Question

In: Operations Management

3. Under the JCT Standard Building Contract, 2016 edition, the parties have to complete and sign...

3. Under the JCT Standard Building Contract, 2016 edition, the parties have to complete and sign the Agreement to create a contractual relationship. What is the equivalent document applicable to the NEC4 ECC? Comment on the data about the project that must be incorporated by a contract in that form (Word limit: 1000)

Solutions

Expert Solution

The equivalent document to NEC4ECC is the FIDIC contract

FIDIC is usually divided in two parts: Part I consisting of the general conditions and Part II concerning the conditions of particular application (including guidelines for the preparation of Part II clauses). Part I contains the general terms of the contract, such issues as rights and obligations of each party, procedure for payment, variation, certification and dispute resolution.

Part II of the contract is the conditions of particular application and is to be used to introduce project specific clauses, such as language of the contract, choice of law, the name of the person or firm appointed to act as Engineer or Employers representative for the project among other terms. The Appendix usually contains sample of documents to be used for the procurement process.

In most FIDIC forms there is a default hierarchy for the documents forming the contract. The order of priority is as stated below and in the event of inconsistency the first on the list takes precedence:

  1. The Contract Agreement
  2. The Letter of Acceptance (this is the formal acceptance of the contractor's tender and marks the formation of the contract)
  3. The Letter of Tender
  4. Part II – the conditions of particular application
  5. Part I – general conditions of contract
  6. The Specification and Drawings (Red Book), The Employer’s Requirements (Yellow Book), the Schedules (Red and Yellow Books)
  7. Further documents (if any), listed in the Contract Agreement or in the Letter of Acceptance.

The parties are allowed to rearrange the priority of documents or stipulate that no priority or order of hierarchy will apply to the contract. This can be done in Part II of the contract.

Dispute Resolution - FIDIC contracts adopt a multi-tier dispute resolution process. The emphasis in recent years has been on the amicable settlement of disputes. The process usually provides as a first step, for disputes to be submitted for adjudication before an Engineer or a Dispute Board. If one (or both) of the parties is dissatisfied, a period is allowed for amicable settlement. If the parties are not able to settle the dispute during the ‘amicable settlement’ period, the final stage is to proceed to arbitration. FIDIC contracts provide as a default position that the arbitration rules of the International Chambers of Commerce should apply in the arbitration of disputes arising from the contract.


Related Solutions

Under the Restatement, if the parties to a contract attach materially different meanings to their manifestations...
Under the Restatement, if the parties to a contract attach materially different meanings to their manifestations and neither party knows or has reason to know the meaning attached by the other: a. and neither party is to blame, there is no contract at all. b. and both parties are to blame, there is no contract at all. c. and one party is to blame, that party will be held responsible, but the contract is not void. d. All of these.
1. Describe the respective obligations of the parties under a contract for the sale or lease...
1. Describe the respective obligations of the parties under a contract for the sale or lease of goods? 2. Explain the perfect tender rule and the exceptions to this rule that apply to sales and lease contracts. 3. Explain the options that are available to the nonbreachingparty when the other party to a sales or lease contract repudiates the contract prior to the time for performanc. 4. Describe the remedies that are available to a seller or lessorwhen the buyer...
The owner of the property must sign the contract to confirm they have received a special...
The owner of the property must sign the contract to confirm they have received a special document. What is the document and what does it contain? it is question of certificate 4 in building and construction from assesment of CPCCBC4008B Conduct on-site supervision of building and construction projects
Brian owns and manages an apartment building. Danny and Brian sign a lease under which Danny...
Brian owns and manages an apartment building. Danny and Brian sign a lease under which Danny agrees to rent an apartment for $4,000 per month plus all utility costs associated with the apartment. The lease is for a 3 year term, although Danny can terminate the lease provided he gives three months’ notice. One year into the term, Danny asks Brian to sign a modification to the lease that indicates that the utility bills are to be split equally between...
a building design was complete and is under construction. You had selected a window with a...
a building design was complete and is under construction. You had selected a window with a U-value of 1.6 and a solar heat gain coefficient (SHGC) of 0.25. The window manufacturer informs you that they no longer carry that window model, but that they can give you a window with a U-value of 1.6 and SHGC of 0.4. How would this new window impact your building's modeled heating and cooling energy consumption?
a building design was complete and is under construction. You had selected a window with a...
a building design was complete and is under construction. You had selected a window with a U-value of 1.6 and a solar heat gain coefficient (SHGC) of 0.25. The window manufacturer informs you that they no longer carry that window model, but that they can give you a window with a U-value of 1.6 and SHGC of 0.4. How would this new window impact your building's modeled heating and cooling energy consumption?
Problem 3 An entity entered into a construction contract to build a condo building at a...
Problem 3 An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s): 20x0 20x1 20x2 20x3 Costs incurred during the year $ 6500 19500 25000 5800 Estimated costs to complete 38500 26000 6500 - Billings 18000 18000 - 18000 For each of the parts below, prepare the ‘mini’ income statement for the project for each...
In determining the meaning of a contract under the UCC, which of the following will have...
In determining the meaning of a contract under the UCC, which of the following will have first priority? A. Course of Performance B. Course of Dealing C. Usage of Trade D. Express Terms
You sign a mortgage contract. You have enough cash to make a 20% down payment.Your monthly...
You sign a mortgage contract. You have enough cash to make a 20% down payment.Your monthly payments will be $1,200 for 30 yrs starting one month away from today. If the interest rate is 3% APR, whats the maximum value of the house you can afford. 355,784.07 284,627.26 356,673.53 285,338.83 287,659.18
Big Red Engineering Associates entered into a 3 year contract to construct an office building at...
Big Red Engineering Associates entered into a 3 year contract to construct an office building at a contract price of $1,700,000. With the construction data below prepare the necessary journal entries to record cost incurred, billings to customers, cash collections, and the end of year adjusting entry applicable to percentage of completion method:                                                  Year 1                    Year 2                    Year 3 Construction cost incurred       250,000                 900,000                  210,000 Estimated cost to complete   1,000,000                  287,500                       0 Progress Billings                      190,000               1,200,000                  310,000 Collections...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT