Question

In: Finance

Projects A and B have first costs of $5000 and $9000, respectively. Project A has net...

Projects A and B have first costs of $5000 and $9000, respectively. Project A has net annual benefits of $2500 during each of its 5-year useful life, after which it can be replaced identically. Project B has net annual benefits of $3300 during each year of its 10-year life.  Use Present Worth analysis, an interest rate of 30% per year, and a 10-year analysis period to determine which project to select. Please provide the present worth of the best alternative.

(show all equations)

Solutions

Expert Solution

Project A
Discount rate 0.3
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -5000 2500 2500 2500 2500 -2500 2500 2500 2500 2500 2500
Discounting factor 1 1.3 1.69 2.197 2.8561 3.71293 4.826809 6.274852 8.157307 10.6045 13.78585
Discounted cash flows project -5000 1923.077 1479.29 1137.915 875.31949 -673.323 517.9405 398.4158 306.4737 235.749 181.3454
NPV = Sum of discounted cash flows
NPV Project A = 1382.2
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 0.3
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -9000 3300 3300 3300 3300 3300 3300 3300 3300 3300 3300
Discounting factor 1 1.3 1.69 2.197 2.8561 3.71293 4.826809 6.274852 8.157307 10.6045 13.78585
Discounted cash flows project -9000 2538.462 1952.663 1502.048 1155.4217 888.7859 683.6815 525.9088 404.5453 311.1887 239.3759
NPV = Sum of discounted cash flows
NPV Project B = 1202.08
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

Project A is best as it has higher NPV (present worth)


Related Solutions

Projects A and B have the following cash flows: year A B 0 -5000 -5000 1...
Projects A and B have the following cash flows: year A B 0 -5000 -5000 1 2000 5000 2 0 1500 3 3000 1500 4 5000 1500 What is the IRR of the project A? Please write an answer in decimals. For example, 12.34% would be 0.1234. Also, round your answer to the fourth decimal.
Consider a project that costs $5000 and has an expected future cash flow of $1000 per...
Consider a project that costs $5000 and has an expected future cash flow of $1000 per year for 20 years. If we wait one year, the cost will increase to $5500 and the expected future cash flow will increase to $1200. If the required return is 13%, should we accept the project? If so, when should we begin? Thank you.
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows...
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows of CF0, CF1, CF2, CF3, CF4, CF5. (Years 0-5). Project B has cash flow of CF0, CF1, CF2, CF3. The discount rate for the projects is 10.5%. a) Analyze these two projects and recommend a project to accept. b) Carefully outline all your analysis and reasoning and discuss your methodologies for arriving at your solution in detail. Project A Project B CF0 (4,650.00) (8,300.00)...
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4...
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4 CFA −$2,050    $750    $760    $770    $780 CFB −$4,300 $1,500 $1,518 $1,536 $1,554 Both projects have a required return of 10.25%. What are NPV and IRR of the two projects? If project A and B are mutually exclusive, what is your decision with regard to accepting vs. rejecting each project? Why? What is the crossover rate?
Two equipments A and B have initial costs of $100,000 and $120,000 and expected to generate annual savings during the first year of $88,000 and $98,000 respectively.
Two equipments A and B have initial costs of $100,000 and $120,000 and expected to generate annual savings during the first year of $88,000 and $98,000 respectively. The value of these annual savings is expected to increase by 10% per year (over previous period). Assume service life of 2 years, operating hours per year of 4500, Use the NPW method to determining 5 savings/ hour for each equipment. Select the optimal equipment based on your results.  
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B....
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B. Each lasts for one time period and the firm has no other projects. Project A will result in a cash flow of £27 million in the good state and £10 million in the bad state. Each outcome is equally likely. Project B will result in a cash flow of £34 million in the good state and zero in the bad state. Each outcome is...
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000....
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000. 1 600. 800. 2 800. 600. 3 1,200. 200. 4 Each project has a cost of $ 2,000 and the total cost of capital is 10%. Determine which project should be accepted ?Using Net present value (NPV)
1. a) What is the net present value of a project that has upfront costs of...
1. a) What is the net present value of a project that has upfront costs of $5 million and pays end of the year cash flows of $1 million in one year, $2 million in two years, and $3 million in three years if the annual discount rate for the project is 3 percent? Show how much money you would have at the end of three years if you bought the project and what you would have instead if you...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT