Question

In: Operations Management

Consider the bottle-filling process, which has a lower specification limit of 0.99 liter and an upper...

Consider the bottle-filling process, which has a lower specification limit of 0.99 liter and an upper specification limit of 1.01 liters. The standard deviation is 0.005 liter and the mean is 1 liter. The company wants to reduce its defective probability from 45,500 PPM to 1000 PPM.

A. Determine the current Capability index.

B. Determine the new aspired capability index.

C. To what level would they have to reduce the standard deviation in the process to meet this target?

Solutions

Expert Solution

Calculations were done in Excel and snapshots are shown below:

Formulas:

A. Current Process Capability Index = 0.667

B. New Aspired Process Capability Index = 1.0968

C. Standard deviation in the process would have to be reduced to 0.003 to achieve new aspired process capability index of 1.0968.


Related Solutions

(1) C&A's potato chip filling process has a lower specification limit of 9.5 oz and an...
(1) C&A's potato chip filling process has a lower specification limit of 9.5 oz and an upper specification limit of 10.5 oz. The standard deviation is 0.3 oz. and the mean is 10 oz. What is the process capability index (Cp) for the chip filling process?(a) 0.56(b) 1.11(c) 0.33(d) 3.33 (2) Which of the following represents customer requirement from a process?(a) Sample size in control charts(b) USL and LSL(c) Process standard deviation(d) UCL and LCL (3) The mean of a...
Consider a process under statistical quality control. The upper specification limit of the statistic of interest...
Consider a process under statistical quality control. The upper specification limit of the statistic of interest is 101, while the lower specification is 42. The sample plan is for 7 samples per period. The average range of the process is 13. What is the capability of the process assuming it is centered exactly between the specification limits and the statistic of interest has a normal distribution?
Given the data below, a lower specification of 78.2, and an upper specification of 98.9, what...
Given the data below, a lower specification of 78.2, and an upper specification of 98.9, what is the long term process performance (Ppk)? Data 101.4791 94.02297 95.41277 106.7218 90.35416 86.9332 94.87044 95.91265 93.98042 108.558 86.17921 85.01441 96.14778 92.59247 92.49536 87.4595 104.3463 90.57274 99.38992 80.61536 82.31772 97.05331 87.64293 103.3648 98.09292 87.72921 110.1765 86.76847 87.22422 94.88148 86.01183 91.43283 104.0907 97.77132 98.69138 95.55565 106.2402 95.96255 88.05735 100.2796 99.00995 86.18458 95.41366 99.32314 95.75733 88.82675 93.39986 98.34077 94.72198 99.14256 92.37767 94.94969 89.63531 87.56148 88.02731 97.57498...
Given the data below, a lower specification of 62.6, and an upper specification of 101.8, what...
Given the data below, a lower specification of 62.6, and an upper specification of 101.8, what is the long term process performance (ppk)? Data 66.06284 82.57716 78.64111 92.72893 76.18137 71.46201 76.24239 74.83622 69.87486 77.90479 82.39439 79.18856 84.34492 77.32829 80.50536 83.36017 97.34745 84.56226 87.95131 65.64412 70.73183 74.28879 89.07007 78.50745 77.51397 89.04946 73.75787 91.30598 87.12589 89.29855 81.398 86.52962 84.33249 80.48321 81.87089 83.54964 71.19464 80.02001 90.00112 82.29257 77.55125 88.07639 88.95467 83.92542 88.33509 84.36723 77.89679 82.38985 67.81415 80.68263 87.25767 81.1521 82.15546 72.52171 67.58353 86.11663...
1. There is a lower limit but no upper limit for a random variable that follows...
1. There is a lower limit but no upper limit for a random variable that follows the a. ​uniform probability distribution. b. ​exponential probability distribution. c. ​normal probability distribution. d. ​binomial probability distribution. 2. The weight of football players is normally distributed with a mean of 200 pounds and a standard deviation of 25 pounds. What is the minimum weight of the middle 95% of the players? a. 196 b. 190 c. 151 d. 249 3. A scatter diagram reveals...
The lower flammability limit (LFL) and upper flammability limit (UFL) are important safety limits which describe...
The lower flammability limit (LFL) and upper flammability limit (UFL) are important safety limits which describe the minimum and maximum volume fraction in air, respectively, that a flammable substance can burn if ignited. If the range of concentration of benzene in air in which ignition could take place is 1.4 - 8.0 vol%, what would be the corresponding temperatures for air saturated with benzene in the vapour space of a storage tank assuming a total pressure in the vapour space...
The normal variance for filling a liter Coke bottle is 0.5 ounces. In a recent measurement,...
The normal variance for filling a liter Coke bottle is 0.5 ounces. In a recent measurement, variance was found to be 0.8 ounces. Should Coca-Cola's management be concerned? Discuss why or why not. In replies to peers, provide an example to support your position.
Upper Control Limit (UCLx). (3 marks) Lower Control Limit (LCLx). (3 marks) Upper Control Limit (UCLR).
Upper Control Limit (UCLx). Lower Control Limit (LCLx). Upper Control Limit (UCLR).
a process in statistical control has a mean of .3119 and specification limit of .307 to...
a process in statistical control has a mean of .3119 and specification limit of .307 to .317. if the standard deviation of the process is .0013, what percent of the process output is expected to be below the specification limit?
Lower limit = Q1 – 1.5Å~IQR Upper limit = Q3 + 1.5Å~IQR IQR = Q3 −...
Lower limit = Q1 – 1.5Å~IQR Upper limit = Q3 + 1.5Å~IQR IQR = Q3 − Q1 1. The manager of a local fast-food chain wants to improve the service provided to customers who use the drive-up window. As a first step in this process, the manager records how long it takes from the time the customer first enters the drive-in window until they are served their food at the final window. Below are the times (in minutes) for the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT