Question

In: Finance

Scenario The Department of Technology is planning to replace the packaging machine in the graphic communication...

Scenario

The Department of Technology is planning to replace the packaging machine in the graphic communication lab in the Spring of 2021. The one currently in use was purchased from ESKO in 2011 for $100,000. The installation of the machine was done by the facility department on campus with a price tag of $5,000, including the labor and all the necessary harness. The new machine to be purchased has a cutting table doubles the size of the old one, with a throughput capacity four times of the old machine.

Q1. According to the vendor, ESKO, the price for the new machine for academic usage is directly related to the machine’s throughput capacity (not its physical size). If the cost-capacity factor between 2011 and 2021 is 0.85, what will be the estimated purchase price of the new machine?

Hint. No cost indexing information is needed here as the vendor has already incorporated the time-related cost change into the price they charge for the new machine.

Q2. In order to estimate the cost of operations, the graphic communication area coordinator needs to estimate the time of usage in the class setting. If it takes 45 minutes to set up and finish cutting the first box, and the learning curve slope is 0.75 according to the past experience, how long will it take to set up and finish cutting the third box?

Solutions

Expert Solution

ANSWER 1

Price in 2011= $ 100000 (excluding cost of installation)

Troughput Capacity = 4 times

Cost Capacity Factor =0.85

So, Cost of New Machine = Cost of old Machine ( Throughput Capacity of New Machine/ Troughput Capacity of Old Machine)*0.85

=100000(4/1)*0.85

= $ 340000

ANSWER 2

Learning Curve

Time taken for 1st Unit 45 Minutes

Learning Curve Slope = 75%

Formula = Tn =T1n^b

where n = unit number

T1= amount of time to produce Ist unit

b = Learning Curve Factor ie calculated as In(P)/In(2) where In(X) is natural Log of X

Here b= -0.415

So, Time Taken For 1st Unit 45 Minutes,

Time taken for IInd Unit 33.75 Minutes

Time Taken For Third Unit = 28.52 Minutes

Cumulative Time to Set and finish 3 boxes = 107.27 Minutes


Related Solutions

3. A French company is planning to replace the old machine for a new one. The...
3. A French company is planning to replace the old machine for a new one. The new machine will cost Euro 4 million, the old one can not be sold. The new machine will be used for 20 years, then it can be sold for 25% of the purchase price. Each year the company will save Euro 450,000 on the production costs, but the maintenance costs will be higher too: Euro 40,000 per year. The MARR of this company is...
Daisy Hill Hospital is planning to replace its CT scan machine. The machine system costs approximately...
Daisy Hill Hospital is planning to replace its CT scan machine. The machine system costs approximately $2,500,000, and an additional $500,000 for installation. Estimated charges per scan is $600. There is an estimated weekly utilization (volume) of 30 scans. Each scan will cost the hospital $35 in supplies. The system is expected to operate for $50 weeks per year. Associated annual labor costs for purchasing the CT scan machine is an estimated $100,000. Maintenance costs are estimated to be $80,000,...
Bellrome Company is planning to replace an old machine with the following related information: Book value...
Bellrome Company is planning to replace an old machine with the following related information: Book value P300,000 Remaining useful life 5 years Current market value 150,000 Additional information:  The replacement machine can be acquired at a list price of P500,000. A 5% cash discount is available if the said machine is paid within 30 days from acquisition date. Freight and installation costs is estimated at P75,000.  Should the company decide not to acquire the new machine, it needs...
The production department of Y Company is planning to purchase a new machine to improve product...
The production department of Y Company is planning to purchase a new machine to improve product quality. The company’s management accountant is currently evaluating two options- Buy the machine OR Rent it. Following information is available: The company has to pay £3,200 to set up the machine. Insurance cost £450 per annum. If it is bought, the new machine is depreciated on reducing balance basis at the rate of 25%. After various calculations, the company has to pay £4,200 maintenance...
. Direct materials used in the Packaging Department . . . . . . . ....
. Direct materials used in the Packaging Department . . . . . . . . . . . . . . . . . . . $38,000 2. Costs assigned to units completed and transferred out of Mixing . . . . . . . . . 231,000 3. Direct labour incurred in the Mixing Department . . . . . . . . . . . . . . . . . . . . . . 11,000...
1. Simon is the product manager for Packaging Plus. Simon purchased a new packaging machine for...
1. Simon is the product manager for Packaging Plus. Simon purchased a new packaging machine for $125,000 to save on labor costs. The first year, the machine worked well and the company was able to save $60,000, with machine operating and maintenance expenses of $25,000. The second year, operating expenses were slightly higher at $28,000, but savings increased to $80,000. The third year, expenses increased again to $30,000, and savings decreased to $65,000. The fourth year, the machine began to...
Mountainside Industries manufactures specialized plastic boxes in two processes: Molding and Packaging. In the Packaging Department,...
Mountainside Industries manufactures specialized plastic boxes in two processes: Molding and Packaging. In the Packaging Department, materials are added at the end of the process. The following data are given: Costs Units Trans.-in Materials Conv. Work in process, July 1 30 $1,590 $       0 $   513 Transferred in during July ? Completed during July 105 Work in process, July 31 15 Costs added during July $4,410 $1,050 $1,767 The conversion process on the beginning inventory is 70 percent completed and...
We are trying to decide whether to replace the original machine with a new machine. Original...
We are trying to decide whether to replace the original machine with a new machine. Original Machine: Initial cost = 1,000,000; Annual depreciation = 180,000; Purchased 2 years ago; Book Value = 640,000; Salvage today = 700,000; Salvage in 3 years = 150,000 New Machine: Initial cost = 600,000; 3-year life, straight-line depreciation; Salvage in 3 years = 100,000; Cost savings = 50,000/year Required return = 10% and Tax rate = 40% a. Should we replace the original machine with...
Colby Firestone Corporation is considering the purchase of a new machine to replace an old machine....
Colby Firestone Corporation is considering the purchase of a new machine to replace an old machine. The new machine will cost $135,000, has an installation cost of $5000, and will have an expected life of five years with a salvage value of $5,000. The new machine will require $2000 additional working capital. The new machine will result in a cost savings of $20,000 a year. Sales are expected to increase $9,000 per year. The old machine was purchased five years...
Colby Firestone Corporation is considering the purchase of a new machine to replace an old machine....
Colby Firestone Corporation is considering the purchase of a new machine to replace an old machine. The new machine will cost $135,000, has an installation cost of $5000, and will have an expected life of five years with a salvage value of $5,000. The new machine will require $2000 additional working capital. The new machine will result in a cost savings of $20,000 a year. Sales are expected to increase $9,000 per year. The old machine was purchased five years...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT