In: Accounting
Egerton Manufacturing Ltd produces a range of products at seven separate sites. The directors have decided to introduce Activity Based Costing (ABC) and have asked each site manager to obtain and analyse the relevant data for their site. Product costs are currently calculated using absorption costing, with overheads being absorbed on a machine hour basis. As part of the process of introducing ABC, the directors wish to assess the profitability of individual products, with the possibility that the product range may be reduced. You are the Manager of the Brumley site and you have obtained the following data:
Product |
A |
B |
C |
$ |
$ |
$ |
|
Selling price per unit |
300 |
530 |
435 |
Direct material per unit |
55 |
67 |
98 |
Direct labour per unit |
41 |
54 |
57 |
Overheads per unit |
117.20 |
293 |
117.20 |
Total cost per unit |
213.20 |
414 |
272.20 |
Budgeted production volume |
600 units |
400 units |
200 units |
Machine hours per unit |
0.6 |
1.5 |
0.6 |
Production runs in period |
32 |
40 |
25 |
Number of sale orders |
19 |
5 |
15 |
Number of deliveries of material |
8 |
2 |
16 |
The budgeted overheads of the site for the period are:
Machine running costs |
$78,560 |
Set up costs |
$82,900 |
Material handling costs |
$49,500 |
Machine hours are limited to 1,140 hours per period.
Required:
a) Calculate the cost of each product using ABC. Choose appropriate cost drivers for each activity
b) Draft a memo to the Managing Director which:
(i) Using the ABC information, indicates which product(s) should no longer be manufactured and justify your recommendation;
(ii) Discuss any other factors which should be considered before a final decision is made.
Solution :
Part A : Cost per unit under ABC
Step 1 : Computation of OH Recovery rate | |||||
S.No | Activity | Cost Pool | Cost Driver | Quantity of Cost Driver | ABC Rate (Cost Pool ÷ Cost driver) |
1) | Machine running costs | $ 78,560 | Machine Hours | 1140 | $ 68.91 |
2) | Set up costs | $ 82,900 | Production Runs | = 32+40+25 = 97 | $ 854.64 |
3) | Material handling costs | $ 49,500 | Number of deliveries of material | = 8 + 2 + 16 = 26 | $ 1,903.85 |
Step 2 : Overhead cost under ABC | ||||
S.No | Particulars | A | B | C |
1) | Production volume (units) | 600 | 400 | 200 |
2) | Machine hours p.u | 0.60 | 1.50 | 0.60 |
3) | Machine hours for budgeted units (1 x 2) | 360 | 600 | 120 |
4) | ABC rate of Machine running costs | $ 68.91 | $ 68.91 | $ 68.91 |
5) | Machine running costs (3 x 4) | $ 24,808.42 | $ 41,347.37 | $ 8,269.47 |
6) | Production Runs | 32 | 40 | 25 |
7) | ABC rate of Set up | $ 854.64 | $ 854.64 | $ 854.64 |
8) | Set up costs (6 x 7) | $ 27,348.45 | $ 34,185.57 | $ 21,365.98 |
9) | Number of deliveries of material | 8 | 12 | 26 |
10) | ABC rate of Material handling costs | $ 1,903.85 | $ 1,903.85 | $ 1,903.85 |
11) | Material handling costs (9 x 10) | $ 15,230.77 | $ 22,846.15 | $ 49,500.00 |
12) | Total Overhead cost ( 5+8+11) | $ 67,387.64 | $ 98,379.09 | $ 79,135.45 |
13) | Overhead cost p.u ( 12 ÷ 1) | $ 112.31 | $ 245.95 | $ 395.68 |
Step 3 : Product Cost p.u under ABC | ||||
S.No | Particulars | A | B | C |
1) | Direct material p.u | $ 55.00 | $ 67.00 | $ 98.00 |
2) | Direct labor p.u | $ 41.00 | $ 54.00 | $ 57.00 |
3) | Overhead cost p.u (as per Step 2) | $ 112.31 | $ 245.95 | $ 395.68 |
4) | Total cost per unit (1+2+3) | $ 208.31 | $ 366.95 | $ 550.68 |
Part B (i) : Memo
To : The Managing Director,Egerton Manufacturing Ltd
Please find the analysis of the per unit profits and losses of the products A,B&C as per the ABC costing
S.No | Particulars | A | B | C |
1) | Selling price p.u | $ 300 | $ 530.00 | $ 435.00 |
2) | Direct material p.u | $ 55.00 | $ 67.00 | $ 98.00 |
3) | Direct labor p.u | $ 41.00 | $ 54.00 | $ 57.00 |
4) | Overhead cost p.u (as per Step 2) | $ 112.31 | $ 245.95 | $ 395.68 |
5) | Total cost per unit (2+3+4) | $ 208.31 | $ 366.95 | $ 550.68 |
6) | Profit/(Loss p.u) (1-6) | $ 91.687 | $ 163.052 | $ (115.677) |
Based on the above analysis, it can be concluded that Product C, should not be manufactured as it results in a loss.
Part B (ii) : Other factors to consider
1) Evaluate whether the cost drivers selected are accurate and make
the required changes to any new cost and cost drivers
identified.
2) Identify the Value added and non-value added activities of Product C, and check whether any cost savings or savings in machine hours is possible.
3) The market demand for the product should be analyzed and evaluate if there are any alternative options to ensure the supply of Product C to the market. Options like sub-contracting, direct purchase from the market or implementing any change in the production process should be considered and evaluated.
4) The life cycle stage of the products should be considered.