Question

In: Civil Engineering

describe how the role of the A/E varies in the different approaches : traditional contract, Design...

describe how the role of the A/E varies in the different approaches : traditional contract, Design build, and PMC approach

Solutions

Expert Solution

The A/E varies in the different approaches : traditional contract, Design build, and PMC approach

Traditional Contract:

The 'traditional' procurement route, sometimes referred to as 'design bid build' (or 'bid build' by contractors) remains the most commonly used method of procuring building works.

The client first appoints consultants to design the project in detail and then prepare tender documentation, including drawings, work schedules and bills of quantities. Contractors are then invited to submit tenders for the construction of the project, usually on a single-stage, competitive basis. This may be referred to as a 'traditional contract'. The contractor is not responsible for the design, other than temporary works, although some traditional contracts do provide for the contractor to design specific parts of the works.

Typically, the client retains the design consultants during the construction phase to prepare any additional design information that may be required, to review any designs that might be prepared by the contractor, and to inspect the works. Normally, one consultant (often, but not necessarily, the architect) will be appointed to administer the contract.

Traditional construction contracts are most commonly lump-sum contracts, however, measurement contracts and cost reimbursement contracts can also be used for ‘traditional’ projects where design and construction are separate, sequential activities.

This form of procurement is suitable for both experienced and inexperienced clients. Fully developing the design before tender gives the client certainty about design quality and cost, but it can be slower than other forms of contracting, and as the contractor is appointed only once the design is complete, they are not able to help improve the buildability and packaging of proposals as they develop.

It is considered to be a low risk method of contracting for the client, as the contractor takes the financial risk for construction. However, if design information is incomplete at tender, or if significant variations are required after the contractor has been appointed, the cost to the clientcan be significant. Because of this, and because of the separation of design and construction, traditional procurement can be seen as adversarial.

Design–build contractor:

The "design–builder" is often a general contractor, but in many cases a project is led by a design professional (architect, engineer, architectural technologist or other professional designers). Some design–build firms employ professionals from both the design and construction sector. Where the design–builder is a general contractor, the designers are typically retained directly by the contractor. Partnership or a joint venture between a design firm and a construction firm may be created on a long term basis or for one project only.

Until 1979, the AIA American Institute of Architects' code of ethics and professional conduct prohibited their members from providing construction services. However today many architects in the United States and elsewhere aspire to provide integrated design and construction services, and one approach towards this goal is design–build. The AIA has acknowledged that design–build is becoming one of the main approaches to construction. In 2003, the AIA endorsed "The architect's guide to design–build services",[3] which was written to help their members acting as design–build contractors. This publication gives guidance through the different phases of the process: design services, contracts, management, insurances, and finances.

Contractor-led design–build projects: the architect's role:

On contractor-led design–build projects, management is structured so that the owner works directly with a contractor who, in turn, coordinates subcontractors. Architects contribute to contractor-led design–build projects in one of several ways, with varying degrees of responsibility (where "A/E" in each diagram represents the architect/engineer):

Three models of contractor-led design–build

  1. Architect as employee of contractor: The architect works for the contractor as an in-house employee. The architect still bears professional risk and is likely to have less control than in other contractor-led design–build approaches.
  2. Architect as a subcontractor: Here, the architect is one of the many subcontractors on the team led by the contractor. The architect bears similar professional risk but still with little control.
  3. Architect as second party in contractor-led integrated project delivery (IPD): The architect and contractor work together in a joint venture, both coordinating the subcontractors to get the project built. The building owner has a single contract with this joint venture. The contractor leads the joint venture so in supervising the subs, the architect might defer to the contractor. The architect bears the same risk as they do in the traditional approach but has more control in IPD, even if they were to defer to the contractor.

Architect-led design–build projects:

Architect-led design–build projects are those in which interdisciplinary teams of architects and building trades professionals collaborate in an agile management process, where design strategy and construction expertise are seamlessly integrated, and the architect, as owner-advocate, project-steward and team-leader, ensures high fidelity between project aims and outcomes. In architect-led design–build projects, the architect works directly with the owner (the client), acts as the designer and builder, coordinating a team of consultants, subcontractors and materials suppliers throughout the project lifecycle.

Architects lead design–build projects in several ways, with varying degrees of responsibility (where "A/E" in each diagram represents the architect/engineer):

Three models of architect-led design–build

  1. Architect as provider of extended services: Contracted to the owner, the architect extends his or her services beyond the design phase, taking responsibility for managing the subcontractors on behalf of the owner. The architect bears similar risk but has more control over the project than in the traditional approach or on contractor-led design–build projects.
  2. Architect as primary party in architect-led integrated project delivery (IPD): Again, as in working together in a joint venture, both coordinating the subcontractors to get the project built. Again, the building owner has a single contract with this joint venture. This time, the architect leads the joint venture so in supervising the subs, the contractor might defer to the architect. The architect might bear more risk than they do in the traditional approach but risk is shared with the owner and the contractor, as outlined in their agreement. An alternative approach to effectuating this delivery structure is for the architect to contract directly with the owner to design and build the project, and then to subcontract the procurement and construction responsibilities to its allied general contractor, who enters into further subcontracts with the trades. This is a difference in form, rather than in substance, because the business and legal terms of the agreement between the architect and the general contractor may be the same regardless of whether they are characterized as a joint venture or as a subcontract. It is the "flip side of the coin" of the contractor-led approach described above in which the general contractor subcontracts the design to the architect.
  3. Architect as full service leader of design build process: Contracted to the owner, the architect offers full service to the owner, taking responsibility for managing the subcontractors, consultants and vendors, and involving them throughout the project, start to finish, from design through construction. The architect's role shifts during the project, from designer to site supervisor (effectively taking the role of a general contractor), but monitors the project vision, and is able to call upon subcontractors' construction expertise throughout. The architect bears the greatest risk but also has more control over the project than in either the traditional approach, or in the contractor-led and other architect-led design–build projects.

Contracts:

A single set of integrated contracts combining design and construction responsibilities, rather than two discrete contracts for each, acknowledges the interdependence of the architects' and construction trades' project responsibilities, and reduces the likelihood of disputes.

PMC Approach:

PMC (PROJECT MANAJEMENT CONSULTANT)  Is Usually the manager of a project in behalf of the Company (Client). The PMC handle the contracts issued by the Company to perform a project such as EPC’s, Services, Training, interventory, logistics, etc... This contractor is used to help the Company structure to handle projects.


Related Solutions

How E - commerce is different from traditional commerce? Describe four differences with example.
How E - commerce is different from traditional commerce? Describe four differences with example.
Engineer E and Owner O are engaged in contract negotiations for E to design and build...
Engineer E and Owner O are engaged in contract negotiations for E to design and build a building for O. The proposed contract is for $200,000. The estimated duration of the turnkey project is 15 months. After reaching an oral agreement of the above, O tells E that they should get together over the next few weeks to hammer out the contract language details for a formal written contract. E begins work without notifying O and completes approximately 30% of...
define restorative justice? How is restorative justice different from traditional justice approaches? Do you believe this...
define restorative justice? How is restorative justice different from traditional justice approaches? Do you believe this should be implemented in all cases? Why or why not?
Describe the different approaches and analysis on global taxation
Describe the different approaches and analysis on global taxation
Describe the different types of approaches to marketing research. Provide an example of how marketing research...
Describe the different types of approaches to marketing research. Provide an example of how marketing research led to a new product?
Name and describe two different approaches to navigation in react native?
Name and describe two different approaches to navigation in react native?
Analyse how the HR function varies between organisations in different sectors and of different sizes. (AC2.2)...
Analyse how the HR function varies between organisations in different sectors and of different sizes. (AC2.2) You should examine three of the following types of organisation. 1. A public authority (Government Sector) 2. A national private company 3. An SME 4. A voluntary (Third Sector) organisation (approx 250 words)
Describe the various approaches in assessing the cost of nursing care Examine the role of recruiting...
Describe the various approaches in assessing the cost of nursing care Examine the role of recruiting and retaining nurses in the cost of nursing care. Explain the impact of nursing turnover on nursing care costs. Examine whether the cost assessment methods used in your organization are effective. Give reasons for your answer.
Describe the various approaches in assessing the cost of nursing care Examine the role of recruiting...
Describe the various approaches in assessing the cost of nursing care Examine the role of recruiting and retaining nurses in the cost of nursing care. Explain the impact of nursing turnover on nursing care costs. Examine whether the cost assessment methods used in your organization are effective. Give reasons for your answer. Essay style.
Describe a best design practice for designing a wired LAN. Describe a (different) best design practice...
Describe a best design practice for designing a wired LAN. Describe a (different) best design practice for designing a wireless LAN.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT