In: Operations Management
1. This study (work sampling*) is focusing on machine operations. Using the following data,
Observed Data |
Categorize √ S (Service) I (Idle) |
Number of Observation |
Machine Running |
S or I |
222 |
Remove Scrap |
S or I |
48 |
Change tool |
S or I |
17 |
Change material |
S or I |
60 |
Adjust die |
S or I |
23 |
Wait for maintenance service |
S or I |
53 |
Wait for next material |
S or I |
25 |
ANSWER :
a)
Machine Idle (I): these are the events during which neither the machine is operating nor it is getting serviced. So there are two processes when machine was ideal.
Machine Ideal events = wait for maintenance service + wait for next material = 53 + 25 = 78 observations
Machine servicing (S): These are the events when machine goes through overhaul activities.
Machine servicing (S) = Remove scrap + change tool + change material + adjust die
Machine servicing (S) = 48 + 17 + 12 + 23 = 100 observations
b)
Machine service (S) = Remove scrap + change tool + change material + adjust die
Machine service (S) = 48 + 17 + 60 + 23 = 148 observations.
Total machine observations = 222 + 48 + 17 + 60 + 23 + 53 + 25 = 448 observations.
Percent of time machine is down (Not Idle but serviced by the operator):
P% = [Machine service (S) / Total machine observations] x 100 percent
P % = [148/448] x 100 %
P% = 33.03 Percent
c)
Machine time per piece = 40 Min
Supervisor time = 8 hour per shift
Actual production for one machine = machine capacity
= operating hours x operating rate x number of machines
= (40/60) Hours x 8 hours per shift x 1
= 5.36
Thus actual production for one machine is approximately 5 units.
d)
Unit cost = [operator’s payment + machine cost for power and supplies] / total units produced per hour
Unit cost = [$10 + $20] / 5.36
Unit Cost = 30 / 5.36 = $5.6
e)
Assign machine 1 to first operator and machine 2 to second operator = unit cost of machine 1 and unit cost of machine 2
= {[$10 + $20] / 5.36} + {[$10 + $20] / 5.36}
Unit cost = $11.2
Have both operators help each other and service all two machines as needed. This choice will result into no production in the event of both the machine breakdown
Unitl cost = [$10 + $20] for operator 1 + [$10 + $20] for operator 2
Unit cost = $60
Assign machine 1 & 2 to the first operator and don’t assign second operator = unit cost of machine 1 and 2 keeping operator constant
= {$10 + ($ 20 x 2)} / 5.36
Unit cost = $9.32
Thus from above calculations, Third choice is the best where machine 1 & 2 is assigned to the first operator and second operator is not assigned with the machine since the unit cost of this choice is $9.32 which is less than the unit cost of other two choices.