In: Economics
Answer:
Given that:
You operate you own building company and have decide to bid on a government contract to build a pedestrian walk way in a national park during the coming winter.
A)
Total allocated cost for the project =440,000
Incremental cost=268,000
Let's say we add 79% to incremental costs
So,
Allocated cost estimate-79%*440000-347600
So,
The price would be=(347600+268000)-615600
B)
To maximize the expected value of contribution,the difference between allocation cost and incremental cost should be maximum.
So,we should add minimum to the incremental cost i.e
61% of 440000-268400
So,
Price-268400+268000-536400
C)
Since between 60% and 80% is added in the incremental value,so the bid price will be calculated at the maximum rate which would be 79%.
Similarly we could add minimum ratio i.e 61% to maximize the expected value of contribution .
Expected value basically is the difference between the gross revenue and material cost.But since only the incremental and allocated value is given ,so we can use expected ration to calculate the price.