In: Operations Management
Complete the Risk Register (yellow-colored columns) provided below based on the information given.
Staffs involved – Mr Shariff (Company’s Accountant), Ms Liza (Company’s Project Manager) and Mr Halim (Company’s Quality Assurance Control)
Mitigation/Contingency Plan that can be applied (select the BEST plan for each risk):
| 
 Risk ID  | 
 Risk Description  | 
 Probabi-lity  | 
 Rating  | 
 Effect on Cost/ Schedule/Quality  | 
 Owner  | 
 Mitigation/ Contingency Plan  | 
| 
 1  | 
 Late submission of information, delays in document approval by the customer  | 
 Medium  | 
 High  | 
 Schedule  | 
||
| 
 2.  | 
 Incorrect or incomplete stated requirements  | 
 High  | 
 High  | 
 Cost, Schedule  | 
||
| 
 3.  | 
 Changes in the requirement during development  | 
 High  | 
 High  | 
 Cost, Schedule  | 
||
| 
 4  | 
 Problems with the delivery of the product into production because of the unavailability of servers.  | 
 High  | 
 Medium  | 
 Schedule  | 
||
| 
 5.  | 
 Problems of integration with internal systems of the customers  | 
 Medium  | 
 Medium  | 
 Cost, schedule, quality  | 
||
| 
 6.  | 
 Tight time limits that influence the testing flow  | 
 Medium  | 
 High  | 
 Cost, schedule, quality  | 
| Risk ID | Description | Owner | Mitigation Plan | Explanation | 
| 1 | Late submission of information, delays in document approval by the customer | Company’s Accountant | Scheduling of meetings and the provision of the necessary information in advance. | This plan allows preparation time to customer from submission and approval of documents | 
| 2 | Incorrect or incomplete stated requirements | Company's QA Control | Frequent demonstrations of new functionality | This plan allows us to take frequent feedback so that we don't work on the wrong requirements for long. | 
| 3 | Changes in the requirement during development | Project Manager | Splitting the development into short iterations. | This plan allows us to show our work and get it approved frequently so that we don't have to rework. | 
| 4 | Problems with the delivery of the product into production because of the unavailability of servers. | Company’s Accountant | Getting further details on installing the product from the Customer’s IT Department as soon as possible. | This plan allows us to be completely familiar with the Client's IT infrastructure to minimize potential delivery problems | 
| 5 | Problems of integration with internal systems of the customers | Company's QA Control | Install the beta version of the product and test the product in order to identify the problems associated with integration. | This plan allows us to run our work on a small scale to fix potential errors and avoid big problems | 
| 6 | Tight time limits that influence the testing flow | Project Manager | Following the development schedule. Timely notification of potential problems or shifts in the schedule. | It allows us with time to respond with mitigative measures which could be an increased workforce in case of delays. |