In: Accounting
Question No. 3 (Marks 15)
Required:
Prepare the sale budget for the next year. (Marks 2)
The company has the following opening and required closing inventory levels.
PS units |
TG UNITS |
|
Opening inventory |
100 |
50 |
Required closing inventory |
1,100 |
50 |
Required:
Prepare the production budget for the coming year. (Marks 3)
Product 1 |
Product 2 |
|
Budgeted production in units |
2,700 |
4,100 |
Two types of labour are used in producing the three products. Standard times per unit and expected wage rates for the forthcoming year are shown below:
Product 1 |
Product 2 |
|
Hours per unit |
||
Skilled labour |
3 |
1 |
Semi-skilled labour |
4 |
4 |
Skilled labour is to be paid at the rate of $9/hour and semi-skilled labour at the rate of $6/hour.
Required:
Complete the following: (Marks 5)
Month |
Sales and production units |
December (actual) |
50,000 |
January (budget) |
55,000 |
February (budget) |
60,000 |
March (budget) |
65,000 |
In the past, the business has maintained its inventories of raw materials at 100,000 units. However, it plans to increase raw material inventories to 110,000 units at the end of January and 120,000 units at the end of February. The business takes one month’s credit from its suppliers.
Required:
Calculate the forecast payments to suppliers each month, for raw material purchases
SOLUTION
Que 3 (a) | ||
Sales Budget | ||
For the next Year | ||
PS | TG | |
Budgeted Sellling units (a) | 5000 | 1000 |
Price per unit (b) | $95 | $130 |
Total sales (a x b) | $475,000 | $130,000 |
Answer for the next que (a) | ||
Production Budget | ||
PS | TG | |
Budgeted sales in units | 5000 | 1000 |
Add: Desired ending inventory | 1100 | 50 |
Total needs | 6100 | 1050 |
Less: Beginning inventory | 100 | 50 |
REQUIRED PRODUCTION | 6000 | 1000 |
Answer for the next que (a) | |||
(i) Computation of Number of hours of skilled labor required & Total Cost of skilled labor | |||
Product 1 | Product 2 | Total | |
Budgeted production in units | 2700 | 4100 | 6800 |
Skilled labour hours required per unit | 3 | 1 | - |
Total skilled labor hours required (Budgeted production*Skilled labor hours per unit) | 8100 | 4100 | 12200 |
Rate per hour for skilled labor | $9 | $9 | $9 |
Cost of skilled labor (Total skilled hours required*Rate per hour) | $72,900 | $36,900 | $109,800 |
(i) Computation of Number of hours of Semiskilled labor required & Total Cost of Semi-skilled labor | |||
Product 1 | Product 2 | Total | |
Budgeted production in units | 2700 | 4100 | 6800 |
Semi-skilled labour hours required per unit | 4 | 4 | 4 |
Total semi-skilled labor hours required (Budgeted production*semi-skilled labor hours per unit) | 10800 | 16400 | 27200 |
Rate per hour for semi-skilled labor | $6 | $6 | $6 |
Cost of semi-skilled labor (Total semi-skilled hours required*Rate per hour) | $64,800 | $98,400 | $163,200 |