Question

In: Finance

Question 1 What of the following project is a non-normal cash flow project? Project cost (negative...

Question 1

What of the following project is a non-normal cash flow project?

Project cost (negative CF) is followed by a series of positive cash inflows.

Project cost (negative CF) is followed by a series of positive cash inflows and a final negative cash flow when closing the project.

Project cost (negative CF) is followed a negative cash flows and then a series of positive cash inflows.

Project cost (negative CF) is followed two years’ negative cash flows and then a series of positive cash inflows.

Question 2

What’s the weakness of the discounted payback period?

Provides an indication of a project’s risk and liquidity.

Ignores the time value of money.

Ignores cash flows occurring after the payback period.

Both (B) and (C) correct

Question 3

A firm is considering an investment project with the following cash flows: Year 0 = -$150,000 (initial costs); Year 1= $40,000; Year 2 =$90,000; and Year 3 = $30,000; and Year 4 = $60,000. The company has a 10% cost of capital, calculate the IRR for the project.

10.0%

14.2%

17.2%

19.7%

Question 4

Two projects are mutually exclusive if the cash flows of one are unaffected by the acceptance of the other, but independent if the cash flows of one can be adversely impacted by the acceptance of the other.

True

False

Solutions

Expert Solution

Question 1

The correct answer is -

Project cost (negative CF) is followed by a series of positive cash inflows and a final negative cash flow when closing the project.

Non - normal cash flow project is one in which the cash flow pattern changes more than once. Cash outflow is denoted as negative outflow and cash inflow is positive outflow. In this project cash outflow (negative) is followed by positive cashflow and then again cash outflow. The cashflow pattern is changing more than one, hence it is non normal cash flow project.

In all other options the series of cash flow is changing once only, hence those are normal cash cash flow projects.

Question 2

Correct answer is-

Ignores cash flows occurring after the payback period.

Payback period is the time period required to cover the initial investment back. After payback period profit start occurring. Discounted payback period takes in to account the time value of money of future cash inflows.

It is disadvantage of using discounted payback period as a technique used for evaluating the capital budgeting decision that it doesnot take into account the cashflows occurring after payback period.

Hope it helps!


Related Solutions

Here is project Y: The cash flow in year 0 is negative $23,000. The cash flow...
Here is project Y: The cash flow in year 0 is negative $23,000. The cash flow in year 1 is $32,000. The cash flow in year 2 is $26,000. The cash flow in year 3 is negative $12,000. Here is project Z: The cash flow in year 0 is negative $42,000. The cash flow in year 1 is $58,000. The cash flow in year 2 is $39,000. The cash flow in year 3 is negative $35,000. Your decision rule is...
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1...
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1 -80,500 2 138,425 3 -105,455 4 30,030 Required: 1.1.Fill in the following table: Cost of Capital (%) Project NPV 0 5 10 15 20 25 30 35 50 1.2.Use the values developed in part (1.1) to draw an NPV profile for this project. 1.3.What is the IRR for this project? 1.4.Describe the conditions under which the company should accept this project.
QUESTION 1 Maxwell Feed & Seed is considering a project that has the following cash flow...
QUESTION 1 Maxwell Feed & Seed is considering a project that has the following cash flow data.  What is the project's IRR?   Year                                    0                    1                    2                    3                    4                    5   Cash flows                  -$9,500         $2,000          $2,025          $2,050          $2,075        $2,100 2.82% 3.10% 2.08% 2.31% 2.57% 10 points    QUESTION 2 Which of the following are limitations of the regular payback period it takes into account the time value of money it utilizes an arbitrary cut-off criterion it uses cash flows generated by the project beyond the end of the payback period it is simple to calculate...
If average revenue is less than average cost there will be a negative cash flow and...
If average revenue is less than average cost there will be a negative cash flow and the firm will be forced to shutdown. Is this correct? Why or why not?
Can free cash flow be a negative number? What does a lack of free cash flow...
Can free cash flow be a negative number? What does a lack of free cash flow indicate for a business? Please indicate why free cash flow may be a better indicator than Cash Flows from Operating Activities of financial strength.
I computed 3 projects's accumulated value with cash flow. for the project 1 I got negative...
I computed 3 projects's accumulated value with cash flow. for the project 1 I got negative accumulated value, for the project 2 I got negative accumulated value. For project 3( company takes project 1 and 2 at the same time) I got positive accumulated value. I was wondering why the company takes project 1 and 2 at the same time can get positive accumulated value.... its kind of counterintuitive to me. Can you hepl me out? plz explain it as...
Scott Enterprises is considering a project that has the following cash flow and cost of capital...
Scott Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r: 11.00% Year 0 1 2 3 4 Cash flows −$1,000 $350 $350 $350 $350 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV...
shannon co. is considering a project that has the following cash flow and cost of capital...
shannon co. is considering a project that has the following cash flow and cost of capital (r) data. What is the project discount paycheck? R+ 12.00% Year 0 1 2 3 CF -$1000 $450 $425 $400 $410 $400
reed enterprises is considering a project that has the following cash flow and cost of capital...
reed enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project NPV? note that a projects expected NPV can be negative, in which case it will be rejected. R: 11.00% Year 0 1 2 3 CF -1,065 $500 $475 $450
Robbins Inc. is considering a project that has the following cash flow and cost of capital...
Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r. 10.25% Year 0 1 2 3 4 5 Cash flows −$1,000 $300 $300 $300 $300 $300 a. $117.33 b. $105.89 c. $123.51 d. $130.01 e. $111.47 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT