Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products.

Blender Electric Mixer
Direct material $ 22 $ 37
Direct labor 16 29
Manufacturing overhead @ $46 per machine hour 46 92
Cost if purchased from an outside supplier 64 109
Annual demand (units) 24,000 36,000

Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $34. Kitchen Magician’s management has a policy of filling all sales orders, even if it means purchasing units from outside suppliers.

Required:

  1. If 58,000 machine hours are available, and management desires to follow an optimal strategy, how many units of each product should the firm manufacture? How many units of each product should be purchased?
  2. With all other things constant, if management is able to reduce the direct material for an electric mixer to $22 per unit, how many units of each product should be manufactured? Purchased?

Solutions

Expert Solution

Solution 1:

Computation of contribution margin per grinding minute
Blender Electric Mixer
Cost if purchased from an outside supplier $64.00 $109.00
Variable costs:
Direct materials $22.00 $37.00
Direct labor $16.00 $29.00
Variable Overhead (Total Overhead- $34 per Hour) $12.00 $24.00
Total variable costs $50.00 $90.00
Total Saving per unit $14.00 $19.00
Machine Hours per unit 1 2
Contribution margin per Machine Hour $14.00 $9.50
Rank 1 2
Units of each product to be produced
Machine hours per unit Units to be produced
Blender 1.00 24000
Electric Mixer (58000-24000)/ 2 2.00 17000
Units Purchased
Blender 0
Electric Mixer (36000-17000) 19000

Solution 2:

Computation of contribution margin per grinding minute
Blender Electric Mixer
Cost if purchased from an outside supplier $64.00 $109.00
Variable costs:
Direct materials $22.00 $22.00
Direct labor $16.00 $29.00
Variable Overhead (Total Overhead- $34 per Hour) $12.00 $24.00
Total variable costs $50.00 $75.00
Total Saving per unit $14.00 $34.00
Machine Hours per unit 1 2
Contribution margin per Machine Hour $14.00 $17.00
Rank 2 1
Units of each product to be produced
Machine hours per unit Units to be produced
Blender 1.00 0
Electric Mixer (58000/2) 2.00 29000
Units Purchased
Blender 24000
Electric Mixer (36000-29000) 7000

Related Solutions

Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct Material $26 $45 Direct Labor $20 $33 Manufacturing overhead @ $54 per machine hour $54 $108 Cost if purchased from an outside supplier $68 $116 Annual demand (units) $28,000 $34,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $42. Kitchen Magician's management has a policy of filling all sales orders, even...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct Material $26 $45 Direct Labor $20 $33 Manufacturing overhead @ $54 per machine hour $54 $108 Cost if purchased from an outside supplier $68 $116 Annual demand (units) $28,000 $34,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $42. Kitchen Magician's management has a policy of filling all sales orders, even...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 18 $ 28 Direct labor 11 39 Manufacturing overhead @ $46 per machine hour 46 92 Cost if purchased from an outside supplier 65 133 Annual demand (units) 34,000 40,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $23. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 21 $ 30 Direct labor 14 42 Manufacturing overhead @ $52 per machine hour 52 104 Cost if purchased from an outside supplier 71 140 Annual demand (units) 37,000 46,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $26. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 17 $ 26 Direct labor 10 38 Manufacturing overhead @ $44 per machine hour 44 88 Cost if purchased from an outside supplier 64 132 Annual demand (units) 33,000 38,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $22. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 17 $ 26 Direct labor 10 38 Manufacturing overhead @ $44 per machine hour 44 88 Cost if purchased from an outside supplier 64 132 Annual demand (units) 33,000 38,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $22. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 22 $ 32 Direct labor 15 43 Manufacturing overhead @ $54 per machine hour 54 108 Cost if purchased from an outside supplier 75 146 Annual demand (units) 38,000 45,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $27. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 22 $ 32 Direct labor 15 43 Manufacturing overhead @ $54 per machine hour 54 108 Cost if purchased from an outside supplier 75 146 Annual demand (units) 38,000 45,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $27. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Direct...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Direct material $ 26 $ 45 Direct labor 20 33 Manufacturing overhead @ $54 per machine hour 54 108 Cost if purchased from an outside supplier 68 116 Annual demand (units) 28,000 34,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $42. Kitchen Magician’s management has a policy of filling all sales orders, even if...
Chef Gourmet, Inc., has assembled the following data pertaining to its two most popular products. Blender...
Chef Gourmet, Inc., has assembled the following data pertaining to its two most popular products. Blender Food Processor   Direct material $ 24 $ 41   Direct labor 18 31   Manufacturing overhead @ $50 per machine hour 50 100   Cost if purchased from an outside supplier 66 114   Annual demand (units) 26,000 30,000      Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $36. Management has a policy of filling all sales orders, even...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT