In: Operations Management
A company assembles and sells skateboards. One popular model is the "ICE". The final assembly plan for April to September, which also represents 50% of a full year’s demand:
Month | April | May | June | July | August | September | October |
---|---|---|---|---|---|---|---|
Forecast (units) | 5000 | 7000 | 10000 | 2000 | 4000 | 3000 | ? |
Demand (units) | 4500 | 8000 | 10000 | 1900 | 4000 | 3200 | ? |
The company is using MRP. The forecast for Skateboard ICE for the next coming six weeks:
Week | w36 | w37 | w38 | w39 | w40 | w41 |
---|---|---|---|---|---|---|
Demand (forecast, units) | 750 | 750 | 750 | 900 | 950 | 1000 |
The company are buying all components from different suppliers. They are only making the wheel assembly and the assembly of the final skateboard, see also the diagram above.
Item | Stock level | Value/item | Lot size | Lead time (weeks) |
---|---|---|---|---|
Skateboard ICE | 1800 | $250.00 | 2000 | 1 |
Decks | 4000 | $20.00 | 1500 | 2 |
Wheel assemblies | 1200 | $80.00 | Even hundreds | 1 |
Bolts and Nuts, M6 | 25000 | $0.50 | 50000 | 1 |
Risers | 30000 | $1.00 | 50000 | 1 |
Wheels | 20000 | $8.00 | 40000 | 2 |
Bearings | 40000 | $4.00 | 50000 | 2 |
Trucks | 2000 | $19.00 | ? | 2 |
Nuts, M8 | 50000 | $0.25 | 100000 | 1 |
The company has an ordering cost of $150/order and the inventory carrying cost is estimated to 10%.
3a. If we use moving average with n=5, what is the forecast for Skateboard ICE for October?
3b. If we use exponential smoothing with α=0.3, what is the forecast for Skateboard ICE for October?
3c. Suppose it's now week 35. In what week should production of wheel assemblies start?
3d. In relation to question 3c above, what quantity of wheel assemblies will be needed?
3e. The company have had some problems with the supplier of the truck parts and therefore want to review the setup. But first they want to check how many truck parts they should order each time by calculating the Economic Order Quantity (EOQ).
What quantity of truck parts should the company order?
3f. The supplier of the truck parts replies to the company that if they order in lots of 10 000 each time, they will get a 5 % discount.
What is the total cost for the truck parts if the company order 10 000 each time?
Answer to question 1 :
For n = 5 , forecast for October basis moving average
= Sum of forecasts( for period May to September) /5
= ( 7000 + 10000 + 2000 + 4000 + 3000) / 5
= 26000/5
= 5200
Answer to question 2:
Basis exponential smoothing, relevant equation as follows :
Ft = alpha x At + ( 1- alpha) x Ft-1
Ft = Forecast for period t
Ft-1 = Forecast for period t-1
At = Actual demand for period t
Alpha = 0.3
Also , F0 = A0 ( Forecast for period 0 is assumed to be same as actual demand for period 0)
The below table highlights the forecast values arrived basis exponential smoothing method ( for period April till September)
Forecast for October will be same as Forecast value for September arrived through exponential smoothing
Accordingly, forecast for skateboard ICE for October = 4408 units
Month |
Actual demand , A |
Forecast, F |
April |
5000 |
5000 |
May |
7000 |
5600 |
June |
10000 |
6920 |
July |
2000 |
5444 |
August |
4000 |
5011 |
September |
3000 |
4408 |
October |
4408 |
Answer to question 3:
Lead time of components going into production of wheel assemblies as follows :
Wheels : 2 weeks
Bearing : 2 weeks
Trucks : 2 weeks
Nuts : 1 week
Hence maximum lead time of component = 2 weeks
Thus if wheel assembly is required on 35th week. Production of assembly of wheel assembly should start at = 35 week – 2 week = 33th week
Supply of wheel assembly has a lead time of 1 week for production of Skateboard ICE ,
In other words for skateboards which are required on week 36, production of wheel assembly should start at week 33
Below table presents when Skateboard ICE is required and corresponding production of wheel assembly must start :
Week when skateboard required |
W36 |
W37 |
W38 |
W39 |
W40 |
W41 |
Week when wheel assembly production shall start |
W33 |
W34 |
W35 |
W36 |
W37 |
W38 |
Answer to question 4:
Annual demand for skateboard ICE
= 2 x ( Cumulative demand for period April to September)
= 2 x ( 4500 + 8000 + 10000 + 1900 + 4000 + 3200 )
= 2 x 31600
= 63200
Since 1 Skateboard ICE requires 2 wheel assembly, annual requirement of wheel assemblies = 2 x 63200 = 126400
However 1200 wheel assemblies are already in stock
Hence number of wheel assemblies which will be required annually = 126400 – 1200 = 125200
Answer to question 5 :
Annual demand for skateboard ICE
= 2 x ( Cumulative demand for period April to September)
= 2 x ( 4500 + 8000 + 10000 + 1900 + 4000 + 3200 )
= 2 x 31600
= 63200
Since 1 Skateboard ICE requires 2 wheel assembly and each wheel assembly requires 1 truck,
1 skateboard ICE requires 2 truck parts
Therefore , annual demand of truck parts = D = 2 X 63200 = 126400
Ordering cost = Co = $150
Inventory carrying cost = Cc = 10% of value of each truck part = 10% of $19 = $1.9
Therefore, Economic Order Quantity ( EOQ)
= Square root ( 2 x Co x D/ Cc)
= Square root ( 2 x 150 x 126400 /1.9)
= 4467.42 ( 4467 rounding to nearest whole number)
COMPANY SHOULD ORDER 4467 NUMBER OF TRUCK PARTS |
Answer to question #6:
Order quantity = 10,000 units
Total annual ordering cost, $
= Ordering cost x number of orders
= Ordering cost x Annual demand of truck parts/ Order quantity
= 150 x 126400/10000
= $1896
The discounted price ( after 5% discount) for each truck = 95% of $19 = $18.05
Total annual inventory holding cost , $
= Holding cost per unit per year x average inventory
= ( 10% of discounted price) x Order quantity /2
= ( 10% of $18.05) x 10000/2
= 1.805 x 5000
= $9025
Total annual material cost of truck parts = 126400 ( annual requirement) x $18.05 ( value per truck part) = $2281520
Total cost for truck parts
= Annual ordering cost + annual inventory holding cost + annual material cost
= $1896 + $9025 + $2281520
= $2292441
TOTAL COST OF TRUCK PARTS = $ 2292441 |