Question

In: Operations Management

1. This study (work sampling*) is focusing on machine operations. Using the following data, Categorize the...

1. This study (work sampling*) is focusing on machine operations. Using the following data,

  1. Categorize the events into the interesting activities such as machine idle (I), machine servicing (S).

    Observed Data

    Categorize

            √

    S (Service)

    I (Idle)

    Number of Observation

    Machine Running

    S or I

    222

    Remove Scrap

    S or I

    48

    Change tool

    S or I

    17

    Change material

    S or I

    60

    Adjust die

    S or I

    23

    Wait for maintenance service

    S or I

    53

    Wait for next material

    S or I

    25

  2. What % (p) of the time Machine is down (not idle but “serviced by the operator”) roughly?
  3. An analyst determined that the machining time (Tm) per piece was 40min. What is the actual production for the one machine supervised by one operator for an 8-hour shift given the above conditions?
  4. What is the unit cost ? The operator is paid $10.00/hr and each machine costs $20.00/hr for power and supplies.
  5. Since there is so much lost production due to idle time, management is considering assigning another machine to the first operator. There are three approaches or choices: i) Assign Machines #1 to the first operator and Machines #2 to the second operator, or ii) have both operators help each other and service all two machines as needed. iii) Assign Machines #1 and #2 to the first operator and don’t assign a second operator. Which choice is best, i.e. lowest unit cost?

Solutions

Expert Solution

ANSWER :

a)

Machine Idle (I): these are the events during which neither the machine is operating nor it is getting serviced. So there are two processes when machine was ideal.

Machine Ideal events = wait for maintenance service + wait for next material = 53 + 25 = 78 observations

Machine servicing (S): These are the events when machine goes through overhaul activities.

Machine servicing (S) = Remove scrap + change tool + change material + adjust die

Machine servicing (S) = 48 + 17 + 12 + 23 = 100 observations

b)

Machine service (S) = Remove scrap + change tool + change material + adjust die

Machine service (S) = 48 + 17 + 60 + 23 = 148 observations.

Total machine observations = 222 + 48 + 17 + 60 + 23 + 53 + 25 = 448 observations.

Percent of time machine is down (Not Idle but serviced by the operator):

P% = [Machine service (S) / Total machine observations] x 100 percent

P % = [148/448] x 100 %

P% = 33.03 Percent


c)

Machine time per piece = 40 Min

Supervisor time = 8 hour per shift

Actual production for one machine = machine capacity

= operating hours x operating rate x number of machines

= (40/60) Hours x 8 hours per shift x 1

= 5.36

Thus actual production for one machine is approximately 5 units.


d)

Unit cost = [operator’s payment + machine cost for power and supplies] / total units produced per hour

Unit cost = [$10 + $20] / 5.36

Unit Cost = 30 / 5.36 = $5.6


e)

Assign machine 1 to first operator and machine 2 to second operator = unit cost of machine 1 and unit cost of machine 2

= {[$10 + $20] / 5.36} + {[$10 + $20] / 5.36}

Unit cost = $11.2

Have both operators help each other and service all two machines as needed. This choice will result into no production in the event of both the machine breakdown

Unitl cost = [$10 + $20] for operator 1 + [$10 + $20] for operator 2

Unit cost = $60

Assign machine 1 & 2 to the first operator and don’t assign second operator = unit cost of machine 1 and 2 keeping operator constant

= {$10 + ($ 20 x 2)} / 5.36

Unit cost = $9.32

Thus from above calculations, Third choice is the best where machine 1 & 2 is assigned to the first operator and second operator is not assigned with the machine since the unit cost of this choice is $9.32 which is less than the unit cost of other two choices.


Related Solutions

Question 4: Using the compensation data, categorize the data into 13 categories, beginning with $400,000 <...
Question 4: Using the compensation data, categorize the data into 13 categories, beginning with $400,000 < x < $800,000, $800,000 < x < $1,200,000, etc. (6 pts.) CEO Total Comp Frequency       400,000       800,000    1,200,000    1,600,000    2,000,000    2,400,000    2,800,000    3,200,000    3,600,000    4,000,000    4,400,000    4,800,000    5,200,000 I cannot provide the DATA because it dont let me post the question otherwise you can use any data just show me the...
1. The following data resulted from a study taken on a horizontal milling machine: Pieces produced...
1. The following data resulted from a study taken on a horizontal milling machine: Pieces produced per cycle: 8. Average measured cycle time: 8.36 minutes. Average measured effort time per cycle: 4.62 minutes . Average rapid traverse time: 0.08 minutes. Average cutting time power feed: 3.66 minutes. Performance rating: 115 percent. Allowance (machine time): 10 percent . Allowance (manual time): 15 percent. The operator works on the job a full eight-hour day and produces 380 pieces. How many standard hours...
Discuss the advantages of using work sampling to understand how employees allocate their time among work...
Discuss the advantages of using work sampling to understand how employees allocate their time among work activities.
The following data was calculated during a study on credit card debt. Using the following data,...
The following data was calculated during a study on credit card debt. Using the following data, how would we interpret the results if the significance level was 1%? A business loan officer would like to test the claim that the average amount of credit card debt for a small business is greater than 3.9 thousand dollars. The test statistic is calculated as t0=1.48 The p-value is between 0.05 and 0.10. Select the correct answer below: A, Fail to reject H0....
1) Find out the standard time using the following data: Average time for machine elements =...
1) Find out the standard time using the following data: Average time for machine elements = 6 min. Average time for manual elements = 4 min. Performance rating = 110% Allowances = 10% of normal time 2) The actual observed time for an operation was 1 minute per piece. If the performance rating of the operator was 120 and a 5 per cent personal time is to be provided, the standard time in minute per piece is:
home / study / business / operations management / operations management questions and answers / Using...
home / study / business / operations management / operations management questions and answers / Using The Case Analysis Below. Analyze The Case “Why Uber Can't Make Money” About 2400 ... Your question has been answered Let us know if you got a helpful answer. Rate this answer Question: Using the Case analysis below. analyze the case “Why Uber Can't Make Money” about 2400 words in l... Using the Case analysis below. analyze the case “Why Uber Can't Make Money”...
1. Using the following data, find the.. (show work) a. mean b. median c. mode d....
1. Using the following data, find the.. (show work) a. mean b. median c. mode d. range e. standard deviation 936 928 924 880 934 923 878 930 936 2. Make a box-plot for the following data: 34 36 39 43 51 53 62 63 73 79 3. The blood pressure of 40 women have a mean of 110.8 mm hg and a standard deviation of 17.1 mm hg. Is a measurement of 181 mm hg unusual?
The following data resulted from a study taken on a horizontal milling machine: Pieces produced per...
The following data resulted from a study taken on a horizontal milling machine: Pieces produced per cycle: 8. Average measured cycle time: 8.36 minutes. Average measured effort time per cycle: 4.62 minutes. Average rapid traverse time: 0.08 minutes. Average cutting time power feed: 3.66 minutes. Performance rating: 115 percent. Allowance (machine time): 10 percent. Allowance (manual time): 15 percent. The operator works on the job a full eight-hour day and produces 380 pieces. How many standard hours does the operator...
Using the data provided in the excel file, show all of your work for the following...
Using the data provided in the excel file, show all of your work for the following calculations: a.) mean temperature of unmixed reagents (oC) b.) δελταT from graph (oC) c.) q absorbed by reaction mixture (J) d.) q absorbed by calorimeter, stirrer, and thermometer (J) e.) q total absorbed (J) f.) q total released (J) g.) calculation to show limiting reagent h.) deltaH neutralization for the reaction (kJ/mole of acid) A student reacted 100.0 mL of 0.9800 M HCl with...
A company bought a machine on January 1, 2017 for use in operations. The machine cost...
A company bought a machine on January 1, 2017 for use in operations. The machine cost $35,000 and the estimated residual value was $3,000. The machine has useful life of 3 years and produced 15,000 during 2017, 20,000 units during 2018 and 25,000 during 2019. Compute the depreciation expense under the straight line method for 2017, 2018 and 2019. Compute the depreciation under the units of production method for 2017, 2018 and 2019. Compute the depreciation under the double declining...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT