In: Accounting
Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production of 105,000 gallons of paint in July and completes 82,000 gallons. The costs of the resources used by Sanchez in July consist of the following:
Materials | $ | 286,444 |
Conversion costs (labor and overhead) | 286,100 | |
Required:
The production supervisor estimates that the ending work-in-process is 88 percent complete. Compute the cost of paint transferred to finished goods and the amount in work-in-process ending inventory as of July 31. (Do not round intermediate calculations.)
Answer:
Cost transferred to Finished Goods=$453,161.1739
WIP Ending=$119,382.8261
Calculation:
If helpful, Thumbs UP please:)