In: Finance
Answer-A:
Accounting Brak-even point is the point at which business generates zero profit or suffer no loss. It can be calculated as under:
BEP = Fixed Cost /Contribution Per Unit
Step-1: Calculation of Fixed Cost of Project
Fixed Cost= $14 Million + Depreciation
Deprecition (using SLM) = Cost of Project - Residual Value / Economic Life of Project
= (66 - 6)/ 10 = 6 Million
Fixed Cost = 14 + 6 = $20 Million
Step 2: Calculation of Contribution Per Unit:
Contribution per Unit = Sale Price per Unit - Variable Cost per Unit
= 64 - 24 = $ 40 per unit
Step: 3 Calculation of Accounting BEP:
= 20,000,000 / 40 = 500,000 units
Answer-b:
DOL, DFL, DCL are the concepts based on the marginal costing system, so first calculate the profit using marginal costing as follow:
Sales (1800000 * 64) |
115200000 |
Less: Variable Cost (1800000 * 24) |
43200000 |
Contribution |
72000000 |
Less: Fixed Cost |
20000000 |
EBIT |
52000000 |
Less: Interest Payment (20.40 million * 6.28%) |
1281120 |
EBT |
50718880 |
Less: Tax (50718880 * 25%) |
12679720 |
EAT |
38039160 |
Degree of Operating Leverage = Contribution / EBIT = 72000000/52000000 = 1.38
Degree of Financial Leverage = EBIT / EBT = 52000000/50718880 = 1.02
Degree of Combined Leverage = DOL * DFL = 1.38 * 1.02 = 1.41
Answer- C: NPV Break Even Point is the point at which NPV of the project will be zero, It can be calculated using following formula:
EAC + (Annual Fixed Cost * (1 – Tc) – (Annual Depreciation * Tc) / ( Sale Price – Variable Cost)
Step- 1: EAC is the annual equivalent cost of the intial investment in project. It is calculated by dividing the intial investment by the annuity factor equal to economic life of project discount at the rate of cost of project:
Initial Investment= 66,000,000
Annuity Factor (10 years, discounted @14%) = 5.2161
EAC = 66,000,000/5.2161 =12,653,131.65
Step-2: Calculate after tax annual fixed cost of the project:
Annual fixed cost excluding depreciation = 14,000,000
Corporate Tax = 25%
After tax Annual Fixed Cost = 14,000,000 (1 – 25%) = 10,500,000
Step 3: Calculate annual tax savings on depreciation of the project:
Annual depreciation = 6,000,000
Tax rate = 25%
Annual Savings = 6,000,000 * 25% = 1,500,000
NPV BEP = (12,653,131.65 + 10,500,000 - 1,500,000) / (64 – 24)
= 21,653,131.65 / 40 = 541,328 units