Question

In: Finance

The World Bank is considering an application from the country of Equatoria for a large dam...

The World Bank is considering an application from the country of Equatoria for a large dam project. In order to build this dam, villagers from an entire village will need to be relocated. In addition, there will be some watershed damage and ecological losses due to habitat destruction. Monetary costs and benefits for the dam project are given as follows:

Construction costs: $650 million at the beginning of the first year of the project. Construction costs for the start of the second year of the project will be 12% higher than the first year costs, and at the start of year 3 (the final year of construction) the costs will be 15% higher than the first year costs. Operating costs: $75 million/year (starting in year 3); and then increase to $80 million/year from year 8 onward Hydropower generated: 4 billion kilowatt hours/year (available from year 3) Price of electricity: $0.08/kilowatt hour Irrigation water available from the dam: 20 billion litres/year (available from year 3) Price of water: $0.008/litre Agricultural production lost from flooded lands: $54 million/year (loss from year 2)

Forestry production lost from flooded lands: $28 million/year (loss from year 2) Note: 1 billion = 1000 million  

You, as a consultant have been approached by the World Bank to carry out an analysis from which you will provide your recommendations.  

Your tasks: A. Calculate the NPV and the B/C using a real discount rate of 4.6%. Set up a basic template to complete your CBA. Put the variables in the clearly labeled cells above your Large Dam Project. Since we are given agricultural and forestry production losses, if we incorporate these we are automatically creating a ‘withwithout project’ analysis. Next complete your Large Dam Project with clearly labelled columns. Do this by creating formulae using your variables in the cells above. Always use formulae linked back to the data cells above so that if you wish to change a data cell value (for a sensitivity analysis) then all your calculations will automatically

2  

change. Once you have created a formula in one cell of a column you should be able to drag down so that it accurately duplicates the formula right down the column. To do the analysis I want you to complete the columns initially for 10 years of the project. However, we can assume that once built this dam will remain in place indefinitely. So to extend the analysis to cover the long term, follow these instructions:  

i) Underneath Yr 10 put Yr 11 to infinity (11 – infinity).

ii) Since the last few years have the same Net Cash Flow (NCF) and we do not have any further information, we can assume that the future NCFs will remain the same. This means that we can calculate the future NCFs based on these last NCFs and use the formula for a perpetuity that states: PV of all future expected cashflows = NCF/discount rate, (this effectively capitalizes the future NCFs)

iii) To create the formula for this in the NCF cell for yrs 11 – infinity (in your NCF column), use the NCF cell in year 9 and divide this value by the discount rate cell. (Use the year 9 NCF rather than the one in year 10, because you will shortly be changing the NCF entry in year 10). You have now calculated the PV of all future NCFs, to the beginning of year 11 (as this is the beginning point of yrs11-infinity).

iv) But you want your final PV to be today (year 0) not year 11. Remember that the beginning of year 11 is the same as the end of year 10, so now you can add this cell containing the large value for (NCF/disc. rate) into your calculation for the year 10 NCF. v) Your final column is where you calculate the PV(NCF)s – i.e. the PV of each entry in your NCF column.  

vi) Finally, sum your PV(NCF) column and this sum will give you your NPV. vii) Similarly, for your B/C you will need to calculate the PV(future Costs) and PV(future Bens) in a similar manner (as you did for the NCF) for years 11 – infinity. This is so that you capture all future streams of costs and also of benefits. Then finally calculate the NPV(Costs) and NPV(Benefits) so that you can use these to calculate your B/C.  

Also begin a Word doc. and for Part A. give the NPV(Large Dam) and also the B/C(Large Dam).

B. Now consider an alternative project: several smaller dams constructed to avoid flooding significant agricultural land or forested areas. For this project, total construction costs are exactly half the costs of the large dam project, while operating costs are two-thirds those of the large dam. Power and irrigation benefits are also half as much as those for the large dam. Agricultural land and forests are not affected and the project incurs no ecological or resettlement costs.  

(i) Calculate the NPV of this Smaller Dams Project using the discount rate of 4.6%. You already have all the variables set up (for the Large Dam project) so do not create new cells but work from the original cells. Conduct your analysis for the Smaller Dams Project on a new table beneath that for the Large Dam Project (using some or all the same columns). Label the Small Dams Project clearly (all on the one sheet of your spreadsheet file – this makes marking easier). Include the years 11 – infinity in your Small Dams analysis in exactly the same way as you did for the Large Dam project.

On your Word doc. for B.

(i) give the NPV(Smaller Dams).

(ii) Now you are to compare both projects under different discount rates. Set up a table with a column containing various discount rates, another column for the NPV for the Large Dam Project and a third column for the NPV for the Small Dams Project. Complete the table and use it to draw a graph that shows the changing NPVs plotted against the discount rate, for both projects on the one graph. Make sure your graph is properly labelled and has an appropriate title that contains your name. On your Word doc. for B (ii) if your decision regarding the two different dam projects were to be based solely on the CBAs calculated thus far, give the range of discount rates for which you would choose the Large Dam Project over the Smaller Dams Project, and vice versa.

(iii) For just the Large Dam Project, carry out this sensitivity analysis: Suppose the amount of hydropower generated was overestimated, and instead 3.2 billion kilowatt hours/year were generated and in addition, the price of electricity was $0.06/kilowatt hour and the price of water was $0.005/litre. Make these changes and make a note of the new NPV and B/C, and then return your analysis to its original numbers for handing in.

On your Word doc. for B

(iii), for the Large Dam Project give the NPV and B/C under this sensitivity analysis. In a sentence what would you say about this? Also explain what the B/C is predicting regarding our investment

C. Finally, in your Word document you are to evaluate the two projects, the Large Dam project (originally, before the sensitivity analysis) and the Smaller Dams project individually and then make comparison between the two. Your evaluation should include a discussion on the costs and benefits not quantified in your spreadsheet analyses. In this discussion make recommendations as to how you could incorporate these costs and benefits into your spreadsheet analysis. Conclude this analysis by giving your final recommendations to the World Bank. 600words

Solutions

Expert Solution

LARGE DAM PROJECT
Year 0 1 2 3 4 5 6 7 8 9 10
Construction costs -650 -728 -747.5
Operating costs -75 -75 -75 -75 -75 -80 -80 -80
Price of Hydropower(4000 mlns. *0.08) 320 320 320 320 320 320 320 320
Price of Water(20000 mlns.*0.008) 160 160 160 160 160 160 160 160
Agricultural prodn.lost -54 -54 -54 -54 -54 -54 -54 -54 -54
Forestry prodn.lost -28 -28 -28 -28 -28 -28 -28 -28 -28
PV of Yr.11-Infinity NCFs(318/4.6%) 6913.043
Net cash flows -650 -728 -829.5 323 323 323 323 323 318 318 7231.043
PV F at 4.6% 1 0.95602 0.91398 0.87379 0.83536 0.79862 0.76350 0.72992 0.69782 0.66714 0.63780
PV at 4.6% -650 -695.985 -758.146 282.23279 269.821 257.955 246.611 235.7658 221.9083 212.1495 4611.945
NPV 4234.258
Benefits
Price of Hydropower(4000 mlns. *0.08) 320 320 320 320 320 320 320 320
Price of Water(20000 mlns.*0.008) 160 160 160 160 160 160 160 160
PV of total price(320+160)for yrs. 11-to Infinity(480/4.6%) 10434.78
Total benefits 0 0 0 480 480 480 480 480 480 480 10914.78
PV F at 4.6% 1 0.956023 0.91398 0.8737857 0.835359 0.79862 0.763501 0.729925 0.697825 0.667137 0.637798
PV at 4.6% 0 0 0 419.41715 400.9724 383.339 366.4807 350.364 334.956 320.2256 6961.427
NPV of Benefits 9537.181
Costs
Construction costs -650 -728 -747.5
Operating costs -75 -75 -75 -75 -75 -80 -80 -80
Agricultural prodn.lost -54 -54 -54 -54 -54 -54 -54 -54 -54
Forestry prodn.lost -28 -28 -28 -28 -28 -28 -28 -28 -28
PV of total costs(80+54+28)for yrs. 11-to Infinity(162/4.6%) -3521.74
Total costs -650 -728 -829.5 -157 -157 -157 -157 -157 -162 -162 -3683.74
ie. 650 728 829.5 157 157 157 157 157 162 162 3683.739
PV F at 4.6% 1 0.956023 0.91398 0.8737857 0.835359 0.79862 0.763501 0.729925 0.697825 0.667137 0.637798
PV at 4.6% 650 695.9847 758.1463 137.18436 131.1514 125.384 119.8697 114.5982 113.0476 108.0761 2349.481
NPV of Costs 5302.924
B/C= NPV Benefits/ NPV Costs= 1.80
SMALLER DAMS PROJECT
Year 0 1 2 3 4 5 6 7 8 9 10
Construction costs -325 -364 -373.75
Operating costs -50 -50 -50 -50 -50 -53 -53 -53
Price of Hydropower(4000 mlns. *0.08/2) 160 160 160 160 160 160 160 160
Price of Water(20000 mlns.*0.008/2) 80 80 80 80 80 80 80 80
PV of Yr.11-Infinity NCFs(187/4.6%) 4065.217
Net cash flows -325 -364 -373.75 190 190 190 190 190 186.6667 186.6667 4251.884
PV F at 4.6% 1 0.95602 0.91398 0.87379 0.83536 0.79862 0.76350 0.72992 0.69782 0.66714 0.63780
PV at 4.6% -325 -347.992 -341.6 166.01929 158.7182 151.738 145.0653 138.6857 130.2607 124.5322 2711.843
NPV 2712.271
Benefits
Price of Hydropower(4000 mlns. *0.08/2) 160 160 160 160 160 160 160 160
Price of Water(20000 mlns.*0.008/2) 80 80 80 80 80 80 80 80
PV of total price(160+80)for yrs. 11-to Infinity(240/4.6%) 5217.391
Total benefits 0 0 0 240 240 240 240 240 240 240 5457.391
PV F at 4.6% 1 0.956023 0.91398 0.8737857 0.835359 0.79862 0.763501 0.729925 0.697825 0.667137 0.637798
PV at 4.6% 0 0 0 209.70857 200.4862 191.669 183.2404 175.182 167.478 160.1128 3480.713
NPV of Benefits 4768.591
Costs
Construction costs -325 -364 -373.75
Operating costs -50 -50 -50 -50 -50 -53 -53 -53
PV of total opg.costs 53 for yrs. 11-to Infinity(53/4.6%) -1152.17
Total costs -325 -364 -373.75 -50 -50 -50 -50 -50 -53.3333 -53.3333 -1205.51
ie. 325 364 373.75 50 50 50 50 50 53.33333 53.33333 1205.507
PV F at 4.6% 1 0.956023 0.91398 0.8737857 0.835359 0.79862 0.763501 0.729925 0.697825 0.667137 0.637798
PV at 4.6% 325 347.9924 341.6 43.689286 41.76796 39.9311 38.17507 36.49625 37.21733 35.58062 768.8701
NPV of costs 2056.32
B/C= NPV Benefits/ NPV Costs= 2.32
Diffferent discount rates--6%,8%,3.5%. 15%
LARGE DAM PROJECT
Net cash flows -650 -728 -829.5 323 323 323 323 323 318 318 7231.043
PV F at 6% 1 0.94340 0.89000 0.83962 0.79209 0.74726 0.70496 0.66506 0.62741 0.59190 0.55839
PV at 6% -650 -686.792 -738.252 271.19703 255.8463 241.364 227.7023 214.8134 199.5171 188.2237 4037.777
NPV of cash flow 3561.397
Total benefits 0 0 0 480 480 480 480 480 480 480 10914.78
PV F at 6% 1 0.94340 0.89000 0.83962 0.79209 0.74726 0.70496 0.66506 0.62741 0.59190 0.55839
PV at 6% 0 0 0 403.01726 380.205 358.684 338.3811 319.2274 301.1579 284.1113 6094.758
NPV of Benefits 8479.541
Total costs 650 728 829.5 157 157 157 157 157 162 162 3683.739
