Question

In: Operations Management

In a turnkey project, the turnkey contractor requested you as a consultant to put up irregular...

In a turnkey project, the turnkey contractor requested you as a consultant to put up irregular (i.e. non-conforming to current engineering practice) proposals to maximize profits from the project. Discuss the key points that you must address so as not to compromise on your professional ethics. Demonstrate your solution through a simple case study/example.

Answering Format for the question you had selected:

1. What are your personal belief and stand on this matter?

2. What is the ethical and/or legal issue to be considered? Please state this with reference to the correct Rules and Regulations on Engineering Ethics and Professionalism / standards / codes for engineers. You need to mention the code/standard in your essay.

3. Identify and describe potential stakeholders.

4. Identify alternative ways to resolve the issue, and discuss their potential effects on all stakeholders.

Solutions

Expert Solution

Let me provide an example in IT environment where we had a turnkey support project wherein we were supposed to provide Infrastructure support for our client. We had our existing team of Network folks who were specialized in Network Data Domain. In the new turnkey support project, the clients were asking us to support Network Data, Voice and Security. This was a high budget urgent project and the contractor (Sales team in this case) were pushing us (the IT Operations team) to go ahead and announce that we have the required Network Voice and Security expertise too and that we are ready to take up the project at the earliest.

1. In any environment, satisfying the customer plus the belief that customer comes before anyone else is the motto for any thriving business. In this case, even though it was an urgent project, we cant take up the two additional verticals as we didnt have the necessary expertise. Network Security is highly critical and any breaches would lead to leaking customer data which would prove harmful for both my company as well as my customer

2. As per the Code of ethics for Engineers, they are supposed to perform services only in their area of expertise and not outside. First, it is an ethical issue wherein we are promising to deliver something which we have no idea about. Secondly, as suggested in answer 1, if there is a breach in security then there are mulitple legal problems that we would have to face

3. Potential Stakeholders are our IT Operations team who is the service provider, Sales team who is the contractor in this case, and the Client who is the service recipient/customer

4. There were two alternative ways - a) Cross train the expert resources on the two new verticals. This will take more time and cant be achieved due to the urgency in schedule of the project. b) Recruit new resources with experience in the two new verticals. This was the selected option. It did hit the Profit Margin but, we ended up in the good books of the client who in-turn provided us more projects


Related Solutions

Assume that you are a consultant for a city or community that is trying to put...
Assume that you are a consultant for a city or community that is trying to put in place a long-term sustainability plan. You are fully in charge of making sure that all the key stakeholders are invited, involved, engaged and heard throughout the process. On this Discussion Board, I would like you to comment on how you would go about ensuring that process. You may choose a state/city/community and environmental/socio-economic problem of your choice.
You are a contractor on a $45 million project in down town Los Angeles. The project...
You are a contractor on a $45 million project in down town Los Angeles. The project is scheduled to be completed in 2 years. You are 6 months into the project so far and project performance reports indicate that the budget has been exceeded by 10% thus far. Your schedule has also been delayed by more than a month due to subcontractor issues and labor disagreements. As a result, the quality of the job is suffering. It is your job...
You are a labor consultant. Your services have been requested to mediate a labor dispute between...
You are a labor consultant. Your services have been requested to mediate a labor dispute between unionized construction workers and their employer regarding overtime compensation. Write a one to two page essay describing how you would engage with the disputing parties in Private Mediation.
Hired to be a consultant for a movie production company 4. You will need to put...
Hired to be a consultant for a movie production company 4. You will need to put together a complete program charter for making your efforts a success:- You will also need to put together a complete program charter for making your efforts a success: -staffing needs both internal and external technical and analytical support, where required -time plan -financial budget for the job -how and when you will be paid
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursed construction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursedconstruction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of financial...
You are a construction engineer working for a large utility contractor. The project you are working...
You are a construction engineer working for a large utility contractor. The project you are working on is in New York City (Manhattan). You are installing approximately 1,000 L.F. of 48” dia. RCP for storm drains. Invert elevation ranges from 9’ to 14’ below grade. Pay lines for the trench are indicated in the attached specification. Soil characteristics range from SM to SC, based on the Unified Soil Classification. What considerations would you make with regards to a trenching &...
You are working as a consultant and are assigned the task to set up a secure...
You are working as a consultant and are assigned the task to set up a secure communication channel between three premises in the company. The communication should be using symmetric encryption with new keys exchanged on a daily basis. All premises have individual X.509 certificates. Describe a solution that includes how to carry out the encryption, key exchange and certifying that there is no malicious man-in-the-middle attempt Kindly answer this question in the field of Applied Computer Security....
You are a consultant to a large manufacturing corporation that is considering a project with the...
You are a consultant to a large manufacturing corporation that is considering a project with the following net after-tax cash flows (in millions of dollars): Years from Now After-Tax Cash Flow 0 -100 1-10 18 The project's beta is 1.1. a. Assuming that rf = 5% and E(rM) = 10%, what is the net present value of the project? (Do not round intermediate calculations. Enter your answer in millions rounded to 2 decimal places.) Net Present Value b. What is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT