The Hunicut and Hallock Corporation makes two versions of the same basic file cabinet, the TOL (Top-of-the-line) five drawer file cabinet and the HQ (High-quality) five drawer filing cabinet. You are reviewing the MRP for the HQ file cabinet. The HQ file cabinet is made up of five drawers with each drawer requiring two bearings, one on each side. Complete the Materials Requirements Plan (MRP) below in order to answer the questions in the quiz.
HQ | 1 | 2 | 3 | 4 | |
Gross Requirements | 50 | 0 | 100 | 20 | |
Scheduled Receipts | 50 | ||||
Projected Available Balance | 22 On-hand |
||||
Net Requirements | |||||
Planned Order Receipt | |||||
Planned Order Release |
Lead Time = 1 period; Safety-stock = 10; Lot-size = multiples of 50
Drawers | 1 | 2 | 3 | 4 | |
Gross Requirements | |||||
Scheduled Receipts | 300 | 200 | |||
Projected Available Balance | 35 On-hand |
||||
Net Requirements | |||||
Planned Order Receipt | |||||
Planned Order Release |
Lead Time = 1 period; Safety-stock = 15; Lot-size = multiples of 100
Bearings | 1 | 2 | 3 | 4 | |
Gross Requirements | 100 | ||||
Scheduled Receipts | 595 | ||||
Projected Available Balance | 20 On-hand |
||||
Net Requirements | |||||
Planned Order Receipt | |||||
Planned Order Release |
Lead Time = 2 periods; Safety-stock = 10; Lot-size ≥ 450
MRP:
Particulars |
Period |
0 |
1 |
2 |
3 |
4 |
HQ OH =22 LT=1 SS=10 Q = Multiples of 50 |
Gross Requirements |
0 |
50 |
0 |
100 |
20 |
Scheduled Receipts |
0 |
50 |
0 |
0 |
0 |
|
Projected On-hand |
22 |
22 |
22 |
22 |
22 |
|
Net Requirements |
0 |
0 |
0 |
78 |
8 |
|
Planned Order Receipts |
0 |
0 |
0 |
100 |
50 |
|
Planned Order Releases |
0 |
0 |
100 |
50 |
0 |
|
Drawers OH =35 LT=1 SS=15 Q = Multiples of 100 |
Gross Requirements |
0 |
0 |
500 |
250 |
0 |
Scheduled Receipts |
0 |
300 |
200 |
0 |
0 |
|
Projected On-hand |
35 |
35 |
335 |
35 |
85 |
|
Net Requirements |
0 |
0 |
0 |
215 |
0 |
|
Planned Order Receipts |
0 |
0 |
0 |
300 |
0 |
|
Planned Order Releases |
0 |
0 |
300 |
0 |
0 |
|
Bearings OH =20 LT=2 SS=10 Q≥450 |
Gross Requirements |
0 |
0 |
600 |
100 |
0 |
Scheduled Receipts |
0 |
595 |
0 |
0 |
0 |
|
Projected On-hand |
20 |
20 |
615 |
15 |
365 |
|
Net Requirements |
0 |
0 |
0 |
85 |
0 |
|
Planned Order Receipts |
0 |
0 |
0 |
450 |
0 |
|
Planned Order Releases |
0 |
450 |
0 |
0 |
0 |
Formula:
Net requirements = Gross requirements – On hand inventory – Scheduled receipts.