depreciation applies, and Te = 40%. The (GI - OE) estimate is made for the first 3 years; it is zero in year 4 when each asset is sold. Alternative X Y First Cost, $ –8,000 –13,000 Salvage Value, Year 4, $ 0 2,000 GI-OE, $ per Year...
Perform a present worth (PW)-based evaluation of the two alternatives below using a spreadsheet. The after-tax...
Perform a present worth (PW)-based evaluation of the two alternatives below using a spreadsheet. The after-tax minimum acceptable rate of return (MARR) is 8% per year, Modified Accelerated Cost Recovery System (MACRS) depreciation applies, and Te = 40%. The (GI - OE) estimate is made for the first 3 years; it is zero in year 4 when each asset is sold. Alternative X Y First Cost, $ –8,000 –13,000 Salvage Value, Year 4, $ 0 2,000 GI-OE, $ per Year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT