Question

In: Operations Management

Complete the Risk Register (yellow-colored columns) provided below based on the information given. Staffs involved –...

Complete the Risk Register (yellow-colored columns) provided below based on the information given.

Staffs involvedMr Shariff (Company’s Accountant), Ms Liza (Company’s Project Manager) and Mr Halim (Company’s Quality Assurance Control)

Mitigation/Contingency Plan that can be applied (select the BEST plan for each risk):

  • Splitting the development into short iterations.
  • Getting further details on installing the product from the Customer’s IT Department as soon as possible.
  • Following the development schedule. Timely notification of potential problems or shifts in the schedule.
  • Scheduling of meetings and the provision of the necessary information in advance.
  • Frequent demonstrations of new functionality.
  • Install the beta version of the product and test the product in order to identify the problems associated with integration.

Risk ID

Risk Description

Probabi-lity

Rating

Effect on Cost/ Schedule/Quality

Owner

Mitigation/

Contingency Plan

1

Late submission of information, delays in document approval by the customer

Medium

High

Schedule

2.

Incorrect or incomplete stated requirements

High

High

Cost, Schedule

3.

Changes in the requirement during development

High

High

Cost, Schedule

4

Problems with the delivery of the product into production because of the unavailability of servers.

High

Medium

Schedule

5.

Problems of integration with internal systems of the customers

Medium

Medium

Cost, schedule, quality

6.

Tight time limits that influence the testing flow

Medium

High

Cost, schedule, quality

Solutions

Expert Solution

Risk ID Description Owner Mitigation Plan Explanation
1 Late submission of information, delays in document approval by the customer Company’s Accountant Scheduling of meetings and the provision of the necessary information in advance. This plan allows preparation time to customer from submission and approval of documents
2 Incorrect or incomplete stated requirements Company's QA Control Frequent demonstrations of new functionality This plan allows us to take frequent feedback so that we don't work on the wrong requirements for long.
3 Changes in the requirement during development Project Manager Splitting the development into short iterations. This plan allows us to show our work and get it approved frequently so that we don't have to rework.
4 Problems with the delivery of the product into production because of the unavailability of servers. Company’s Accountant Getting further details on installing the product from the Customer’s IT Department as soon as possible. This plan allows us to be completely familiar with the Client's IT infrastructure to minimize potential delivery problems
5 Problems of integration with internal systems of the customers Company's QA Control Install the beta version of the product and test the product in order to identify the problems associated with integration. This plan allows us to run our work on a small scale to fix potential errors and avoid big problems
6 Tight time limits that influence the testing flow Project Manager Following the development schedule. Timely notification of potential problems or shifts in the schedule. It allows us with time to respond with mitigative measures which could be an increased workforce in case of delays.

Related Solutions

Fill in the yellow-colored columns by matching these scenarios with the right category (Tangible Benefit/Intangible Benefit/Tangible...
Fill in the yellow-colored columns by matching these scenarios with the right category (Tangible Benefit/Intangible Benefit/Tangible Cost/Intangible Cost). Explain why. No Scenarios Category Explanation 1 With the new system, it is expected of an increase of appointments to be filled at short notice. The expected increase in appointments made = 1 in 3 minutes = 200 slots = RM1000 per slot = RM200,000 Tangible Benefit 2 The system has allowed for nurses in reducing the need to do double data...
Complete a rapid assessment based on the scenario provided below, and provide a SBAR report to a classmate.
Complete a rapid assessment based on the scenario provided below, and provide a SBAR report to a classmate. Remember to include all concepts of patient safety, standard precautions, and professional standards. You are called to the room of 2-year-old Jonah by his mother who states the child has suddenly started breathing very loudly and does not look right. Upon entering the room you quickly recognize that the child is in respiratory distress as his lips are cyanotic and the use...
Please complete the weighted average information with the information provided. (Not all information provided may be...
Please complete the weighted average information with the information provided. (Not all information provided may be relevant in completing the question). Inventory Information Inventory on hand at the beginning of October: Units Cost / unit Total Cost Purchase # 1 15 60 $900 Purchase # 2 25 70 1,750 40 $2,650 October 2018 transactions related to buying and selling widget inventory 1-Oct Sold 30 widgets at $125 each on credit 3-Oct Purchased 60 widgets at a cost of $80 per...
Please complete the LIFO information with the information provided. (Not all information provided may be relevant...
Please complete the LIFO information with the information provided. (Not all information provided may be relevant in completing the question). Inventory Information Inventory on hand at the beginning of October: Units Cost / unit Total Cost Purchase # 1 15 60 $900 Purchase # 2 25 70 1,750 40 $2,650 October 2018 transactions related to buying and selling widget inventory 3-Oct Purchased 60 widgets at a cost of $80 per widget on credit 10-Oct Sold 45 widgets at $150 each...
Using the information given below draw and label a flowchart of the processes involved in production...
Using the information given below draw and label a flowchart of the processes involved in production of phthalic anhydride. Use boxes and/or other symbols to represent process units and lines with arrows to represent inputs and outputs. Indicate the process conditions. Phthalic anhydride (PA) is produced via partial oxidation of o-xylene using oxygen. The feed to the plant is o-xylene and air. Air is compressed to approximately 2 bar in a centrifugal compressor and heated to 360°C using high-pressure steam...
Based on the information provided below, estimate the income and expenditure and prepare a basic budget...
Based on the information provided below, estimate the income and expenditure and prepare a basic budget in the template provided. The Melbourne Football Club and the recreational centre has the following income and expenditure. Identify each item as income or expenditure and fill in the template provided to get total income and expenditure for the year. Assume one (1) season of the game per year. Sales: The number of opening hours per week: 14 The average sales per hour: $120...
Answer the following questions based on the information provided below: You are conducting a study to...
Answer the following questions based on the information provided below: You are conducting a study to determine the impact of a new reading intervention on students test scores. You randomly assign 40 students to either the intervention group or the control group (those not participating in the intervention). You also break the students into morning and afternoon classes to determine which is the best time of day to conduct the intervention. 1. What is the dependant variable? 2. What is/are...
Robert is considering an investment opportunity based on the information provided in the table below. Explain...
Robert is considering an investment opportunity based on the information provided in the table below. Explain the steps she has to undertake in order to earn a risk-free profit by engaging in a forward contract. USD 6-month risk free rate 2.45% EUR 6-month risk free rate 3.60% EUR/USD Spot exchange rate 1.1278 EUR/USD 6-month forward rate 1.1480
Please complete the October journal entries with the information provided. (Not all information provided may be...
Please complete the October journal entries with the information provided. (Not all information provided may be relevant in completing the question). Inventory Information Inventory on hand at the beginning of October: Units Cost / unit Total Cost Purchase # 1 15 60 $900 Purchase # 2 25 70 1,750 40 $2,650 October 2018 transactions related to buying and selling widget inventory 1-Oct Sold 30 widgets at $125 each on credit 3-Oct Purchased 60 widgets at a cost of $80 per...
Please complete a classified balance sheet with the information provided. (Not all information provided may be...
Please complete a classified balance sheet with the information provided. (Not all information provided may be relevant in completing the question). Inventory Information Inventory on hand at the beginning of October: Units Cost / unit Total Cost Purchase # 1 15 60 $900 Purchase # 2 25 70 1,750 40 $2,650 October 2018 transactions related to buying and selling widget inventory 1-Oct Sold 30 widgets at $125 each on credit 3-Oct Purchased 60 widgets at a cost of $80 per...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT