  1. On January 1, 2017, Spartan Company signed a $240 million contract with the City of Amherst to construct a new city hall. Spartan expects to construct the building within two years and incur total expenses of $180 million. Spartan incurred $72 million in construction costs during 2017 and the remaining $108 million in 2018. Using the percentage-of-completion method, how much revenue should Spartan recognize in 2017?

Solutions

Expert Solution

  • Total cost = $ 180 millions
  • Cost incurred in 2017 = $ 72 millions
  • Percentage completed in 2017 = $72 million / 180 millions = 40%
  • Answer:
    Revenue to be recognised in the year 2017 = $ 240 million contract revenue x 40% = $ 96 millions
  • Final Answer value = $ 96 millions or $ 96,000,000

Related Solutions

On January 1 of year 1, Falk Company signed a contract to lease space in a...
On January 1 of year 1, Falk Company signed a contract to lease space in a building for 3 years. The lease contract calls for annual (prepaid) rental payments of $141,000 on each January 1 throughout the life of the lease and for the lessee to pay for all additions and improvements to the leased property. Present value of the three lease payments is $392,400. Required: 1. Assume the lease is accounted for as a finance lease. Prepare entries for...
On January 1, 2020, the company signed on a lease contract which qualifies as finance lease....
On January 1, 2020, the company signed on a lease contract which qualifies as finance lease. It calls for annual payments of $52,538 at 1/1/2020 for the first payments, and 12/31 of each year thereafter over a six-year lease term. The present value of total lease payment is $280,000 under 5% annual interest rate. Make journal entries for each of following dates, including any interest or amortization expenses. January 1, 2020, signs the lease contract and makes the first payment...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and warehouse for a small wholesale company. The project was originally expected to be completed in two years, but difficulties in hiring a sufficient pool of skilled workers extended the completion date by an extra year. As well, significant increases in the price of steel in the second year resulted in cost overruns on the project. Capsule Corp. was able to negotiate a partial recovery...
On January 1, 2017, Loud Company enters into a 2-year contract with a customer for an...
On January 1, 2017, Loud Company enters into a 2-year contract with a customer for an unlimited talk and 5 GB data wireless plan for $65 per month. The contract includes a smartphone for which the customer pays $299. Loud also sells the smartphone and monthly service plan separately, charging $649 for the smartphone and $65 for the monthly service for the unlimited talk and 5 GB data wireless plan. On July 1, 2017, the customer realizes that she needs...
On January 1, 2017, Loud Company enters into a 2-year contract with a customer for an...
On January 1, 2017, Loud Company enters into a 2-year contract with a customer for an unlimited talk and 5 GB data wireless plan for $65 per month. The contract includes a smartphone for which the customer pays $299. Loud also sells the smartphone and monthly service plan separately, charging $649 for the smartphone and $65 for the monthly service for the unlimited talk and 5 GB data wireless plan. Required: 1. Calculate the transaction price for the smartphone and...
On January 1, 2017, Loud Company enters into a 2-year contract with a customer for an...
On January 1, 2017, Loud Company enters into a 2-year contract with a customer for an unlimited talk and 5 GB data wireless plan for $65 per month. The contract includes a smartphone for which the customer pays $299. Loud also sells the smartphone and monthly service plan separately, charging $649 for the smartphone and $65 for the monthly service for the unlimited talk and 5 GB data wireless plan. Required: 1. Calculate the transaction price for the smartphone and...
Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with...
Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with Pear Ltd to build a factory. The contract price was $ 12,000,000. The relevant information is as follows: Financial year ending 30 June: Construction costs for year Billings and payments for year 2018 $ 3,500,000 $ 3,000,000 2019 $ 5,000,000 $ 5,000,000 2020 $ 1,500,000 $ 4,000,000 Pear Ltd will be in control of the asset throughout the construction process. The contract is completed...
In 2018, a football player signed a contract reported to be worth $75.3 million. The contract...
In 2018, a football player signed a contract reported to be worth $75.3 million. The contract was to be paid as $10.7 million in 2018, $11.7 million in 2019, $13.1 million in 2020, $13.2 million in 2021, $13.2 million in 2022, and $13.4 million in 2023. If the appropriate interest rate is 8 percent, what kind of deal did the player snag? Assume all payments are paid at the end of the year. (Do not round intermediate calculations and enter...
In 2015, a baseball player signed a contract reported to be worth $98.5 million. The contract...
In 2015, a baseball player signed a contract reported to be worth $98.5 million. The contract was to be paid as $14.7 million in 2015, $14.9 million in 2016, $17.1 million in 2017, $17.2 million in 2018, $17.2 million in 2019, and $17.4 million in 2020. If the appropriate interest rate is 9 percent, what kind of deal did the player snag? Assume all payments are paid at the end of the year. (Enter your answer in dollars, not millions...
Your company has just signed a​ three-year nonrenewable contract with the city of New Orleans for...
Your company has just signed a​ three-year nonrenewable contract with the city of New Orleans for earthmoving work. You are investigating the purchase of heavy construction equipment for this job. The equipment costs ​$203,000 and qualifies for​ five-year MACRS depreciation. At the end of the​ three-year contract, you expect to be able to sell the equipment for ​$74,000. If the projected operating expense for the equipment is ​$68,000 per​ year, what is the​ after-tax equivalent uniform annual cost​ (EUAC) of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT