Question

In: Finance

An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown as follows.

 An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown as follows. Identify the range of costs of capital that a firm would use to accept and reject this project.

image.png

 The point at which the NPV profile intersects the horizontal axis represents the _______ .

Solutions

Expert Solution

NPV is the difference between the present value of cash inflows and the present value of cash outflows over a period of time. Now, in capital budgeting decision making, a positive NPV is desirable and it is assumed to add value to the firm. In case of a negative NPV, it erodes the value of firm.

Now, in question above,

Green color area represent area of positive NPV - project can be ACCEPTED there

Purple color area represent area of negative NPV - project should be REJECTED there

the point at which the NPV profile intersects horizontal axis represented the IRR. Point of intersection is zero NPV and IRR is the cost of capital at which NPV is zero.


Related Solutions

A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the...
A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's -( payback, MIRR, IRR ?)(where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the--------? of the differences in the projects' cash flows (Project Delta). A _______? NPV profile indicates that increases in the cost...
What is the project's NPV.
What is the project's NPV.
Based on the NPV Profile Shown Below, what is the approximate internal rate of return (IRR)?...
Based on the NPV Profile Shown Below, what is the approximate internal rate of return (IRR)? You work for a company whose primary long term financial goal is to undertake projects that maximize company value. You have been asked to provide a recommendation with respect to ranking three mutually exclusive projects. The first project has a NPV of $200K and an IRR of 10%; the second has a NPV of $180K and an IRR of $12%; the third has a...
If the IRR for a project is 20%, then the project's NPV would be:
If the IRR for a project is 20%, then the project's NPV would be:
In what types of situations would capital budgeting decisions be made solely on the basis of project's net present value (NPV)?
In what types of situations would capital budgeting decisions be made solely on the basis of project's net present value (NPV)? Identify potential reasons that might drive higher NPV for a given project. Substantiate your response by providing an example to explain your thought process.
What are the pros and cons of the various capital budgeting decision methods (NPV, IRR, MIRR,...
What are the pros and cons of the various capital budgeting decision methods (NPV, IRR, MIRR, PB, DPB)? If you had to pick one method to use for all project valuation situations, which one would you pick, and why? Please explain your answer! I am trying to understand the concept.
NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV...
NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV profile. Hint​: Be sure to use a discount rate of zero for one intercept ​(y​-axis) and solve for the IRR for the other intercept ​(x​-axis). Year 0   -$250,000 Year 1   $49,000 Year 2   $80,000 Year 3   $114,000 Year 4   $139,000 What is the NPV of Project​ L-2 where zero is the discount​ rate? What is the IRR of Project​ L-2? Which of the graphs...
Q1. A project's base case or most likely NPV is $44,000, and assume its probability of...
Q1. A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is 85% higher than the base case and assume the worst scenario NPV is 35% lower than the base case. Both the best case scenario and the worst case scenario have a 25% probability of occurrence. Find the project's coefficient of variation. Q2. Rick Kish has a $140,000 stock portfolio. $50,000 is invested in a...
A project's base case or most likely NPV is $44,000, and assume its probability of occurrence...
A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is 65% higher than the base case and assume the worst scenario NPV is 35% lower than the base case. Both the best case scenario and the worst case scenario have a 25% probability of occurrence. Find the project's coefficient of variation.   Enter your answer rounded to two decimal places. For example, if your answer is...
What is the project's NPV? Crane Lumber, Inc., is considering purchasing a new wood saw that...
What is the project's NPV? Crane Lumber, Inc., is considering purchasing a new wood saw that costs $60,000. The saw will generate revenues of $100,000 per year for five years. The cost of materials and labor needed to generate these revenues will total $60,000 per year, and other cash expenses will be $10,000 per year. The machine is expected to sell for $4,800 at the end of its five-year life and will be depreciated on a straight-line basis over five...