In: Finance
Pharoah Manufacturing Co. is evaluating two projects. The company uses payback criteria of three years or less. Project A has a cost of $901,000, and project B’s cost is $1,268,100. Cash flows from both projects are given in the following table. Year Project A Project B 1 $86,212 $586,212 2 313,562 413,277 3 427,594 231,199 4 285,552 What are their discounted payback periods? (Round answers to 2 decimal places, e.g. 15.25. If discounted payback period exceeds life of the project, enter 0.00 for the answer.) Discounted payback period of project A 0.00 Discounted payback period of project B 0.00 Which will be accepted with a discount rate of 8 percent? Pharoah should choose
Please show not using excel or financial calculator functions
First of all let us put the given data in tabular format:
Project A has a cost of and project B’s cost is . Cash flows from both projects are given in the following table. Year Project A Project B 1 2 3 231,199 4
Year | Project A | Project B |
0 | -$901,000, | -$1,268,100 |
1 | $86,212 | $586,212 |
2 | 313,562 | 413,277 |
3 | 427,594 | 231,199 |
4 | 285,552 | 0 |
Following are the discounted CF for the projects:
Project A:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -9,01,000.00 | 1/(1+0.08)^0= | 1 | 1*-901000= | $ -9,01,000.00 |
1 | $ 86,212.00 | 1/(1+0.08)^1= | 0.925925926 | 0.925925925925926*86212= | $ 79,825.93 |
1 | $ 3,13,562.00 | 1/(1+0.08)^1= | 0.925925926 | 0.925925925925926*313562= | $ 2,90,335.19 |
3 | $ 4,27,594.00 | 1/(1+0.08)^3= | 0.793832241 | 0.79383224102017*427594= | $ 3,39,437.90 |
4 | $ 2,85,552.00 | 1/(1+0.08)^4= | 0.735029853 | 0.735029852796453*285552= | $ 2,09,889.24 |
Project B:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -12,68,100.00 | 1/(1+0.08)^0= | 1 | 1*-1268100= | $ -12,68,100.00 |
1 | $ 5,86,212.00 | 1/(1+0.08)^1= | 0.925925926 | 0.925925925925926*586212= | $ 5,42,788.89 |
2 | $ 4,13,277.00 | 1/(1+0.08)^2= | 0.85733882 | 0.857338820301783*413277= | $ 3,54,318.42 |
3 | $ 2,31,199.00 | 1/(1+0.08)^3= | 0.793832241 | 0.79383224102017*231199= | $ 1,83,533.22 |
Now we will calculate the discounted PV for the projects:
Project A:
Year | Opening Balance | Investment | DCF | Closing Balance |
0 | $ 9,01,000.00 | $ 9,01,000.00 | ||
1 | $9,01,000.00 | $79,825.93 | $ 8,21,174.07 | |
2 | $8,21,174.07 | $2,90,335.19 | $ 5,30,838.89 | |
3 | $5,30,838.89 | $3,39,437.90 | $ 1,91,400.99 | |
4 | $1,91,400.99 | $2,09,889.24 | $ -18,488.26 |
We see that at the end of year 3 the closing balance is $1,91,400.99 while the DCF in year 4 is $2,09,889.24 therefore sometime during the year the entire closing balance was recovered. We assume that it is earned uniformly throughout the year therefore the time take is 1,91,400.99/2,09,889.24 = 3.91 years
Project B:
Year | Opening Balance | Investment | Principal repayment | Closing Balance |
0 | $ 12,68,100.00 | $ 12,68,100.00 | ||
1 | $ 12,68,100.00 | $ 5,42,788.89 | $ 7,25,311.11 | |
2 | $ 7,25,311.11 | $ 3,54,318.42 | $ 3,70,992.70 | |
3 | $ 3,70,992.70 | $ 1,83,533.22 | $ 1,87,459.48 | |
4 | $ 1,87,459.48 | $ - | $ 1,87,459.48 |
We see that at the end of year 3 the closing balance is $1,87,459.48 while the DCF in year 4 is $0 therefore the closing balance was not recovered
As neither of the project has the discounted payback period of less than 3, none meets the criteria