Question

In: Accounting

Identifying Relevant Costs and Revenues The Village of Bomont operates a power plant on a river...

Identifying Relevant Costs and Revenues
The Village of Bomont operates a power plant on a river that flows through town. The village uses some of this generated electricity to operate a water treatment plant and sells the excess electricity to a local utility. The city council is evaluating two alternative proposals:

  • Proposal A calls for replacing the generators used in the plant with more efficient generators that will produce more electricity and have lower operating costs. The salvage value of the old generators is higher than their removal cost.

  • Proposal B calls for raising the level of the dam to retain more water for generating power and increasing the force of water flowing through the dam. This will significantly increase the amount of electricity generated by the plant. Operating costs will not be affected.

Required
Presented are a number of cost and revenue items. Indicate in the appropriate columns whether each item is relevant or irrelevant to proposals A and B.

Proposal A Proposal B
1. Cost of new furniture for the city manager's office
2. Cost of old generators
3. Cost of new generators
4. Operating cost of old generators
5. Operating cost of new generators
6. The police chief's salary
7. Depreciation on old generators
8. Salvage value of old generators
9. Removal cost of old generators
10. Cost of raising dam
11. Maintenance costs of water plant
12. Revenues from sale of electricity

Solutions

Expert Solution

Answer:

Proposal A Proposal B Explanation
1. Cost of new furniture for City Manager’s office N/A N/A There is no cost associated with building the office furniture
2. Cost of old generators X N/A It is the cost associated with proposal A as in the second proposal they are increasing the level of dam not the replacement of generators
3. Cost of new generators X N/A Since in proposal A they are replacing the generators so this is the cost associated with proposal A
4. Operating cost of old generators N/A X As in proposal A the old generators are replacing with the new one there would not be any operating cost associated with proposal A but in proposal B it would be there
5. Operating cost of new generators X N/A As in proposal A the old generators are replacing with the new one there would operating cost associated with proposal A but not in proposal B.
6. Police Chief’s salary N/A N/A No cost
7. Depreciation on old generators X X It would be there in case of both the proposals as in Proposal A it is required to find the current book value of the generators and to find the capital gain or loss. For B it is to record the book value of the generators
8. Salvage value of old generators X X It is used in both to calculate the depreciation for the generators
9. Removal cost of old generators X N/A In proposal A since it is getting replaced with the new one.
10. Cost of raising dam N/A X In proposal B since they are planning to raise the water level of the dam not the replacement of the generators
11. Maintenance costs of water plant X X In both since this is the cost associated with the plant. It would incur no matter which proposal they choose
12. Revenues from sale of electricity X X in both as this would help in determining the total revenue generated by the plant, no matter which proposal in chosen.

Related Solutions

Understand the concept of relevant revenues and costs. What makes a revenue or cost relevant? ________________________________________________...
Understand the concept of relevant revenues and costs. What makes a revenue or cost relevant? ________________________________________________ ________________________________________________ ________________________________________________ Know and understand the following terms: Avoidable costs _______________________________________________________________ Opportunity costs _____________________________________________________________ Relevant Costs ________________________________________________________________ Differential Costs ______________________________________________________________ Sunk Costs ___________________________________________________________________ Differential Revenues ___________________________________________________________ Understand the concept of Cost Hierarchy and Cost Avoidance. What are the different cost hierarchies and when are they eliminated? ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Review examples of costs in the above 4 categories that we covered in class...
A coal-fired power plant produces power  with costs . Each unit of power earns the plant ....
A coal-fired power plant produces power  with costs . Each unit of power earns the plant . Burning coal releases particulate matter (PM2.5), a pollutant that is known to cause heart disease, lung disease, and birth defects. The coal plant borders a wildlife sanctuary which sells tourism visits  for a price $30. However, the sanctuary's animals are getting sick due to the negative externality of PM2.5, such that the costs to the sanctuary are . The local government decides to tax the...
Your company operates a steel plant. On average, revenues from the plant are $30 million per...
Your company operates a steel plant. On average, revenues from the plant are $30 million per year. All of the plants costs are variable costs and are consistently 80% of revenues, including energy costs associated with powering the plant, which represent one quarter of the plant’s costs, or an average of $6 million per year. Suppose the plant has an asset beta of 1.25, the risk-free rate is 4%, and the market risk premium is 5%. The tax rate is...
A power company operates three power generation plants. One is a wind plant, and the other...
A power company operates three power generation plants. One is a wind plant, and the other two consume a combination of Fuel 1 and Fuel 2, emitting carbon dioxide in the process. In addition, all three plants require maintenance. The amount of fuel consumed (in Mg), maintenance required (in person-hours), carbon dioxide (CO2) emitted (in Mg), and power generated (in MWh) per day of operation is as follows: Maintenance Fuel 1 Fuel 2 CO2 Power Plant Required Required Required Emitted...
Project 5.2: Identifying a Power Plant Problem You are an independent consultant and operate a business...
Project 5.2: Identifying a Power Plant Problem You are an independent consultant and operate a business known as Pro-Active Consultants Inc. from your home. Four days ago you received a telephone call from Paullette Machon, who is vice president, operations, of Baldur Agricultural Chemicals (BAC), a company with manufacturing plants across the country. She said she has a task for you and invited you to visit her at the BAC office at 1450 Disraeli Crescent (of the town or city...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam enters the first turbine stagge at 12 MPa, 560*C and expands to 1 MPa, where some of the steam is extracted and diverted to the open feedwater heater operating at 1 MPa. The remaining steam expands through the second turbine stage to the condenser pressure of 6 kPa. Saturated liquid exits the open feedwater heater at 1 MPa. The net power output for the...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam enters the first turbine stage at 12 MPa, 520◦C and expands to 1 MPa, where some of the steam is extracted and diverted to the open feedwater heater at 1 MPa. The remaining steam expands through the second turbine stage to the condenser pressure of 6 kPa. Saturated liquid exits the open feedwater heater at 1 MPa. For isentropic processes in the turbines and...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam enters the first turbine stage at 12 MPa, 560°C and expands to 1 MPa, where some of the steam is extracted and diverted to the open feedwater heater operating at 1 MPa. The remaining steam expands through the second turbine stage to the condenser pressure of 50 kPa. Saturated liquid exits the open feedwater heater at 1 MPa. The net power output for the...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam...
A power plant operates on a regenerative vapor power cycle with one open feedwater heater. Steam enters the first turbine stage at 12 MPa, 560°C and expands to 1 MPa, where some of the steam is extracted and diverted to the open feedwater heater operating at 1 MPa. The remaining steam expands through the second turbine stage to the condenser pressure of 28 kPa. Saturated liquid exits the open feedwater heater at 1 MPa. The net power output for the...
A steam power plant operates with a boiler that is heated from a heat source at...
A steam power plant operates with a boiler that is heated from a heat source at 457 °C and produces 450 ton/hr. of steam. The steam leaves the boiler at 425 °C and 4 MPa. The steam reaches a turbine at 375 °C and 3 MPa and leaves it at 50 kPa with 4% liquid water. This mixture is flown into a condenser that rejects the heat into a river at 17 °C. Water leaves the condenser at 50 kPa...