In: Finance
a company is considering a new 3-year expansion project that requires an initial fixed asset investment of $5.076 million. the fixed asset will be depreciated straight-line to zero over its 3-year tax life, after which time it will have a market value of $394,800. the project requires an initial investment in net working capital of $564000. the project estimated to generate $4512000 in annual sales, with costs of $1804800. the tax rate is 33 percent and the required return on the project is 18 percent. calculate npv and irr*** of this project. should the project be accepted or rejected?
| 1] | `Cost of fixed assets | $ 5,076,000 |
| +Increase in NWC | $ 564,000 | |
| =Initial investment | $ 5,640,000 | |
| 2] | Annual sales | $ 4,512,000 |
| -Annual costs | $ 1,804,800 | |
| -Depreciation [5076000/3] | $ 1,692,100 | |
| =NOI | $ 1,015,100 | |
| -Tax at 33% | $ 334,983 | |
| =NOPAT | $ 680,117 | |
| +Depreciation | $ 1,692,100 | |
| =Annual OCF | $ 2,372,217 | |
| 3] | After tax salvage value [394800*(1-33%)] | $ 264,516 |
| +Recovery of NWC | $ 564,000 | |
| After tax terminal cash inflow | $ 828,516 | |
| 4] | CALCULATION OF NPV: | |
| PV of annual OCF = 2372217*(1.18^3-1)/(0.18*1.18^3) = | $ 5,157,847 | |
| +PV of terminal cash inflows = 828516/1.18^3 = | $ 504,260 | |
| Total PV of cash inflows | $ 5,662,108 | |
| -Initial investment | $ 5,640,000 | |
| =NPV | $ 22,108 | |
| 5] | CALCULATION OF IRR: | |
| IRR is that discount rate for which NPV = 0 | ||
| It is to be found out by trial and error, by | ||
| discounting with different discount rates till 0 | ||
| NPV is reached. | ||
| Discounting with 19%: | ||
| PV of annual OCF = 2372217*(1.19^3-1)/(0.19*1.19^3) = | $ 5,076,347 | |
| +PV of terminal cash inflows = 828516/1.19^3 = | $ 491,654 | |
| Total PV of cash inflows | $ 5,568,001 | |
| -Initial investment | $ 5,640,000 | |
| =NPV | $ (71,999) | |
| IRR lies between 18% and 19% as 0 NPV would be | ||
| obtained between them. | ||
| By simple interpolation, IRR = 18%+1%*22108/(22108+71999) | 18.23% | |
| 6] | As the NPV is positive, the project should be | |
| accepted. |