PV F at 6% 1 0.94340 0.89000 0.83962 0.79209 0.74726 0.70496 0.66506 0.62741 0.59190 0.55839
PV at 6% 650 686.7925 738.252 131.82023 124.3587 117.32 110.6788 104.414 101.6408 95.88755 2056.981
NPV of Costs 4918.145
NPV Benefits/NPV Costs(B/C) 1.72
SMALLER DAMS PROJECT
Net cash flows -325 -364 -373.75 190 190 190 190 190 186.6667 186.6667 4251.884
PV F at 6% 1 0.94340 0.89000 0.83962 0.79209 0.74726 0.70496 0.66506 0.62741 0.59190 0.55839
PV at 6% -325 -343.396 -332.636 159.52766 150.4978 141.979 133.9425 126.3609 117.117 110.4877 2374.23
NPV of cash flow 2313.11
Total benefits 0 0 0 240 240 240 240 240 240 240 5457.391
PV F at 6% 1 0.94340 0.89000 0.83962 0.79209 0.74726 0.70496 0.66506 0.62741 0.59190 0.55839
PV at 6% 0 0 0 201.50863 190.1025 179.342 169.1905 159.6137 150.579 142.0556 3047.379
NPV of Benefits 4239.771
Total costs -325 -364 -373.75 -50 -50 -50 -50 -50 -53.3333 -53.3333 -1205.51
PV F at 6% 1 0.94340 0.89000 0.83962 0.79209 0.74726 0.70496 0.66506 0.62741 0.59190 0.55839
PV at 6% -325 -343.396 -332.636 -41.98096 -39.6047 -37.3629 -35.248 -33.2529 -33.462 -31.5679 -673.149
NPV of   Costs -1926.66
NPV Benefits/NPV Costs(B/C) 2.20
Summary:
Discount Rates NPV B/C
Larger Smaller Larger Smaller
3.50% 4834.71 3068.19 1.86 2.41
4.60% 4234.26 2712.27 1.80 2.32
6% 3561.40 2313.11 1.72 2.20
8% 2750.68 1831.60 1.62 2.04
15% 890.20 722.55 1.27 1.52
iii.Sensitivity Analysis:
LARGE DAM PROJECT
Year 0 1 2 3 4 5 6 7 8 9 10
Construction costs -650 -728 -747.5
Operating costs -75 -75 -75 -75 -75 -80 -80 -80
Price of Hydropower(3200 mlns. *0.06) 192 192 192 192 192 192 192 192
Price of Water(20000 mlns.*0.005) 100 100 100 100 100 100 100 100
Agricultural prodn.lost -54 -54 -54 -54 -54 -54 -54 -54 -54
Forestry prodn.lost -28 -28 -28 -28 -28 -28 -28 -28 -28
PV of Yr.11-Infinity NCFs(130/4.6%) 2826.087
Net cash flows -650 -728 -829.5 135 135 135 135 135 130 130 2956.087
PV F at 4.6% 1 0.95602 0.91398 0.87379 0.83536 0.79862 0.76350 0.72992 0.69782 0.66714 0.63780
PV at 4.6% -650 -695.985 -758.146 117.96107 112.7735 107.814 103.0727 98.53987 90.71725 86.72777 1885.386
NPV 498.8616
Benefits
Price of Hydropower(4000 mlns. *0.08) 192 192 192 192 192 192 192 192
Price of Water(20000 mlns.*0.008) 100 100 100 100 100 100 100 100
PV of total price(320+160)for yrs. 11-to Infinity(292/4.6%) 6347.826
Total benefits 0 0 0 292 292 292 292 292 292 292 6639.826
PV F at 4.6% 1 0.956023 0.91398 0.8737857 0.835359 0.79862 0.763501 0.729925 0.697825 0.667137 0.637798
PV at 4.6% 0 0 0 255.14543 243.9249 233.198 222.9424 213.1381 203.7649 194.8039 4234.868
NPV of Benefits 5801.785
Costs
Construction costs -650 -728 -747.5
Operating costs -75 -75 -75 -75 -75 -80 -80 -80
Agricultural prodn.lost -54 -54 -54 -54 -54 -54 -54 -54 -54
Forestry prodn.lost -28 -28 -28 -28 -28 -28 -28 -28 -28
PV of total costs(80+54+28)for yrs. 11-to Infinity(162/4.6%) -3521.74
Total costs -650 -728 -829.5 -157 -157 -157 -157 -157 -162 -162 -3683.74
ie. 650 728 829.5 157 157 157 157 157 162 162 3683.739
PV F at 4.6% 1 0.956023 0.91398 0.8737857 0.835359 0.79862 0.763501 0.729925 0.697825 0.667137 0.637798
PV at 4.6% 650 695.9847 758.1463 137.18436 131.1514 125.384 119.8697 114.5982 113.0476 108.0761 2349.481
NPV of Costs 5302.924
B/C= NPV Benefits/ NPV Costs= 1.09
After sensitivity analysis as in iii.
NPV= 498.8616
B/C= 1.09
Both NPV & B/C Ratio predictions depend on the price of electricity & water
C..Decision:
At diff. discount rates , NPV is greater for larger dam alternative--but B/C ratio is higher for the smaller dams alternative.
Naturally ,as per mathematics, lower discount rates give higher NPVs & higher B/C ratio (the latter is derived from NPVs of benefits & costs--so naturally the discount rates will influence the final number.)
If the decision is to be based solely on NPV criteria, then larger dams are recommended.
If the decision is to be based solely on B/C ratio criteria, then smaller dams are recommended .
NPV gives the absolute $ value,whereas, B/C ratio, is all said, a relative figure & as seen above the NPV relevant to that alternative is always less than that of the larger-dam alternative.
When both NPV & B/C ratio, are combined to take a decision, the LARGER DAM alternative is RECOMMENDED irrespective of discount rates.

Related Solutions

The EPA is considering an application from the state of Colorado for a large dam project...
The EPA is considering an application from the state of Colorado for a large dam project on the Colorado River. The basic costs and benefits of the project (in inflation-adjusted dollar values) are as follows: Costs $900 million/year first three years Construction costs: Operating costs: $80 million/year Agricultural product lost from flooded lands: $65 million/year Forest products lost from flooded lands: $40 million/year Benefits Revenues from Power Generation Hydropower generated: 4 billion Kilowatt hours/year Price of electricity: $0.125/Kilowatt hour Revenues...
The EPA is considering an application from the state of Colorado for a large dam project...
The EPA is considering an application from the state of Colorado for a large dam project on the Colorado River. The basic costs and benefits of the project (in inflation-adjusted dollar values) are as follows: Costs $900 million/year first three years Construction costs: Operating costs: $80 million/year Agricultural product lost from flooded lands: $65 million/year Forest products lost from flooded lands: $40 million/year Benefits Revenues from Power Generation Hydropower generated: 4 billion Kilowatt hours/year Price of electricity: $0.125/Kilowatt hour Revenues...
The World Bank is considering whether to lend a country money to build a new water...
The World Bank is considering whether to lend a country money to build a new water supply project that will allow the country to increase its acreage of irrigated crops. The new irrigated crop acreage is expected to generate increases in exports amounting to $1,000 million annually in addition to increases in domestic food sales of $200 million annually. The water supply project will cost $5,000 million up front and $10 million a year for operation and maintenance. The World...
The national insurance commission for a developing country received a loan from the World Bank to...
The national insurance commission for a developing country received a loan from the World Bank to cover the cost of: a) a 2-week trip to the U.S. for 8 top officials of the commission, to observe and learn about insurance regulation in the U.S., and b) a follow-up training program to be held in the developing country for 25 mid-level managers in the insurance industry. Of the World Bank grant, some $30,000 was reserved to cover the cost of the...
How can a country that is not closely linked to the world economy have a large...
How can a country that is not closely linked to the world economy have a large beta?
The World Bank collected data on the percentage of GDP that a country spends on health...
The World Bank collected data on the percentage of GDP that a country spends on health expenditures ("Health expenditure," 2013) and also the percentage of women receiving prenatal care ("Pregnant woman receiving," 2013). The data for 14 countries where this information is available for the year 2011 are in following table (note: outlier data has been removed): Data of Health Expenditure versus Prenatal Care Health Expenditure (% of GDP) Prenatal Care (%) 3.7 54.6 5.2 93.7 5.2 84.7 10.0 100.0...
The World Bank collected data on the percentage of GDP that a country spends on health...
The World Bank collected data on the percentage of GDP that a country spends on health expenditures ("Health expenditure," 2013) and also the percentage of women receiving prenatal care ("Pregnant woman receiving," 2013). The data for the countries where this information is available for the year 2011 is in the table below: Health Expenditure (% of GDP) Prenatal Care (%) 9.6 47.9 3.7 54.6 5.2 93.7 5.2 84.7 10.0 100.0 4.7 42.5 4.8 96.4 6.0 77.1 5.4 58.3 4.8 95.4...
The World Bank collected data on the percentage of GDP that a country spends on health...
The World Bank collected data on the percentage of GDP that a country spends on health expenditures ("Health expenditure," 2013) and also the percentage of women receiving prenatal care ("Pregnant woman receiving," 2013). The data for the countries where this information is available for the year 2011 are in table #10.1.8. Find the correlation coefficient and coefficient of determination and then interpret both. Table #10.1.8: Data of Health Expenditure versus Prenatal Care Health Expenditure (% of GDP) Prenatal Care (%)...
The World Bank collected data on the percentage of GDP that a country spends on health...
The World Bank collected data on the percentage of GDP that a country spends on health expenditures ("Health expenditure," 2013) and also the percentage of women receiving prenatal care ("Pregnant woman receiving," 2013). The data for the countries where this information is available for the year 2011 are in following table: Data of Health Expenditure versus Prenatal Care Health Expenditure (% of GDP) Prenatal Care (%) 3.7 54.6 5.2 93.7 5.2 84.7 10.0 100.0 4.7 42.5 4.8 96.4 6.0 77.1...
The World Bank collected data on the percentage of GDP that a country spends on health...
The World Bank collected data on the percentage of GDP that a country spends on health expenditures ("Health expenditure," 2013) and also the percentage of woman receiving prenatal care ("Pregnant woman receiving," 2013). The data for the countries where this information are available for the year 2011 is in table #10.1.8. Create a scatter plot of the data and find a regression equation between percentage spent on health expenditure and the percentage of woman receiving prenatal care. Then use the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT