In: Accounting
( show the formula in every step and from were the number come from)
standard Costing & Variance Analysis
Delic plc. is a manufacturer of cakes that makes a wide range of cakes. It operates a standard marginal cost accounting system. Given below, is information relating to one of its products, i.e. birthday cakes, which are made in one of the company departments:
Birthday cakes |
Standard marginal product cost per unit ($) |
Direct material (6 kgs at $4 per kg) |
24 |
Direct labour (1 hour at $7 per hour) |
7 |
Variable production overhead |
3 |
total |
34 |
Additional information
Actual production and costs for one of the months were as follows: - Units of birthday cakes produced 18,500 units
|
$
Direct materials purchased and used, 113,500kg 442,650
Direct labour, 17,800 hours 129,940
Variable production overhead incurred 58,800
Fixed production overhead incurred 104,000
total 735,390
Required:
(iii) Wage rate variance
vi) Variable overhead efficiency variance
a) | Original Budget | Flexed Budget | Actual Cost | Total Variance | ||
Birthday cakes in units | 20000 | 18500 | 18500 | |||
Direct material cost | $ 4,80,000 | $ 4,44,000 | $ 4,42,650 | $ 1,350 | Favorable | |
[24*20000] | [24*18000] | |||||
Direct labor cost | $ 1,40,000 | $ 1,29,500 | $ 1,29,940 | $ 440 | Unfavorable | |
[7*20000] | [7*18500] | |||||
Variable production overhead cost | $ 60,000 | $ 55,500 | $ 58,800 | $ 3,300 | Unfavorable | |
[3*20000] | [3*18500] | |||||
Fixed production overhead cost | $ 1,00,000 | $ 1,00,000 | $ 1,04,000 | $ 4,000 | Unfavorable | |
Total cost of production | $ 7,80,000 | $ 7,29,000 | $ 7,35,390 | $ 6,390 | Unfavorable | |
b) | Direct material price variance = (Actual price-Standard price)*Actual quantity purchased = | |||||
= (442650/113500-4.00)*113500 = | $ 11,350 | Favorable | ||||
Direct material usage variance = (Actual quantity used-Standard quantity)*Standard price = (113500-18500*6)*4.00 = | $ 10,000 | Unfavorable | ||||
Total direct materials cost variance = DM price variance+DM quantity variance = 11350-10000 = | $ 1,350 | Unfavorable | ||||
Direct labor rate variance = (Actual rate-Standard rate)*Actual DLH = (129940/17800-7.00)*17800 = | $ 5,340 | Unfavorable | ||||
Direct labor efficiency variance = (Actual DLH-Standard DLH)*Standard rate = (17800-18500*1)*7.00 = | $ 4,900 | Favorable | ||||
Total direct labor cost variance = DL price variance+DL efficiency variance = 5340-4900 = | $ 440 | Unfavorable | ||||
Variable factory overhead expenditure variance = Actual variable factory overhead-Actual hours * Standard variable overhead rate = 58800-17800*1*3 = | $ 5,400 | Unfavorable | ||||
Variable overhead efficiency variance = (Actual hours - Standard hours)*Standard VOH rate = (17800-18500*1)*3 = | $ 2,100 | Favorable | ||||
Total factory overhead cost variance = 3600-2100 = | $ 3,300 | Unfavorable |