In: Finance
Suppose you have the following projected cash flows for a drone pizza delivery business: an initial investment cost of $2,300,000, and with expected net revenues of $850,000 each year for six years. If the required return for the risk of this project is 12%, then
What is the NPV of this project?
What is the Profitability Index for this project?
What is the Internal Rate of Return for this project?
What is the Payback Period of this project? Suppose the cut off period is 2 years.
Should you accept this project?
If applicable, show the formulas used to find these answers.
a | |||||||
Project | |||||||
Discount rate | 0.12 | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Cash flow stream | -2300000 | 850000 | 850000 | 850000 | 850000 | 850000 | 850000 |
Discounting factor | 1 | 1.12 | 1.2544 | 1.404928 | 1.5735194 | 1.762342 | 1.973823 |
Discounted cash flows project | -2300000 | 758928.6 | 677614.8 | 605013.2 | 540190.37 | 482312.8 | 430636.5 |
NPV = Sum of discounted cash flows | |||||||
NPV Project = | 1194696.22 | ||||||
Where | |||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||||
c | |||||||
Project | |||||||
PI= (NPV+initial inv.)/initial inv. | |||||||
=(1194696.22+2300000)/2300000 | |||||||
1.52 | |||||||
b | |||||||
Project | |||||||
IRR is the rate at which NPV =0 | |||||||
IRR | 0.288992281 | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Cash flow stream | -2300000 | 850000 | 850000 | 850000 | 850000 | 850000 | 850000 |
Discounting factor | 1.00E+00 | 1.288992 | 1.661501 | 2.141662 | 2.7605859 | 3.558374 | 4.586717 |
Discounted cash flows project | -2300000 | 659429.9 | 511585.6 | 396888 | 307905.65 | 238873.2 | 185317.8 |
NPV = Sum of discounted cash flows | |||||||
NPV Project = | 0.00% | ||||||
Where | |||||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | ||||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||||
IRR= | 28.90% | ||||||
d | |||||||
Project | |||||||
Year | Cash flow stream | Cumulative cash flow | |||||
0 | -2300000 | -2300000 | |||||
1 | 850000 | -1450000 | |||||
2 | 85000000.00% | -600000 | |||||
3 | 850000 | 250000 | |||||
4 | 85000000.00% | 1100000 | |||||
5 | 850000 | 1950000 | |||||
6 | 850000 | 2800000 | |||||
Payback period is the time by which undiscounted cashflow cover the intial investment outlay | |||||||
this is happening between year 2 and 3 | |||||||
therefore by interpolation payback period = 2 + (0-(-600000))/(250000-(-600000)) | |||||||
2.71 Years | |||||||
E
Reject the project as payback period is more than cutoff of 2 years