Question

In: Operations Management

For the following network determine:


For the following network determine: 

a) The activities on the critical path 

b) The time for the critical path 

c) The slack for EVERY activity 

image.png

Solutions

Expert Solution

step 1 find early start, and early finish from the start of the project for each activity
Activity Duration, D Early start, ES=Max of early finish of preceeding activities Early finish, EF = ES + D
A 5 0 5
B 4 0 4
C 3 5 8
D 6 5 11
E 2 5 7
F 8 11 19
G 5 11 16
step 2 Find Maximum EF = 19 and keep it as the LF of last activities
step 3 calculate LS for each activity after calculating its EF's.
Activity Duration, D Early start, ES=Max of early finish of preceeding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Critical activity, activities with 0 slack time
A 5 0 5 5 0 0 Yes
B 4 0 4 5 1 1 No
C 3 5 8 11 8 3 No
D 6 5 11 11 5 0 Yes
E 2 5 7 11 9 4 No
F 8 11 19 19 11 0 Yes
G 5 11 16 19 14 3 No
  1. activities on the critical path are A, D and F
  2. the time for critical path is 19 (Max of EF's)
  3. Slack for every activity is in the table above

Related Solutions

For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
Given the following information, you are to determine the following Project network. Early, late and slack...
Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 5 B A 8 C A 15 D A 10 E A 10 F B 10 G C, D 12 H E, 15 I G, H 7 J F,G,I 10 K J 12
Build the network and determine the critical path.
Build the network and determine the critical path.
Following a recent network intrusion, a company wants to determine the current security awareness of all...
Following a recent network intrusion, a company wants to determine the current security awareness of all of its employees. Which of the following is the BEST way to test awareness? A. Conduct a series of security training events with comprehensive tests at the end B. Hire an external company to provide an independent audit of the network security posture C. Review the social media of all employees to see how much proprietary information is shared D. Send an email from...
Construct the following network(AOA) and determine the minimum total cost to complete the project if indirect...
Construct the following network(AOA) and determine the minimum total cost to complete the project if indirect cost is Rs.1500 per day. Activity NT CT NC CC 1-2 6 4 6000 7800 1-3 7 4 3000 4200 2-3 4 1 5000 9200 2-5 6 5 6000 7500 3-4 7 3 2000 6800 4-5 3 1 2000 4000 4-6 7 3 4000 5600 5-6 5 4 3000 4100
3.   Consider a sub netting network with a network ID and Mask given as 200.155.187.0/24. Determine...
3.   Consider a sub netting network with a network ID and Mask given as 200.155.187.0/24. Determine the following for the given network address i. To which class does this address belong to                                           (3 Marks) ii. Identify whether the address belongs to public or private class.        (3 Marks) iii. Calculate the new mask required to provide 10 usable hosts per subnet. (8 Marks) iv. What is the dotted decimal notation for the given address.             (3 Marks) v. Calculate...
Consider the following situations and determine whether they exhibit simultaneous consumption, network effects, x-inefficiency or rent-seeking...
Consider the following situations and determine whether they exhibit simultaneous consumption, network effects, x-inefficiency or rent-seeking behavior. Assume the businesses referenced function as monopolies. (a) A pharmaceutical company discovers a vaccine for the common cold. The company puts a significant effort into tests to get it FDA-approved and into hiring lawyers to obtain a patent. (b) An Internet service provider adds thousands of new customers. (c) The head of a family-owned, major hotel chain decides to hire his wild, socialite...
Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS,...
Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS, LF, TF and FF for each activity. Which activities in the project are on the critical path Activity Duration IPA Type of relationship Lag A 4 B 3 C 8 A D 7 A, B E 6 D SS 3 F 3 D G 5 F SS FF 2 Note: If the relationship type is not mentioned, it is FS. If no lag/lead is...
Explain the logic used to determine which activity to reduce on a Project Network based on...
Explain the logic used to determine which activity to reduce on a Project Network based on the cost slope and other relevant information.
Scenario 1 (Use the network 221.153.17.0 for the following questions.) We need to subnet this network...
Scenario 1 (Use the network 221.153.17.0 for the following questions.) We need to subnet this network to support a minimum of 4 (four) networks. How many bits do we need to use from the last octet to support this? How many hosts would each network be able to support? What will the subnet mask be? Give the network, IP range, and broadcast address for the first 3 networks: Network 1:    _________________             Broadcast: _________________ Host IP Range:         _________________ to _________________...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT