Question

In: Finance

Project A and Project B are mutually exclusive. Project A has an IRR of 10 percent....

Project A and Project B are mutually exclusive. Project A has an IRR of 10 percent. Project B has an IRR of 12 percent. The crossover rate is 7%. Both projects have standard cashflow, (i.e. investment at time zero followed by a series of cash inflows). If the firm’s marginal cost of capital is 6 percent, then:

Project B should be accepted and Project A rejected.

Both projects should be accepted.

Both projects should be rejected.

Project A should be accepted and Project B rejected.

How many monthly payments remain to be paid on an 8% compounded monthly mortgage with a 30-year amortization and monthly payments of $733.76, when the balance reaches one-half of the $100,000 mortgage?

approximately 180 payments

approximately 268 payments

approximately 91 payments

approximately 68 payments

Solutions

Expert Solution

Answer : Correct option is Project A should be accepted and Project B rejected.

Reason :

Crossover rate is the rate at which Net present value of Both the projectes are equal. Crossover rate is used by organisations to know which projects is more favorable. In this case Project A is more favourable than Priject B because when the crossover rate is more then cost of capital then we select Project with lower IRR. Therefore Project A should be accepted and Project B rejected.

Answer : Correct Option is approximately 91 payments

Calculations

Using Nper function of Excel

=NPER(rate,pmt,pv,fv)

where rate is the rate of interest per period i.e 8% / 12 = 0.66666667%

pmt is the monthly mortgage payment i.e 733.76

pv is the present value i.e 100000 / 2 = 50000

fv is 0 as we wants to know when it will be repaid .

=NPER(0.66666667%,733.76,50000,0)

The number of payments remaining is 91 payments approximately.


Related Solutions

Consider the following two mutually exclusive projects.  Project A has an NPV of $0.5 billion, an IRR...
Consider the following two mutually exclusive projects.  Project A has an NPV of $0.5 billion, an IRR of 16% and a payback period of 4 years.  Project B has an NPV of $600 million, and IRR of 15% and a Payback period of 3 years. Which project should be chosen?
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B....
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B. Each lasts for one time period and the firm has no other projects. Project A will result in a cash flow of £27 million in the good state and £10 million in the bad state. Each outcome is equally likely. Project B will result in a cash flow of £34 million in the good state and zero in the bad state. Each outcome is...
Novell, Inc., Has the following mutually exclusive project Year Project A Project B 0 $20,000 $23,000...
Novell, Inc., Has the following mutually exclusive project Year Project A Project B 0 $20,000 $23,000 1 12,000 13,000 2 8,500 9,500 3 2,900 8,500 a.1. Calculate the payback period for each period ( do not round intermediate calculations and round your answers to decimal places) Project A Years Project B    Years a.2 If the company's payback period is two years, which, if either, of these projects, should be chosen? b.1. What is the NPV for each project if...
A company is considering two mutually exclusive projects. Initial investment for Project A (IRR=32%) is 15,000...
A company is considering two mutually exclusive projects. Initial investment for Project A (IRR=32%) is 15,000 and for B (IRR=28%) 18,000. For both projects, life time of the projects is 5 years, required rate of return for both the projects is 10%. The net cash flows before the tax and depreciation are as given in the table below. For both projects tax of 40% on cash inflows is to be charged. Year 1 2 3 4 5 Project A 7000...
a firm must choose between two mutually exclusive projects, a & b. project a has an...
a firm must choose between two mutually exclusive projects, a & b. project a has an initial cost of $10000. its projected net cash flows are $800, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. project b has an initial cost of $14000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. the firm’s cost of capital is 6.00%. choose the...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. At what cost of capital would the firm be...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000    a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: Years Project B: Years a-2. If the company's payback period is two years, which, if either, of these projects should be...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,300 –$ 8,700 1 7,500 3,400 2 6,500 2,900 3 2,100 5,300 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project A Project B If the appropriate discount rate is 12...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,800 –$ 9,200 1 8,400 3,900 2 7,000 3,400 3 2,100 5,800 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project B Project A If the appropriate discount rate is 10...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 15,000 –$ 10,300 1 9,500 5,000 2 8,100 4,500 3 2,100 6,900 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A ___ years Project B ___ years Based on the payback period, which project should the company accept? Project B or A? Project B Project A If...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT