An emergency change was made to an IT system as a result of a failure. Which of the following should be of GREATEST concern to the organization's information security manager?
A. The change did not include a proper assessment of risk.
B. Documentation of the change was made after implementation.
C. The information security manager did not review the change prior
to implementation.
D. The operations team implemented the change without regression
testing.
Correct Answer: ???????????????
___________________________________
Note
Not sure if regression testing is a security concern. B maybe the answer??
Question:
An emergency change was made to an IT system as a result of a
failure. Which of the following should be of GREATEST concern to
the organization's information security manager
Ans: The
operations team implemented the change without regression
testing.
(Feel free to drop me a comment, If you need any help)