In: Operations Management
The partially completed inventory record for the driveshaft subassembly in the table below shows gross? requirements, scheduled? receipts, lead? time, and current? on-hand inventory.
a. Complete the last three rows of the record for an FOQ of
50
units. ?(Enter your responses as integers. A response of? "0" is equivalent to being not? applicable.)
?Item: Driveshaft subassembly |
Lot? Size:
FOQequals=50 units |
||||||||
Lead? Time: 3 weeks |
|||||||||
Week |
|||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
||
Gross requirements |
30 |
25 |
20 |
15 |
30 |
30 |
50 |
50 |
|
Scheduled receipts |
75 |
||||||||
Projected? on-hand inventory |
10 |
||||||||
Planned receipts b. Complete the last three rows of the record by using the L4L? lot-sizing rule. c. Complete the last three rows of the record by using the POQ? lot-sizing rule, with Pequals=4. |
Please find below filled up MRP table for both L4L as well as POQ rule.
For L4L:
Projected on hand inventory for period t = Projected on hand inventory for period t-1 + Scheduled receipt for period t – Gross requirement for period t( Provided Projected on hand inventory for period t > = 0)
In case Projected on hand inventory for period t <0as per above calculation , in such case:
Planned order receipt for period t = Gross requirement for period t – Scheduled receipt for period t – Projected on hand inventory for period t-1
Lot sizing rule = L4L
Driveshaft subassembly |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Gross requirement |
30 |
25 |
20 |
15 |
30 |
30 |
50 |
50 |
Scheduled receipt |
75 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Projected on hand inventory: 10 |
55 |
30 |
10 |
0 |
0 |
0 |
0 |
0 |
Planned order receipt |
0 |
0 |
0 |
5 |
30 |
30 |
50 |
50 |
For POQ ( period order quantity ) = 4 :
Calculation for Projected on hand inventory for period t = same as above In case Projected on hand inventory for period t <0as per above calculation , in such case:
Planned order receipt for period t = Sum of gross requirements for periods ( t, t+1 , t+2 , t+3 ) – Scheduled receipt for period t – Projected on hand inventory for period t-1
Lot sizing rule =POQ of 4
Driveshaft subassembly |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
Gross requirement |
30 |
25 |
20 |
15 |
30 |
30 |
50 |
50 |
Scheduled receipt |
75 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Projected on hand inventory: 10 |
50 |
30 |
10 |
110 |
80 |
50 |
0 |
0 |
Planned order receipt |
0 |
0 |
0 |
115 |
0 |
0 |
0 |
50 |