Question

In: Accounting

Explain the basic ideas underlying process costing and how they differ from job costing. Demonstrate how...

Explain the basic ideas underlying process costing and how they differ from job costing. Demonstrate how the presence of beginning inventories affects the computation of unit costs under the first in, first out method.

Solutions

Expert Solution

PROCESS COSTING

Process costing is used when there is mass production of similar products, where the costs associated with individual units of output cannot be differentiated from each other. In other words, the cost of each product produced is assumed to be the same as the cost of every other product. Under this concept, costs are accumulated over a fixed period of time, summarized, and then allocated to all of the units produced during that period of time on a consistent basis.

For example, oil refining, food production, and chemical processing.

Types of Process Costing

There are three types of process costing, which are:

Weighted average costs : This version all costs, whether from a preceding period or the current one, are lumped together and assigned to produced units. It is the simplest version to calculate.

Standard costs : This version is based on standard costs. Its calculation is similar to weighted average costing, but standard costs are assigned to production units, rather than actual costs; after total costs are accumulated based on standard costs, these totals are compared to actual accumulated costs, and the difference is charged to a variance account.

First-in first-out costing (FIFO) : FIFO is a more complex calculation that creates layers of costs, one for any units of production that were started in the previous production period but not completed, and another layer for any production that is started in the current period.

Significant differences of Job costing and process costing systems.

  1. Types of products produced. Companies that use job costing work on many different jobs with different production requirements during each period. Companies that use process costing produce a single product, either on a continuous basis or for long periods. All the products that the company produces under process costing are the same.

  1. Cost accumulation procedures. Job costing accumulates costs by individual jobs. Process costing accumulates costs by process or department.

  1. Work in Process Inventory accounts. Job cost systems have one Work in Process Inventory account for each job. Process cost systems have a Work in Process Inventory account for each department or process.

FIFO costing method separates work and costs of the equivalent units in beginning inventory from work and costs of the equivalent units produced during the current period.

    • Only current work and costs are used to calculate this period’s unit cost.
    • It is assumed that units from beginning inventory are completed first and transferred out.
    • The costs of these units include the costs of the work done in the prior period as well as the current period costs necessary to complete the units.
  • Units started in the current period are divided into two categories:
    • units started and completed and
    • units started but not finished (EWIP).
  • Units in both of these categories are valued using the current period’s cost per equivalent unit.

DEMONSTRATION (FIFO Method)

We use an example of the month of June production costs for a company’s Department B. Department B adds materials only at the beginning of processing. The May 31 inventory in Department B (June’s beginning work in process) consists of 2,000 units that are fully complete as to materials and 60% complete as to conversion. Beginning work in process inventory has accumulated costs of $6,180.

The following costs were added in June: Direct materials issued $ 1,300; direct labor $ 7,200; and manufacturing overhead applied $ 6,000. The units for the period were:

Beginning work in process inventory

2,000 units

Units started this period

10,000 units

Ending work in process inventory

3,000 units

Ending work in process inventory was 1/3 complete as to conversion costs.

Step 1: Physical Flow of Units

For the physical flow of units, we calculate units started AND completed this period as Units started 10,000 – units remaining in ending work in process 3,000 = 7,000 units.

Units in Beg. WIP

2,000

Units Completed and Transferred:

Units Started this period

10,000

   Units from Beg. WIP

2,000

Total Units

12,000

   Units started and completed

7,000

(10,000 – 3,000)

Total Units completed and txfr

9,000

Units in End. WIP

3,000

Total Units

12,000

Step 2: Equivalent Units of Production

We are concerned with the right side of our physical flow of units. We must first FINISH beginning work in process, add units started and completed and units remaining in ending work in process. Beginning work in process is fully complete for materials (or 100% complete) and 60% complete for conversion so to complete these units we will need NO (or 0%) materials and 40% of conversion (100% – 60%). Units started and completed are always 100% complete for materials, labor and overhead! Ending work in process is 1/3 complete for conversion costs, but what about materials? The problem information reads “Department B adds materials only at the beginning of processing” which means we receive all (or 100%) of the materials at the beginning of the process and ending work in process will be fully complete for materials.

Materials

Conversion Costs

Units from beginning WIP

0

   800

[ 2,000 units x (100% – 100% complete)]

[ 2,000 units x (100% – 60% complete)]

Units started and completed

7,000

7,000

(7,000 units x 100% complete)

Units in ending WIP

3,000

1,000

(3,000 units x 100% complete)

(3,000 units x 1/3 complete)   

     Total Equivalent Units

10,000

8,800

Step 3: Cost per Equivalent Units

Under FIFO, we are only interested in the current period costs which is June for this example. Conversion costs are direct labor $7,200 + overhead $6,000.

Materials  

Conversion Costs  

Current Costs added this period

$   1,300

$   13,200

   (7,200 + 6,000)

÷ Total Equivalent Units

    10,000

      8,800

= Cost per Equivalent Unit

$     0.13

$      1.50

Step 4: Assign Costs to Units Completed and Ending Work in Process Inventory

Under FIFO, remember to bring over the costs of beginning work in process first, then multiply the individual equivalent units calculated in step 2 (not the total equivalent units) by the cost per equivalent unit from step 3.

Cost assigned to units completed and transferred out:

Cost of beginning work in process inventory

$6,180

Cost to complete beginning work in process inventory

Materials (0 equivalent units)

$0

Conversion   (800 equiv units x $1.50)

$1,200

$1,200

Cost of units started and completed

Materials (7,000 equiv units x $0.13)

$910

Conversion   (7,000 equiv units x $1.50)

$10,500

$11,410

Total cost of units completed and transferred

$18,790

Cost assigned to ending work in process inventory:

Materials (3,000 equiv units x $0.13)

$390

Conversion   (1,000 equiv units x $1.50)

$1,500

Total cost of units remaining in ending work in process inventory

$1,890

Step 5: Reconcile Costs

Here is our chance to check our work. Total costs to account for should always equal what was assigned in total costs accounted for.

Cost of beginning work in process

$6,180

Costs added in June

$14,500

(1,300 DM + 7,200 DL + 6,000 OH)

Total costs to account for

$20,680

Costs assigned to units completed

$18,790

(from step 4 above)

Costs assigned to ending work in process

$1,890

(from step 4 above)

Total costs accounted for

$20,680


Related Solutions

How does process costing differ from job order costing? When is process costing used instead of...
How does process costing differ from job order costing? When is process costing used instead of job-order costing? Can a company simply choose one method over the other because it likes one method better? Which two types of product costs are typically added together in process costing? Why are they combined?
1 . In what ways does ABC differ from Job Costing and Process Costing 2. Define...
1 . In what ways does ABC differ from Job Costing and Process Costing 2. Define the concepts and give an example for each concept a. Unit level activities b Batch level activities c Product level activities d Customer level activities e. Organization sustaining activities What type of activities should not be assigned to products in ABC? 4. Why are there 2 stages of allocation in ABC? 5. When ABC is used, why is MOH often shift from high volume...
How do job order and process costing systems, as well as their related valuation methods differ?
How do job order and process costing systems, as well as their related valuation methods differ?
How do job order and process costing systems, as well as their related valuation methods differ?
How do job order and process costing systems, as well as their related valuation methods differ?
1) Explain the benefits to be gained from using the following costing systems: Job costing Process...
1) Explain the benefits to be gained from using the following costing systems: Job costing Process Costing Activity based Costing b) Discuss the ethical issues in the use of costing systems above (Hint: what elements of these systems require judgement or choice by management and therefore leave open the possibility of manipulation)
Explain process operations and the way they differ from job order operations in 250 words or...
Explain process operations and the way they differ from job order operations in 250 words or more.
Which of the following differentiates job order costing from process costing? A: Process costing deals with...
Which of the following differentiates job order costing from process costing? A: Process costing deals with unique products produced on large scale while job costing is used when each unit of output is identical and not produced in batches. B: Process costing is used by service industries, and job costing is used by manufacturing industries. C: Process costing is used when each unit of output is identical, and job costing deals with unique products not produced in batches. D: Process...
Please explain job costing and process costing in your own words along with how it can...
Please explain job costing and process costing in your own words along with how it can be used in daily business life.
Discuss Activity Based Costing. Explain what it is and how it differs from Job costing. Explain...
Discuss Activity Based Costing. Explain what it is and how it differs from Job costing. Explain why “true” product costs have only a minor importance in final market price determination. Define and give an example of a “cost object”, “activity” and “resources.” Define “cost driver” and give 4 examples of activity cost pools and an appropriate cost driver for each.
Explain the similarity and difference between process costing and job-order costing.
Explain the similarity and difference between process costing and job-order costing.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT